36C26026Q0104 0002.docx
DOCX document 123 KB Posted
- Attached to
- UPS Battery Replacement & Installation Services, QTY2EA Federal contract opportunity
- Solicitation number
- 36C26026Q0104
About this file
This document is an Amendment to Solicitation 36C26026Q0104 for UPS Battery Replacement and Installation Services at the VA Puget Sound Health Care System in Seattle, Washington. The solicitation is a Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside under NAICS code 238210, with a small business size standard of $19 million. The requirement involves procuring and installing two UPS battery systems, with specific technical evaluation criteria including electrical trade certifications, product literature submission, and technical conformance to specifications.
Key details include a question and answer section addressing site-specific installation logistics such as loading dock access, equipment staging, battery transport routes, and installation requirements. The solicitation deadline is December 17, 2025, at 15:00 PM Pacific Time, with questions accepted until December 10, 2025. Offerors must submit quotes via email to derek.crockett@va.gov, including proof of NETA or similar electrical certifications, detailed product documentation, and demonstrate technical capabilities for battery replacement in a first-floor electrical room with approximately 50 feet of transport distance from the loading dock.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment A- Photos .docx | DOCX document | |
| 36C26026Q0104 0001.pdf | ||
| SCA WAGE DETERMINATIONS KING COUNTY WA..docx | DOCX document | |
| 36C26026Q0104.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
12-17-2025
None 36C260 Network Contracting Office 20
ATTN: V4CONT
1601 E. Fourth Plain Blvd Bldg.17, Suite B428 Vancouver WA 98661
To all Offerors/Bidders
36C26026Q0104 12-04-2025
X
The purpose of this amendment is to answer industry questions and add a new attachment.
1.) Attachment A - Battery Photos is hereby added as an attachment.
2.) All other terms and conditions remain the same.
See contiuation for industry questions and government responses and new attachement; Attachment A - Battery Photos
Derek Crockett
1.) Are there any stairs or ladders to climb up or down to perform work and or transport batteries?
No, there are none.
2.) Is there a loading dock available and what is an estimated distance from facility entrance to battery change out area?
Yes, an estimated 50 feet.
3.) Is there an elevator that requires a breakdown of each battery pallet before reaching the change out area?
No, there is no elevator.
4.) Are there any narrow doorways or hallways (or heavy carpeting) or raised/access floor to transit that would require breakdown of each battery pallet before reaching the change out area?
Electrical Closet has a narrow door way.
5.) Is there a battery monitoring system to dis-engage and re-engage and test before job completion?
There is no external Battery Monitoring System(s) in place.
6.) Is there a forklift, pallet-jack, or carts available to use?
No government equipment of GFE is available for contractor use.
7.) Does the XPL5700FR battery have the Eaton or CSB label on it?
CSB
8.) Can we offer the CSB label for both the PWHR2200W4FR & XPL5700FR?
Technical Conformance to the Specifications is one evaluation factor. Eligible offerors and quotes conforming to the submission requirements will be evaluated based on the salient characteristics and technical specifications submitted of all equipment quoted and the submission of electrical trade certifications as outlined in section E.8 Quote Submission Requirements.
9.) Is an external Battery Monitoring System(s) in place? If so, what are the specifications/ manufacturer and what scope would be required of the bidder to reinstall and commission.
There is no external Battery Monitoring System(s) in place.
10.) Is there documentation that gives visibility into the footprint with which to receive/stage new batteries and salvage old batteries from the site?
See new attachment, Attachment A – Photos.
11.) Can a site visit be arranged to assess access routes, equipment staging areas, and battery cabinet locations within Building 1?
There is no site visit schedule for this requirement. See new attachment, Attachment A – Photos.
12.) Where exactly are the two UPS systems and battery cabinets located within the building (e.g., first level, basement, electrical room, or roof)?
1st Floor, electrical room.
13.) Are stairs or elevators required to access the UPS rooms? If elevators are available, what is the weight capacity?
No, there are no stairs or elevators required to access the UPS rooms.
14.) Are double access doors available along the transport path for safe movement of battery pallets and equipment?
Yes, except for the electrical room.
15.) Is there a loading dock or ramp onsite for receiving the new batteries and staging removal of depleted units?
Yes, there is a loading dock and ramp onsite.
16.) What floor are the UPS units located on, and what type of access is available to them?
1st floor/doors and loading dock access available.
17.) What is the approximate distance from the nearest loading area (building entrance, elevator, or door) to the UPS locations?
Estimated 50 ft.
18.) Will we be required to use stairs to move any of the equipment through the Seattle VAMC?
No, it is on the 1st floor.
19.) Do we need to provide floor protection in any areas while moving equipment and parts?
Yes, the contractor must protect government buildings, equipment, and personnel in performance of this contract. As well as adhere to the general standards outlined in the RFQ and statement of work.
20.) Is there a loading dock available for a normal-sized trailer to utilize for shipment?
Yes, there is a loading dock available for a normal-sized trailer and for shipment. This requirement is FOB destination.
21.) Are designated staging/storage areas available for the replacement batteries and the old batteries?
No, there are no storage areas available for the replacement of the batteries and the old batteries. The contractor is responsible for all equipment under this requirement until final government receipt and acceptance in accordance with the statement of work.
22.) When will the decision be made regarding the necessity of after-hours installation?
As outlined in the RFQ and statement of work, “Before onsite performance and installation, the contractor shall submit a project schedule to the VA COR outlining the proposed installation dates and times for review and approval.”
All onsite project schedules, schedule changes, and expected outages shall be submitted by the contractor and approved in writing at least two weeks in advance by the VA COR.
The contractor shall perform onsite services during Normal duty hours, Monday through Friday from 0700-1630 Pacific Standard Time.
23.) In the RFP on Page 11 of 63 it states “Contractors shall be certified by the InterNational Electrical Testing Association (NETA) or similar accredited association such as NETA Certified Technician and completed the Occupational Safety & Health Administration (OSHA) approved 10-hour construction safety training” Is a Washington State Electrical required to submit this proposal? We have performed projects with battery replacement and have not been required to have an electrical license.
Offerors will be evaluated on technical capabilities to make a best value determination as outlined in the RFQ terms and conditions.
Offerors should submit proof of Offerors must submit proof of employees or personnel with active electrical certifications by the InterNational Electrical Testing Association (NETA) or similar accredited association such as NETA Certified Technician.
B. Technical Conformance to the Specifications- Offerors must submit the following documentation:
1.) Offerors must submit all product literature, technical data sheets, and warranty information for all UPS batteries quoted. Note: It is not the government’s responsibility to obtain additional product information to verify if any alternative product quoted meets the salient characteristics and the technical requirements.
2.) Offerors must submit proof of employees or personnel with active electrical certifications by the InterNational Electrical Testing Association (NETA) or similar accredited association such as NETA Certified Technician.
22. is a certified and/or union electrician is required to be involved in the replacement? Is it necessary to pull permits?
Please see response above for certification requirements and how offerors will be evaluated. Pulling permits is not required.