This document is an Amendment to a Request for Quotation (RFQ) for portable fire extinguisher maintenance services issued by the VA Puget Sound Health Care System. The solicitation (36C26026Q0168) seeks comprehensive maintenance for approximately 1,500 portable fire extinguishers across three campuses: Seattle VA Medical Center, American Lake VA campus, and Magnolia Facility. The acquisition is set-aside exclusively for Service Disabled Veteran Owned Small Businesses (SDVOSB), with an estimated response deadline extended to 12/16/2025.
The amendment includes nine detailed questions and answers addressing specific maintenance requirements, such as inventory management, inspection schedules, replacement protocols, and security onboarding procedures. Key technical details include annual inspections due in June (American Lake) and July (Seattle and Ft. Lawton/Magnolia), mandatory new replacement fire extinguishers for 12-year maintenance, and a requirement for favorable security background investigations for contractor employees. The Statement of Work was updated to clarify replacement schedules, deficiency reporting, and repair cost handling, with provisions for potential contract modifications if unexpected maintenance needs arise.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Seattle Annual Insp Doc.PDF | ||
| American Lake Annual Insp Doc.PDF | ||
| FT. Lawton_Magnolia Annual Insp Doc.PDF | ||
| S02 36C26026Q0168_1.docx | DOCX document | |
| S02 36C26026Q0168.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
12-11-2026
36C260 NCO 20 Network Contracting Office
ATTN: V4CONT
1601 E. Fourth Plain Blvd Bldg.17, Suite B428 Vancouver WA 98661
36C260 NCO 20 Network Contracting Office
ATTN: V4CONT
1601 E. Fourth Plain Blvd Bldg.17, Suite B428 Vancouver WA 98661 To all Offerors/Bidders
36C26026Q0168
X
1. The purpose of this Amendment is to provide Questions and Answers received in response to this solicitation.
2. Questions and Answers (Q&A) 1-9 and edits to the RFQ Statement of Work are provided below.
3. Attachments 1-3 regarding campus inspections are provided below.
4. Ensure to acknowledge this Amendment as part of your quote submission.
5. There are no other changes.
Danielle Carrico Contracting Officer
Questions & Answers (Q&A)
Q1. Section 4.0 of the Statement of Work states the VA will provide a current inventory list of all portable fire extinguishers. Can you please share this with the offerors so we can understand the size, type, location, etc. for each fire extinguisher? This will help ensure all offerors are quoting against the same scope of work.
A1. Yes, a current inventory has been provided, as requested. See Attachments 1-3. (For awareness: Based on recent inspections, we have found the number of extinguishers exceeds code requirements, so the current number will be reduced over time and locations adjusted as necessary. These reductions and/or relocations will be communicated to ensure current inspection inventory and documentation records).
Q2. If the current inventory list or historical documentation such as previous inspection reports cannot be shared, can you please provide a breakdown of the fire extinguisher quantities for each type (ABC, Water, Halotron, Class K, MRI, etc) and size?
A2. See A1.
Q3. Which month are annual inspections due, or when was the most recent annual inspection completed?
a. Are all campuses/buildings due for annual inspections at the same time or vary by location throughout the year?
| A3. Annual Inspection for the American Lake campus is due every June. |
| Annual Inspection for Seattle and Ft. Lawton/Magnolia are due every July. |
Q4. Regarding the 5-year/6-year/12-year maintenance services, can you provide a 5-year maintenance schedule, so we have some guidance on how to include pricing for these services each year in our quote?
a. Alternatively, if this information is not available, would you consider reserving a CLIN in the Price/Cost Schedule to allow offerors to provide unit pricing for each maintenance service to be used in the evaluation of our pricing?
b. Or, provide a maintenance service CLIN with a not to exceed limit which these services can be invoiced against?
A4. The inventory sheet shows when these services are due. See Attachments 1-3 and updated SOW which clarifies when repairs and cost of replacement is included or requires a potential modification.
Q5. For the 12-year maintenance swap out program, we would like to clarify if the replacement fire extinguishers must be out of the box new, or can be refurbished, in good working condition, properly tagged, and ready for service?
A5. Replacement extinguishers must be “out of the box new”.
Q6. For the 12-year maintenance swap out program, are we required to return the original fire extinguisher to the VA and take back the replacement we provided once we have completed the hydrostatic testing on the original fire extinguisher we removed from the VA? Or does the VA keep the replacement unit, and we keep the VA’s original extinguisher?
A6. If the maintenance cost exceeds the cost of replacement, we will proceed with replacement. If the maintenance cost doesn’t exceed the cost of replacement, then we expect the original extinguisher to be returned.
Q7. Is there a specific inspection reporting software such as building reports or something similar used to document inspection results or is it tracked through an inventory spreadsheet or other electronic document format?
A7. Reporting software may cause an issue with our ability to use it due to strict IT requirements, unless you’re able to send us copies of the reports and they meet NFPA 10 reporting requirements. Open to discuss further as necessary.
Q8. Section 3.6 states we are to correct any deficiencies identified during services.
As much as we can predict routine maintenance needs and component replacements, it’s just as difficult to predict issues not related to maintenance that could have a material impact to the contract value. Would you consider reserving a CLIN in the Price/Cost Schedule for repair services to be billed against as needed? This would ensure the government only spends the necessary money on repairs instead of paying for the services whether they are needed or not.
A8. See updated SOW which clarifies when repairs and cost of replacement is included or requires a potential modification.
Q9. Will an escort be required for this work or will we be provided badges and keys to access all spaces?
a. If an escort is required, how many escorts will be provided? If we provided 2 inspectors, will 2 escorts be provided by the VA?
A9. See updated SOW which provides process on security background/onboarding as well as escorts when required. Number of VA provided escorts will be identified on a case by case basis.
Changes to RFQ 36C26026Q0168 Statement of Work Redline Edits to Section 3.5 Removal and replacement The contractor shall identify and remove all old, obsolete, or non-compliant fire extinguishers in accordance with Seattle, American Lake and Fort Lawton six year replacement schedule (see Attachments 1-3). All fire extinguishers that are due for replacement with known due dates per the replacement schedule shall be included in existing price schedule and are not to be separately billed. However, fire extinguishers that fail before the known due date of replacement due to damage or failure of inspection and testing, and need to be replaced fully may be modified into the contract after evaluation and approval by the contracting officer. The modification will be mutually agreed by the contractor and the contracting officer.
Any replaced fire extinguisher shall meet the below criteria:
Redline Edits to Section 3.6 Deficiencies and Repairs The contractor shall report, and repair all discovered minor deficiencies. Minor deficiencies are defined as minor repairs such as replacement of hoses, gauges, seals and refill of existing fire extinguishers. Cost of Minor deficiencies shall be included in the existing price schedule and are not to be separately billed. The Government estimates approximately five instances of minor repairs per year, but this is no guarantee of work or ceiling limits.
New Section 10. Onboarding and Security Requirements with Vendor Visits to Campus
10. Onboarding and Security Requirements for Vendor Visits to Campus A. Favorable adjudication from a successful security background investigation is required and may take approximately 4-6 weeks on average (possibly more or less) depending on the candidates progress and how quickly and correctly all steps within this section are followed. If inspections are due before a candidate is fully adjudicated, then inspectors will be required to obtain VA escorts before proceeding with work. It is the responsibility of the contractor to coordinate in advance if any escorts are required. This does not remove the requirement to obtain favorable adjudication, and contractor shall ensure candidates are working towards favorable adjudication in a prompt and expedited manner.
B. Contractor employees 4). The COR or Government POC will assist the Contractor throughout this process and Contractor must work diligently to complete the onboarding documents. FORMS MUST BE LEGIBLE.
C. After onboarding documents are completed, COR or Government POC will schedule fingerprinting appointment. Fingerprints must be submitted by Contractor employees at any Veterans Affairs Medical Center (VAMC) with a PIV enrollment. In Seattle, the following VAMC location conducts fingerprinting:
Seattle VAMC, Building 7, 1660 S. Columbian Way, Seattle, WA 98108 D. Contractor employees must complete Background Investigation prior to performing in any capacity on VA property.
E. All Contractor employees are subject to the same level of investigation as VA employees who have routine access to VA Facilities. The level of background investigation commensurate with the level of access needed to perform the PWS is Tier 1. All Contractor employees shall be required to complete at least a National Agency Check with Inquiries (NACI) prior to beginning services.
See attached document: Attachment 1 Seattle Annual Insp Doc.
See attached document: Attachment 2 American Lake Annual Insp Doc.
See attached document: Attachment 3 FT. Lawton_Magnolia Annual Insp.