This document is an amendment to a solicitation (Solicitation Number: 36C26024R0054) for Architect-Engineering (A-E) services for preliminary concept and program development, investigative services, design, and construction period services for Project #668-24-102, Replace Windows Building 1 at the Mann-Grandstaff VA Medical Center in Spokane, Washington.

The amendment provides answers to questions received from potential offerors. Key details include: the definition of "recent projects" as those where services were provided within 5 years of the solicitation closing date, the page limits for narrative submissions, confirmation that CPARS are not required with the SF330 submission, and clarification on the "Physical Security" position. The contract is a 100% set-aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSBs), with an anticipated award in June 2024 and a 205-calendar day period of performance for design completion. The NAICS code is 541310 Architectural Services with a $12.5M small business size standard. The magnitude of construction is between $5-10 million.

View the file

Other files

File Type Posted
668-24-102_AE SOW_Attachment A.pdf PDF
668-24-102_AE SOW V3-1.pdf PDF
668-24-102_AE SOW_Attachment B.pdf PDF
668-24-102_AE SOW_Attachment E.xlsx XLSX spreadsheet
36C26024R0054.docx DOCX document
668-24-102_AE SOW_Attachment C.docx DOCX document
668-24-102_AE SOW_Attachment D.xlsx XLSX spreadsheet
PPQ 668-24-102.docx DOCX document
668-24-102 A-E Presolicitation 02.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODECODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

1 2

0001 668-24-102

36C260

Network Contracting Office 20

ATTN: V4CONT

1601 E. Fourth Plain Blvd Bldg.17, Suite B428 Vancouver WA 98661

To all Offerors/Bidders

36C26024R0054

04-16-2024

X x x x 1

The purpose of this Amendment is to provide answers to timely questions received in response to the subject solicitation.

Susan Howe Contracting Officer

36C26024R0054

1. Question: Selection Criteria 2 – Specialized Experience and Technical Competence defines recent projects as those where services were provided in the 5 years prior to the closing date of this solicitation. Please advise if “services” include construction phase services or only design services?

Answer: “Services” as referenced in this statement refer to both design and construction period services. If the entirety of the A/E services, including construction period services, ended within five years of the closing date of this solicitation, it is considered recent.

2. Question: Selection Criteria 2 –Specialized Experience and Technical Competence states that “narratives submitted in Section H of the 330 shall not exceed one (1) page in length for the Offeror and each key consultant,” while allowing 10 pages total for this criterion (this Criterion includes sections F, G & H). Does this mean the 10-page limit applies to Section F + G + the Specialized Experience narrative in Section H? Does the 1-page limit apply to each Section H narrative topic (1 page for management approach, 1 page for coordination of disciplines/subcontractors, etc.) or is it 1 page combined?

Answer: The 10 pages total limit applies to the narrative submissions in total. The 1 page limit applies to the Offeror and each key consultant; for example, if there is one offeror and two key consultants, each individual could use one page for their narrative for a total of 3 pages.

3. Question: Selection Criteria 3 – Past Performance states that the CPARS database will be reviewed to evaluate the projects and requires PPQs to be submitted for any project that does not have CPARS. Can you please confirm that CPARS are NOT required to be submitted with the SF330?

Answer: Correct, CPARS are not required to be submitted with SF330 submission.

However, as stated in the notice, the contract number must be included for all projects provided in Section F so CPARS can be reviewed in the database.

4. Question: Under Selection Criteria 1, Professional Qualifications, it requests a resume for each of the key positions, including Physical Security. Can you please provide clarification on what is meant by the “Physical Security” position?

Answer: The Physical Security position is held by somebody who provides technical support with the design and implementation of physical security requirements (such as those outlined PG-18-10) for components of the project where additional security beyond standard measures is required.

2024-04-16T15:31:22-0700
SUSAN HOWE