This document is a Contract Amendment (Standard Form 30) for Solicitation 36C26026R0013, pertaining to the renovation of Building T111 at the Boise VA Medical Center. The amendment, issued by the VA Network Contracting Office (NCO 20), provides an additional site visit date on October 22, 2025, and includes responses to prospective offerors' questions. Key clarifications include confirmation that no full Past Performance Questionnaires (PPQs) are required, past performance must be from the prime contractor, and projects must be completed within the past five years, with completed defined as customer acceptance or 100% completion.

The solicitation involves a full building renovation project for the Department of Veterans Affairs, with the site located in Boise. The amendment maintains the original submission dates and provides guidance on technical expertise and past performance submissions. Offerors are instructed to submit project examples as prime contractors, with past performance examples potentially being considered even under the $1M threshold. An additional site visit will be held at 8:00am MT in building 50's conference room, with the previous site visit roster from October 15, 2025, also attached to the amendment.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

10-16-2025

531-24-101 NCO 20 Network Contracting Office

ATTN: V4CONT

1601 E. Fourth Plain Blvd Bldg.17, Suite B428 Vancouver WA 98661

NCO 20 Network Contracting Office

ATTN: V4CONT

1601 E. Fourth Plain Blvd Bldg.17, Suite B428 Vancouver WA 98661 To all Offerors/Bidders

36C26026R0013 10-09-2025

X

The purpose of this amendment is to publish an additional site visit date, provide the site visit roster from 10.15.25 and to provide VA's responses to questions/RFIs received to-date from prospective offerors.

An additional site visit will be held on Wednesday, October 22, 2025 at 8:00am MT, meet inside building 50 conference room.

Please see attached site visit roster from 10.15.25 and responses to RFIs received to date.

There is no change to the RFI submission date or the proposal due date.

-------------------------------------------------SEE CONTINUATION PAGE--------------------------------------------------

Stephen Slaby

Solicitation 36C26026R0013, Amendment 0001 Renovate Building T111, Boise VA Medical Center VA Project Number: 531‐24-101

Questions/RFIs and VA Responses

1. We noted that Exhibit A, included in the solicitation package is only one page, and does not call for client contact information, only offeror and contract information. Can the Government confirm that this is the complete form, and that no other reference or evaluation information is required?

VA Response: The solicitation form is the complete form. Offerors shall input client contact information into the following blocks: Point of Contact (POC), POC Phone Number, Email.

2. Can the Government please confirm that no full PPQs are required.

VA Response: Confirmed, no full PPQs are required.

3. If PPQs are required, is it acceptable to submit previously completed PPQs from past submissions?

VA Response: PPQs are not required. It is acceptable to submit other past performance utilizing completed PPQs from past submissions.

4. Can the Government please clarify whether past performance examples must be from the offeror acting as a Prime Contractor, or if the offeror’s relevant experience as subcontractor will also be considered?

VA Response: Offeror past performance shall be completed as the prime contractor.

5. Do projects presented for Technical Expertise and Past Performance need to be complete, or can they be ongoing and substantially complete (at least 50%)?

VA Response: Under Factor 1, Technical Expertise, Projects submitted shall be completed within the past five (5) years of the date of issuance of this RFP for full building renovation projects. Completed is considered as customer acceptance of the project as either beneficial occupancy or 100% complete. If offerors submit projects as beneficial occupancy (for completion) they shall so annotate so that it is evident to evaluators.

6. Will the Government consider past performance examples from proposed subcontractors or team members, including those under an SBA-approved Mentor-Protégé Agreement, provided the projects meet the stated relevance criteria (e.g., scope, complexity, dollar value)?

VA Response: Offeror past performance shall be completed as the prime contractor.

7. If subcontractor or Mentor-Protégé past performance is permitted, is a Subcontractor Consent Form or Letter of Commitment required at the time of proposal submission? If so, is there a specific format or template the Government prefers?

VA Response: Offeror past performance shall be completed as the prime contractor.

8. For projects performed by subcontractors or Mentor-Protégé entities, are there any specific labeling or formatting expectations (e.g., identification of prime vs. sub role, duration of involvement, or dollar share) the Government requires within the Experience or Past Performance sections?

VA Response: No.

9. Will the Government consider and evaluate past performance examples under the $1M threshold?

VA Response: The Government will consider and evaluate past performance examples under the $1M threshold in accordance with the solicitation.

ATTACHMENTS

See attached document: 36C26026R0013 SiteVisit Roster 15OCT2025.

36C26026R0013 Amendment 0001