36C26025R0070 0001.pdf
PDF 142 KB Posted
- Solicitation number
- 36C26025R0070
About this file
This document is an Amendment of Solicitation/Modification of Contract for VA Project 668-25-102, issued by the Network Contracting Office 20 in Vancouver, WA. The amendment provides answers to 10 technical questions submitted by potential offerors regarding a design and construction project at the Mann-Grandstaff VAMC in Spokane, WA. Key clarifications include: construction cost estimates between $1M-$2M, confirmation of key personnel requirements (Environmental Engineer, Fire Protection Engineer), and details about survey and geotechnical report availability. The geographic location of the firm will be evaluated based on driving distance from the VAMC, with mileage determined using Google Maps. The project involves replacing asphalt drywells and sidewalks, with potential impacts to existing buildings, and requires pre-construction surveys and infection control protocols.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2020 GAO High Quality Project Estimate Characteristics.xlsx | XLSX spreadsheet | |
| Design Review Comment Form.xlsx | XLSX spreadsheet | |
| Bldg 12 As-Built ARCH-STR.pdf | ||
| AE SOW 668-25-102 - Copy.docx | DOCX document | |
| PPQ 668-25-102.docx | DOCX document | |
| Bldg 12 As-Built MEP.pdf | ||
| Site Repair Replace Areas Rev 1.pdf | ||
| Presolicitation Notice - Request for SF 330s.pdf | ||
| 36C26025R0070.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE 7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO. 1. CONTRACT ID CODE
FACILITY CODE CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30 PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243
(Type or print) (Type or print)
(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code)
(If other than Item 6)
(Specify type of modification and authority)
(such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
1 3
0001 05-29-2025
668-25-102
36C260
Network Contracting Office 20
ATTN: V4CONT
1601 E. Fourth Plain Blvd Bldg.17, Suite B428 Vancouver WA 98661
36C260
Network Contracting Office 20
ATTN: V4CONT
1601 E. Fourth Plain Blvd Bldg.17, Suite B428 Vancouver WA 98661
To all Offerors/Bidders
36C26025R0070
05-07-2024
X
X X x
The purpose of this Amendment is to provide answers to timely questions received in response to the subject solicitation.
Please note the requirement for acknowledgement of this amendment in Box 11, including the methods to acknowledge which are listed in Box 11 (a)-(c).
1. Questions: Statement of Work, PN 668-25-102, June 12, 2024. Page 1.
The magnitude for construction is between $5M-$10M, based on the scope of work and our experience with this type of work, we anticipate construction costs between $1M and $2M. Can you describe how you reached the VAAR magnitude for construction? Are there missing items from the scope?
Answer: All items for design are included within the Scope of Work (SOW) section 2.
2. Questions: Statement of Work, Page 1.
Building 1 & 12 are considered CRITICAL, but a Force Protection consultant isn’t listed in the Presolicitation Notice as a key position. Is a Force Protection consultant a key position? Should the Fire Protection Engineer position be Force Protection instead?
Answer: Key positions are listed in the Presoliciation Notice. Positions not list the notice were not considered key positions to this project. However, positions other than those listed as a key position may be required.
3. Questions: Statement of Work, PN 668-25-102, June 12, 2024.
Paragraph 3.10 references HAZMAT (lead, asbestos, PCB, mold, etc) surveys required prior to construction. As none of the work is indoors, it seems unlikely that HAZMAT will be encountered. Is the VA aware of existing HAZMAT that will be encountered?
Answer: Pre-construction surveys are required. Portions of this SOW impact or have the ability to impact existing building depending on design.
4. Questions: Statement of Work, PN 668-25-102, June 12, 2024.
Paragraph 4.3 lists many items that don’t appear to be applicable to this project, for example, 4.3.5. “Floor plans showing doors, windows, interior partitions…” Please confirm only applicable sections of 4.3 will be required and confirmed during the negotiation phase of the selection process. Are there items missing from the Statement of Work that would require these submittals?
Answer: Items not applicable to the design of this project are not required, e.g. floor plans, reflected ceiling plans, furniture plans.
5. Questions: Presolicitation Notice, page 6, list required resumes for key positions. The list includes an Environmental Engineer. Can you describe the scope of anticipated work for an EE? We are a civil firm and can design stormwater utilities to meet federal and WA state requirements. Is the VA aware of critical areas on the campus or other features that would require an Environmental Engineer?
Answer: Environmental Engineer is a key position as indicated by the Presolicitation Notice. Review PG-18-15 Minimum Requirements for A/E Submissions.
6. Questions: Presolicitation Notice, page 6, list required resumes for key positions. The list includes a Fire Protection Engineer. Can you describe the scope of anticipated work for an FPE?
Answer: Design dependent, review SOW. SOW item(s) have potential to impact building(s).
7. Questions: Presolicitation Notice, page 6, references “construction infection control protocols,” as none of this work is interior to a building, can you describe the anticipated ICRA requirements?
Answer: Design dependent, review SOW. SOW item(s) have potential to impact building interior(s).
8. Questions: Presolicitation Notice, page 9-10, Geographic location is listed as a secondary criterion. Can primes get credit for lead subconsultants (civil) being located in Spokane?
Answer: Reference Secondary Selection Criterion per Presoliciation Notice:
a Geographic location.
Location of the firm, as measured by the driving distance (miles) between the Offeror’s principal business location and the Mann-Grandstaff VAMC, 4815 N Assembly St, Spokane, WA. Determination of the mileage will be based on Google Maps. (https://www.google.com/maps/dir/).
9. Questions: Does the VA have any survey reports in CAD of the subject areas?
Answer: The VA does not have any recent survey report in CAD of the subject areas.
10. Questions: Does the VA have any geotechnical reports in the vicinity of parking lot K and buildings 14 and 17?
Answer: There are no available geotechnical reports in the vicinity of parking lot K or Building 14 and 17.
File details come from the government source that posted it. Updated .