This document is a solicitation for a construction project to upgrade 24 Housekeeping Aid Closets (HACs) at the Sheridan, Wyoming Veterans Affairs Medical Center (VAMC). The work includes installing tepid, plumbed emergency eyewashes in the HACs, as well as electrical, plumbing, and finish upgrades. The project is set-aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSBs) and has an estimated value between $500,000 and $1,000,000. Proposals are due by September 6, 2024. The contract performance period is 122 calendar days from the notice to proceed. Bidders must be verified as SDVOSBs by the Small Business Administration prior to award. The evaluation will consider past performance and price using a tradeoff process. Timothy Verburgt is the Contracting Specialist, and Jennifer Crecelius and Rodney Lindberg are the Contracting Officer's Representatives.

View the file

Other files

File Type Posted
36C25924R0121 0004.docx DOCX document
S04 - Site Visit - Sign-In Sheet - Correction from Amend 2.pdf PDF
S05 - RFI Responses from Site Visit - 2nd Set - FE.docx DOCX document
36C25924R0121 0003.docx DOCX document
36C25924R0121 0002.docx DOCX document
S05 - RFI Responses - FE.docx DOCX document
36C25924R0121 0001.docx DOCX document
S04 - Site Visit Meeting Doc.docx DOCX document
S04 - Site Visit Attendance - FE.docx DOCX document
S02 - Drawings.pdf PDF
S02 - ICRA NON-Patient Care Areas.pdf PDF
S02 - ICRA Patient Care Areas.pdf PDF
S02 - Construction Safety Handout.pdf PDF
S02 - Specs.pdf PDF
S22 - LOS - Attachment - 852.219-75 Blank.docx DOCX document
S02 - Lockout-Tagout Program.pdf PDF
S02 - FMS Safety Plan 2023.pdf PDF
PPQ Blank - Past Performance Questionnaire.docx DOCX document
Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. SOLICITATION NUMBER

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

6. PROJECT NUMBER

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

a. NAME

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)

STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES

NO

a.

Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b.

An offer guarantee is, is not required.

c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

36C25924R0121 X 08-06-2024 666-22-107 36C259 Department of Veterans Affairs Network Contracting Office

NCO 19

6162 South Willow Drive, Suite 300 Greenwood Village CO 80111 Timothy Verburgt Timothy.Verburgt@va.gov

Timothy Verburgt 303-712-5707 The contractor shall furnish all labor, equipment, materials, and supervision to complete Upgrades to 24 existing Housekeeping Aid Closets (HACs) including tepid and plumbed emergency eyewashes installed along with addressing electrical receptacles, lighting upgrades, plumbing work, fixtures, storage / shelfing additions, Fiberglass Reinforced Paneling (FRP), and finishing work at the Sheridan Veterans Affairs Medical Center (VAMC) located at 1898 Fort Road, Sheridan, Wyoming 82801.

Project magnitude: between $500,000 and $1,000,000. The NAICS code is 236220 - Small Business size standard is $45 M.

A site visit will be held on at 08-13-24 at 2 PM (MT) Please meet at Building 5 Room 219 (Conference Room.)

at the Sheridan VAMC. Leading the site visit will be Jennifer Crecelius .

All Questions in relation to this solicitation must be submitted in writing via e-mail to Timothy.Verburgt@va.gov and received no later than 08-20-24 at 2:00 PM. Mountain Time (MT).

Proposals Shall be submitted via e-mail in accordance with Part I / Section B, to be considered for this project.

Proposals received in any other format will result in the offeror's proposal not receiving further consideration.

In accordance with P.L. 116-283, this acquisition is 100% set-aside for Service-Disabled Veteran Owned Small Business Concerns. See VAAR 852.219-73, VA Notice of Total Set-Aside for Verified Service-Disabled Veteran-Owned Small Business For information in regard to requirements in order to be considered. Offerors must be both VISIBLE and VERIFIED by The Small Business Administration (SBA) prior to proposal receipt. Failure to be both VERIFIED, and VISIBLE by the SBA Prior to contract award will result in the offerors proposal being deemed non-compliant. ALL offerors are urged to Contact the SBA and submit the aforementioned required documents to obtain SBA (VetCert) verification of their SDVOSB Status if they have not already done so.

Proposals shall be submitted via email to Timothy.Verburgt@va.gov by 09-06-2024 at 2:00 PM MT.

The Government’s obligation under this contract is contingent upon the availability of appropriated funds from which payment for contract purposes can be made. No legal liability on the part of the Government for any payment may arise until funds are made available to the Contracting Officer for this contract and until the Contractor receives notice of such availability, to be confirmed in writing by the Contracting Officer.

X X 52.211-10 X

2PM

MDT

09-06-2024 X

14. NAME AND ADDRESS OF OFFEROR

15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (

26. ADMINISTERED BY

27. PAYMENT WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

36C259 Department of Veterans Affairs Network Contracting Office

NCO 19

6162 South Willow Drive, Suite 300 Greenwood Village CO 80111 Department of Veterans Affairs Financial Service Center PO Box 149971 Austin TX 78714-9971

Table of Contents

PART I - THE SCHEDULE1
SECTION A - SOLICITATION/CONTRACT FORM1
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)1
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK2
A.3 PRICE/COST SCHEDULE5
ITEM INFORMATION5
A.4 Statement of Work6
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS10
2.1 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)17
2.2 52.216-1 TYPE OF CONTRACT (APR 1984)18
2.3 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014)18
2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)19
2.5 52.233-2 SERVICE OF PROTEST (SEP 2006)20
2.6 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)20
2.7 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)21
2.8 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018)21
2.9 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)22
REPRESENTATIONS AND CERTIFICATIONS23
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAY 2024)23
3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)27
3.3 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—CERTIFICATION (NOV 2021)29
GENERAL CONDITIONS32
4.1 52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS (NOV 2021)32
4.2 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) ALTERNATE I (APR 1984)33
4.3 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (FEB 2024)34
4.4 52.223-20 AEROSOLS (MAY 2024)36
4.5 52.223-21 FOAMS (MAY 2024)37
4.6 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022)38
4.7 SUPPLEMENTAL INSURANCE REQUIREMENTS43
4.8 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)43
4.9 VAAR 852.201-70 CONTRACTING OFFICER'S REPRESENTATIVE (DEC 2022)46
4.10 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)46
4.11 VAAR 852.204-70 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL (MAY 2020)46
4.12 VAAR 852.204-71 INFORMATION AND INFORMATION SYSTEMS SECURITY (FEB 2023)47
4.13 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (JAN 2023) (DEVIATION)56
4.14 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (JAN 2023) (DEVIATION)59
4.15 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008)60
4.16 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009)60
4.17 VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (WITHOUT NAS– CPM) (NOV 2018)61
4.18 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)64
4.19 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019)65
4.20 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)66
4.21 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)66
4.22 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020)66
4.23 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019)68
4.24 Wage Determination69
4.25 List of Attachments75

A.3 PRICE/COST SCHEDULE

ITEM INFORMATION

ITEM NUMBER
DESCRIPTION OF SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
0.00
JB
__________________
__________________

666-22-107 - Install Emergency Eyewashes in HACs

Upgrades to 24 existing Housekeeping Aid Closets (HACs) including tepid and plumbed emergency eyewashes installed along with addressing electrical receptacles, lighting upgrades, plumbing work, fixtures, storage / shelfing additions, Fiberglass Reinforced Paneling (FRP), and finishing work.

Contract Period: Base POP Begin:

POP End:

PRINCIPAL NAICS CODE: 236220 - Commercial and Institutional Building Construction PRODUCT/SERVICE CODE: Z2DA - Repair or Alteration of Hospitals and Infirmaries

GRAND TOTAL
__________________

A.4 Statement of Work

Introduction:

The Sheridan, Wyoming Veterans Affairs Medical Center (VAMC), located at 1898 Fort Road, Sheridan, Wyoming 82801, requires upgrades to 24 of its existing Housekeeping Aid Closets (HACs) to have tepid, plumbed emergency eyewashes installed. The in-scope HACs are located in Buildings 1, 2, 3, 4, 5, 6, 8, 9, 71, 71N, 86, and 87 at the Sheridan VAMC campus.

Other work includes addressing electrical receptacles & lighting upgrades, plumbing work & fixtures, storage/shelving adjustments & additions, installation of Fiberglass Reinforced Paneling (FRP), and finishes work. See the drawings and specifications for full details of the project.

The eyewashes must be plumbed, tepid emergency eyewashes that comply with the current versions of Occupational Safety and Health Administration (OSHA) 29 CFR 1910.151(c), American National Standards Institute/ International Safety Equipment Association (ANSI/ISEA) Z358.1-2014, Veterans Health Administration (VHA) General Safety Guidebook requirements, and all other applicable codes and standards.

Statement of Work:

1. General

a. Construction project shall be completed within 122-calendar days from date of full Notice to Proceed (NTP). Contractor’s schedule shall utilize this entire period of performance unless otherwise approved in writing by the Contracting Officer’s Representative (COR) and Contracting Officer (CO).

b. Contractor shall provide all equipment, materials, supplies, tools, software, supervision, and labor required for this project, including, but not limited to, demolition work, providing negative pressure environment for work, and providing all new equipment, utilities, and room finishes as indicated in the plans and specifications.

c. Safety submittals shall be completed and approved prior to the commencement of on-site construction work. Material selection submittals shall be completed and approved prior to ordering of materials for the project.

d. The building tenants not in the construction areas will remain at work in the buildings during this construction. Patients will remain on the floor in areas not under construction, so the contractor shall make patient safety and infection control measures a priority. The contractor shall coordinate work locations and schedules with VA COR so as to minimize impact to building tenants.

e. All electrical, carpentry, architectural, plumbing, mechanical, & finish work, product design, project management, and other work needed on this project shall be provided by the Contractor. All required electrical work, low, medium, or high voltage, shall be installed and terminated by the contractor.

i. No wiring or cabling shall be abandoned in place.

ii. All piping, cabling, and wiring shall be labeled. All cabling and patch cabling shall match the VAMC’s station standard colors.

f. The installation must, as a minimum, be in accordance with all current versions of the applicable codes indicated in the Department of Veterans Affairs (VA) Design Manuals and VA PUBLICATIONS (Master Construction Specifications, Construction Standards, National Fire Protection Association (NFPA), Underwriters Laboratory, International Building Code (IBC), National Electric Code (NEC), building codes and standards, and VA Information Security Handbook 6500.6, 6550.0 etc.).

g. Any penetrations through any floors, ceilings, or walls, shall be fire caulked, or otherwise fire sealed, and shall be done in this contract to meet VA standards and NFPA standards.

i. Contractor shall utilize the VAMC’s station-standard fire stop products or approved equal product(s). The station-standard products are SpecSeal—fire caulk product is SpecSeal SSS Intumescent Firestop Sealant; and, if needed, the SpecSeal Composite Sheet may be used in areas approved by the COR.

h. The Contractor shall inquire of the COR if any existing eyewashes, fixtures, hardware, or any other property removed is desired to be retained by the VA for reuse elsewhere within the medical center, at the time of removal.

i. If the VA desires to retain an item, the Contractor shall deliver it to a location designated by the COR.

ii. If the VA does not desire to retain an item, the Contractor shall dispose of it properly off-station.

i. The new components installed shall be tested and commissioned, re-certified, and/or tested before VA acceptance. All testing parameters shall be provided by the Contractor with source references to the COR and 3rd-party reviewer before testing begins. Copies of all test reports must be provided to the COR.

i. HVAC systems that have changes made to them as part of this project, beyond diffuser replacement, shall be tested and balanced by the Contractor.

ii. Any IT data cables installed or modified as part of this effort shall be tested after installation. Test methods and plans shall be coordinated with the COR.

iii. Any Med Gas systems modified as part of this effort shall be re-certified back to the closest shut-off in the system. The Contractor shall arrange for any required re-certification as part of this contract and shall provide plans and results to the COR for approval.

iv. Fire alarm devices that are tied into the building fire alarm system, that are replaced or relocated as a result of this work, shall be tested before that phase of the project is complete. The Contractor shall arrange for all required fire alarm testing. If a building’s fire alarm system is under warranty, testing must be accomplished by the contractor who holds the warranty.

v. Any fire sprinklers that are relocated as part of this project shall be reviewed and approved by VA Safety prior to installation. All fire sprinkler work shall be coordinated with VA Safety so as to avoid accidentally setting off the system.

j. At the conclusion of the project, the Contractor shall provide the VA and AE with a red-lined set of construction drawings, showing any as-built variations from the plans, as called for in the specifications.

k. The Contractor must repair any damage caused by the Contractor or their subcontractors during this project. Repairs shall be done timely and will be coordinated with the COR. Repairs shall be of equal or better quality and finish than the existing that was damaged.

l. Contractors shall not work on weekends, or federal holidays as specified by U.S. Office of Personnel Management (OPM), unless approved in advance by the COR or CO. For approved weekend or holiday work, Contractor must adjust their workers’ pay accordingly at no additional cost to the VA.

2. Safety and Security

a. The Contractor shall follow all safety specifications and shall always have an OSHA-30 certified person on-site, at each work location, overseeing the construction. All other Contractors and subcontractors working on-site shall have at least OSHA-10 certifications.

b. Some work will be in medical areas of the hospital, on floors with patients present, so the contractor shall plan for infection control measures to include dust containment, negative pressure, and cleanup to hospital standards.

i. The Contractor will, with the participation of the COR, complete an Infection Control Risk Assessment (ICRA), using the VA forms and process, and Contractor shall implement all protection measures called for as a result of the risk assessment. (The current planned ICRAs for this project—one for patient-care areas, and one for non-patient care areas—has been provided with the bid package so the Contractor knows what ICRA protection levels are anticipated.)

c. Contractor shall review the Limited Asbestos and Lead Paint Inspection Report for this project, which is included after Specification Section 02 82 12.13. Based on this report, and to the extent feasible, Contractor shall include in their bid an allowance for foreseen abatement work required to complete this project.

i. For any required abatement work, the Contractor shall comply with the current Wyoming Department of Environmental Quality (WY DEQ), Wyoming state, and Sheridan VAMC standards.

d. For work on an active mental health unit, the Contractor shall follow strict tool control and access control in construction areas. Any patients found in construction areas shall be immediately reported to ward staff and the COR.

i. The Contractor shall read and follow the current version of the FMS Safety Plan, which outlines expectations for tool control and safety on-station, as well as stricter requirements for work on the Acute Psychiatric Ward (APU) located on the 2nd floor of Building 8 (e.g., Rule of Two minimum with one person overseeing the work at all times). Contractor shall distribute the FMS Safety plan to their workers and subcontractors. Contractor shall note this training in their daily logs.

e. All Contractors and subcontractors must obtain a temporary contractor badge from the Engineering Office (Building 5 Room 208) when they first arrive on-site. A valid (i.e., not expired), Government-issued, photo ID (such as a Driver’s License) is required to be issued a badge. Contractors who have a valid PIV Badge or CAC Badge will not need to be issued a temporary badge.

3. Phasing

a. The Contractor must propose a phasing plan for review and approval by both the COR and CO before beginning any work on-site for this project.

a. Not all 24 Housekeeping Aid Closets (HACs) can be worked on concurrently. At least one HAC per floor, or if not possible, at least one HAC per building, must remain operational for Housekeeping to utilize during construction. However, Contractor is encouraged to use more than one crew, as it makes sense, so the project is completed timely.

b. Contractor must work closely with the COR and keep them updated of any changes to their originally approved schedule.

c. The Contractor’s schedule must allow for 48-hours’ minimum inspection time by the COR and/or VA for completed work, and 48-hours’ minimum advanced notice of planned work so COR can inform the staff in the area.

Work will include:

Base Bid:

All work included in the drawings, the specifications, and any work required for fully functional, code-compliant, safe installations.

Alternates:

There are no bid alternates for this project

End of Statement of Work

VA Contacts:

Timothy Verburgt, Contracting Specialist, (303) 712-5707 Jennifer Crecelius, COR, (307) 675-3679 Rodney Lindberg, Alternate COR, (307) 675-3462

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

PART I - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS

PART I/SECTION A – REQUEST FOR PROPOSAL

I.1A JOINT VENTURES

If submitting an offer as a joint venture as defined by P.L. 109-461 AND Department of Veterans Affairs I.L. 049-06-4. Certified SDVOSB/VOSB listed in the SBA certification database at https://veterans.certify.sba.gov/ (see 13 CFR 128). A joint venture may be considered eligible if it meets the requirements in 13 CFR part 128, and the managing joint venture partner makes the representations under VAAR 819.7003 paragraph (b). An offeror must provide a copy of the joint venture agreement specific to the project that is consistent with the percentage of required work and net proceed. Additionally, the offeror must provide a breakdown or labor of which is to be performed by the SDVOSB firm and that which is performed by the small business joint venture firm and that which is sub-contracted. All Joint Ventures will be required to be registered and verified as an entity in VETCERT.

I.2A SELECTION PROCEDURES

This acquisition will be a competitive acquisition utilizing FAR Part 15 source selection employing tradeoff source selection procedures. By submission of its offer, the offeror accedes to all solicitation requirements, including terms and conditions, representations, and certifications. All such offers shall be treated equally except for their prices and performance records. Failure to meet a requirement may result in an offer being determined non-compliant. It is the intent of the Government to award without discussions; however, the Government will reserve the right to have discussions if such are needed.

I.3A PRE-PROPOSAL SITE VISIT

See SF 1442, Block 10 and FAR Provision 52.236-27, Site Visit (Construction) of this solicitation. Please leave extra time to complete COVID-19 screening process when entering the building. Masks are required to be worn by all employees and contractors while on VA property.

I.4A SELECTION CRITERIA

This acquisition will utilize the tradeoff process in accordance with FAR 15.101-1. This process permits tradeoffs between non-cost factors and cost/price and allows the Government to accept other than the lowest priced proposal or other than the highest rated proposal to achieve a best value contract award based on established evaluation criteria. Inherent in this process is the necessity to make tradeoffs considering the non-cost strengths and weaknesses, risks, and the cost (or price) offered in each proposal.

The source selection process will be conducted utilizing FAR part 15.101-1 Trade-off Process Source Selection Procedures with Special Standards of Responsibility. Offers will be evaluated using the following evaluation factors:

Factor 1 – Past Performance Factor 2 – Price

In addition to the general standards of responsibility found at FAR 9.104-1, in accordance with FAR 9.104-2, the special standards of responsibility described below apply to this procurement. Offerors who fail to meet any special standard of responsibility may not be eligible to receive contract award.

Past performance will be evaluated on a basis of significantly more important than, cost or price.

Past Performance Evaluation For Factor 1, based on the evaluation of all recent and relevant past performance for an offeror, an overall performance confidence rating shall be assigned. The performance confidence ratings are defined below:

ASSESSMENT
DESCRIPTION
Substantial Confidence
Based on the offeror’s recent/relevant performance record, the Government has a high expectation that the offeror will successfully perform the required effort.
Satisfactory Confidence
Based on the offeror’s recent/relevant performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort.
Limited Confidence
Based on the offeror’s recent/relevant performance record, the Government has a low expectation that the offeror will successfully perform the required effort.
No Confidence
Based on the offeror’s recent/relevant performance record, the Government has no expectation that the offeror will be able to successfully perform the required effort.
Unknown Confidence (Neutral)
No recent/relevant performance record is available, or the offeror’s performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned.

Note: In the case of an offeror without a record of past performance or for whom information on past performance is not available or so sparse that no meaningful past performance rating can be reasonably assigned, the offeror may not be evaluated favorably or unfavorably on past performance. Therefore, the offeror shall receive an unknown confidence (neutral) performance confidence rating.

(a) Aspects of Past Performance Evaluation. The past performance evaluation is an assessment based on the offeror’s record of relevant and recent past performance information that pertain to the products and/or services outlined in the solicitation requirements. There are two aspects of the past performance evaluation.

(1) The first is to evaluate whether the offeror’s present/past performance is relevant or not relevant to the effort to be acquired. The criteria to establish what is relevant is unique to each source selection.
(2) The second aspect of the past performance evaluation is to determine how well the contractor performed on the contracts. The past performance evaluation performed in support of a current source selection does not establish, create, or change the existing record and history of the offeror’s past performance on past contracts; rather, the past performance evaluation process gathers information from customers on how well the offeror performed those past contracts. In addition, the Government reserves the right to obtain information for use in the evaluation of past performance from all sources including sources outside of the Government. Other sources may include, but are not limited to, past performance information retrieved through the Past Performance Information Retrieval System (PPIRS) using all CAGE/DUNS numbers of Contractors who are part of a partnership or joint venture identified in the Offeror’s proposal, inquiries of owner representative(s), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by the Offeror.
(b) Source Selection Evaluation Board (SSEB) members will review past performance information to determine the quality and usefulness as it applies to the performance confidence assessment.

Adverse past performance is defined as past performance information that supports a less than satisfactory rating on any evaluation element or any unfavorable comments received from sources without a formal rating system.

Factor 1-Past Performance

(a) Solicitation Submittal Requirements:

Offerors shall provide a minimum of two (2) and maximum of five (3) recent and relevant projects (as defined below) to demonstrate their ability to perform the proposed work identified within the Specifications, drawings, and Statement of Work. If a completed Contractor Performance Assessment Reporting System (CPARS) evaluation is available, it shall be submitted. The Government will evaluate past performance based upon sources available to the contracting officer that may include Past Performance Information Retrieval System (PPIRS), Federal Awardee Performance and Integrity Information System (FAPIIS) and Electronic Subcontract Reporting System (eSRS). IF THERE IS NOT A PAST PERFORMANCE EVALUATION IN PPIRS or FAPPIIS, then the offeror shall submit Past Performance Questionnaires (PPQ) for each project. Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other RFPs. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation. If the offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the offeror shall complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the respective project(s). The Government may make reasonable attempts to contact the client noted for that project(s) to obtain the PPQ information. However, offerors should follow-up with clients/references to help ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government’s point of contact, Timothy Verburgt, Timothy.Verburgt@va.gov.

Recency – a recent project is defined as being completed within five years of the due date of this solicitation.

Relevant – includes performance of efforts in a project of renovation or remodeling that include general construction in an active medical facility that are similar or greater in scope, magnitude, and complexity than the effort described in this solicitation.

Offerors are cautioned to submit enough information in the format specified in the solicitation. Offerors may be asked to clarify certain aspects of their proposal (for example, the relevance of past performance information) or respond to adverse past performance information to which the offeror has not previously had an opportunity to respond. Adverse past performance is defined as past performance information that supports a less than satisfactory rating on any evaluation element or any unfavorable comments received from sources without a formal rating system. Communication conducted to resolve minor or clerical errors will not constitute discussions and the contracting officer reserves the right to award a contract without the opportunity for proposal revision.

(b) – Basis of Evaluation:

The contracting officer shall review recent and relevant performance information on each offeror based on past efforts provided by the offeror and may obtain data independently from other government and commercial sources. Past performance regarding predecessor companies, key personnel who have relevant experience, or sub-contractors that will perform major or critical aspects of the requirement will not be considered as highly as past performance information for the principal offeror. Offerors with no past performance history or the offeror’s performance record is so limited that no confidence assessment rating can be reasonably assigned shall receive the rating "Unknown Confidence," meaning the rating is treated neither favorably nor unfavorably.

The Government will consider the currency and relevance of the information, the source of the information, context of the data, and general trends in the Contractor’s performance. This evaluation is separate and distinct from the Contracting Officer’s responsibility determination. The assessment of the offeror’s past performance will be used as a means of evaluating the offeror’s probability to successfully meet the requirements of the RFP.

Initially offers shall be ranked according to price, including any option prices if applicable. The lowest price offer’s past performance shall be evaluated to determine its performance confidence rating.

If the lowest priced evaluated offer is judged to have a Substantial Confidence performance assessment, that offer represents the best value for the government and the evaluation process stops at this point. Award shall be made to that offeror without further consideration of any other offers.

If the lowest price offer does not receive a Substantial Confidence performance confidence rating, the past performance evaluation continues until an offeror’s past performance is judged to have a Substantial Confidence performance rating. The Government reserves the right to award a contract to other than the lowest priced offeror if the lowest priced offeror is judged to have a performance confidence assessment of "Satisfactory Confidence" or lower. In that event, the Source Selection Authority shall make an integrated assessment best value award decision.

Factor 2 – Price:

(a) Solicitation Submittal Requirements:

· Standard Form 1442, Solicitation Offer and Award

· All pages of the SF1442 Continuation Sheet

(b) Basis of Evaluation: The Government will evaluate price based on the total price. Analysis will be performed by one or more of the following techniques to ensure a fair and reasonable price:

· Comparison of proposed prices received in response to the RFP

· Comparison of proposed prices with the IGCE.

· Comparison of proposed prices with available historical information.

Special Standard of Responsibility Solicitation Submittal Requirements:

The Offeror shall submit the following information: (For a partnership or joint venture, the following submittal requirements are required for each Contractor who is part of the partnership or joint venture and for the entity itself. EMR shall not be submitted for subcontractors.)

1. OSHA or EPA Violation(s):

Offerors shall provide Summary of Work-Related Injuries and Illnesses, affirming that the Offeror has no more than three serious, or one repeat, or one willful OSHA or EPA violation(s) in the past 3 years.

2. Experience Modification Rate (EMR):

Offerors shall provide documentation to show that the offeror has an Experience Modification Rate (EMR) of equal to or less than 1.0. If an offeror’s EMR is above 1.0, the offeror must submit a written explanation of the EMR from its insurance carrier on the insurance carrier’s letterhead, describing the reasons for the EMR and the anticipated date the EMR may be reduced to 1.0 or below.

Offerors who fail to meet any special standard of responsibility may not be eligible to receive contract award.

PART I/SECTION B - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS

I.1B COST RANGE: Between $500,000.00 and $1,000,000.00

I.2B GENDER: Wherever the masculine gender is used in this solicitation and contract documents, it shall be considered to include both masculine and feminine.

I.3B METRIC PRODUCTS:

Products manufactured to metric dimensions will be considered on an equal basis with those manufactured using inch-pound units, providing they fall within the tolerance specified using conversion tables contained in the latest revision of Federal Standard No. 376, and all other requirements of this document are met.

If a product is manufactured to metric dimensions and those dimensions exceed the tolerance specified in the inch-pound units, a request should be made to the Contracting Officer to determine if the product is acceptable. The Contracting Officer, in concert with the Contracting Officer’s Representative (COR), will accept or reject the product.

I.4B REQUESTS FOR INFORMATION:

All requests for information must be submitted in writing to the Contracting Officer for action no later than the date shown in Block 10 of the Standard Form 1442, Solicitation, Offer and Award.

I.5B PROPOSAL REQUIREMENTS

General – Both past performance information and price proposal shall be submitted in response to this solicitation. Proposals shall be submitted via email Timothy.Verburgt@va.gov. Emails are limited to 15 MB. The proposal, in its entirety, shall be one email (one attachment for price proposal, one attachment for LOS certification, and one attachment for past performance information) not to exceed 15MB. Failure to submit in the format required and clearly address those factors may result in rejection of the offer. An original Bid Bond, in the amount of twenty (20%) percent (but not to exceed $3,000,000) of the bid price shall be mailed to the address listed in block 8 of the SF1442 and be received at the address no later than the closing date and time. Failure to furnish the required bid guarantee in the proper form and amount, by the time set for due date, will require rejection of the proposal in all cases except those listed in FAR 28.101-4, and may be cause for rejection even then. SEE FAR Provision 52.228-1, Bid Guarantee, of this Solicitation. Electronic copies of the proposals will be time/date stamped by Microsoft Outlook upon receipt of email. Further details on electronic submission are outlined below.

Proposals shall be received by 2:00 P.M. Mountain Time on September 06, 2024. There will be no public opening of the proposals. Submit proposals to: Timothy.Verburgt@va.gov.

Submit bid bonds to:

Department of Veterans Affairs

NCO 19

ATTN: Timothy Verburgt 6162 S Willow Dr., Ste 300 Greenwood Village, CO 80111

Past performance information and price sections of the offeror’s proposal will be evaluated independently. Offerors shall include all required Representations and Certifications and complete their registration in System for Award Management (SAM). See FAR 52.204-7 and 52.204-8, of this solicitation.

Important Notice: Apparent successful offerors must apply for and receive verification from the Small Business Administration (SBA) through the SBA certification database via 13 CFR Part 128, VAAR 819.7011, and VAAR 819.7003 by submission of documentation of Veteran status, ownership and control enough to establish appropriate status. Offerors must be both VISIBLE and VERIFIED by the SBA certification database at the time of offer submission. Failure to be both VERIFIED by SBA and VISIBLE on the SBA certification database at the time of offer submission and contract award will result in the offeror’s proposal being deemed non-compliant. All offerors are urged to contact the SBA and submit the required documents to obtain verification of their SDVOSB status if they have not already done so.

Or

Meet Federal Acquisition Regulation (FAR) class deviation regarding certification of Service-Disabled Veteran Owned Small Business concerns as per CAAC Letter 2024-02, effective January 1, 2024, until SAM.gov is updated to reflect the SBA’s certification or otherwise rescinded.

I.6B PROPOSAL REVISIONS

If it is determined to be necessary, proposal revisions will be requested from the offers received. The Contracting Officer may identify those offerors, whose proposals are within the competitive range based upon the selection criteria identified in this solicitation. Negotiations may be conducted with those firms falling within the competitive range, after which proposal revisions may be requested. Offerors submitting proposal revisions will not be required to re-submit any documents which are unchanged from their proposals. They should provide necessary changes to individual paragraphs, as briefly as possible, together with the Table of Contents that clarifies where within the initial proposal the additional information and/or changed document would be placed. A new bid bond shall be submitted only if the final cost proposal revisions are greater than its initial cost proposal.

1.7B REQUIREMENTS FOR ELECTRONIC SUBMISSION OF OFFER

Unless paper offers are specifically authorized in an individual solicitation, all responses to solicitations must be submitted electronically as described below. Responses submitted in a paper form are unacceptable. Failure to comply with this requirement may jeopardize the possibility of receiving an award for the contract due to noncompliance with the terms of the solicitation. You must submit your electronic offer, and any supplemental information (such as spreadsheets, backup data, technical information), using any of the electronic formats and media described below.

In addition, contractors are notified of the award via an electronic Notice of Award e-mail. The award document will be attached to the Notice of Award e-mail.

Acceptable Electronic Formats (Software) for Submission of Offers

1. Files readable using the current Microsoft© Office version Products: Word, Excel, PowerPoint, or Access. Please see security note below for caution regarding use of macros. When submitting construction drawings contractors are required to submit one set in AutoCAD and one set in Adobe PDF. (purpose: contracting can open the PDF version and engineering can open AutoCAD files).

2. Files in Adobe© PDF (Portable Document Format) Files: When scanning documents scanner resolution should be set to 200 dots per inch, or greater.

3. Another electronic format. If you wish to submit an offer using another format other than described in these instructions, e-mail the Contracting Officer who issued the solicitation. Please submit your request at least ten (10) calendar days before the scheduled closing date of the solicitation. Request a decision as to the format acceptability and make sure you receive approval of the alternate format before using it to send your offer.

4. Please note that we can no longer accept .zip files due to increasing security concerns.

E-mail Submission Procedures: For simplicity in this guidance, all submissions in response to a solicitation will be referred to as offers.

a. Subject Line: Include the solicitation number, name of company, and closing date of solicitation. Use only one of the terms Quotation, Offer, Proposal, or Bid depending on the solicitation type.

b. Size: Maximum size of the e-mail message shall not exceed five (5) megabytes. Only one email is permitted unless otherwise stated in this solicitation or in writing by the Contract Officer submitting the solicitation.

c. Unless approved by the contracting officer: DO NOT submit a link to your PDF documents. Please submit your request in an email for other electronic format at least ten (10) calendar days before the scheduled closing date of the solicitation. Request a decision as to the format acceptability and ensure you receive approval of the alternate format before using it to send your offer.

Each electronic offer must also include a signed and scanned SF-1442, Solicitation, Offer, and Award (Construction, Alteration, or Repair)

The Microsoft Outlook © Email time/date stamp will be used to date and time stamp offers for the official record of receipt for the submission. The date and time stamp in recipient’s “inbox” is the official record of receipt.

Security Issues, Late Bids, Unreadable Offers

1. Late submission of offers is outlined at FAR 52.215-1(c)(3). Particular attention is warranted to the portion of the provision that relates to the timing of submission.

2. Please see FAR 15.207(c) for a description of the steps the Government shall take with regard to unreadable offers.

3. To avoid rejection of an offer, vendors must make every effort to ensure their electronic submission is virus-free. Submissions or portions thereof submitted and which the automatic system detects the presence of a virus or which are otherwise unreadable will be treated as “unreadable” pursuant to FAR 15.207(c).

4. The virus scanning software used by our e-mail systems cannot always distinguish a macro from a virus. Therefore, sending a macro embedded in an e-mail message or an e-mail attachment may cause the e-mail offer to be quarantined. You may send both the spreadsheet and the spreadsheet saved in PDF format to ensure that your proposal is readable.

5. Password protecting your offer is not permitted. The Contracting Officer will file the offer electronically which will allow access only by designated individuals.

2.1 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)

(a) Definitions. As used in this provision— "Administrative proceeding" means a non-judicial process that is adjudicatory in nature in order to make a determination of fault or liability (e.g., Securities and Exchange Commission Administrative Proceedings, Civilian Board of Contract Appeals Proceedings, and Armed Services Board of Contract Appeals Proceedings). This includes administrative proceedings at the Federal and State level but only in connection with performance of a Federal contract or grant. It does not include agency actions such as contract audits, site visits, corrective plans, or inspection of deliverables.

"Federal contracts and grants with total value greater than $10,000,000" means—

(1) The total value of all current, active contracts and grants, including all priced options; and

(2) The total value of all current, active orders including all priced options under indefinite-delivery, indefinite-quantity, 8(a), or requirements contracts (including task and delivery and multiple-award Schedules).

"Principal" means an officer, director, owner, partner, or a person having primary management or supervisory responsibilities within a business entity (e.g., general manager; plant manager; head of a division or business segment; and similar positions).

(b) The offeror [ ] has [ ] does not have current active Federal contracts and grants with total value greater than $10,000,000.

(c) If the offeror checked "has" in paragraph (b) of this provision, the offeror represents, by submission of this offer, that the information it has entered in the Federal Awardee Performance and Integrity Information System (FAPIIS) is current, accurate, and complete as of the date of submission of this offer with regard to the following information:

(1) Whether the offeror, and/or any of its principals, has or has not, within the last five years, in connection with the award to or performance by the offeror of a Federal contract or grant, been the subject of a proceeding, at the Federal or State level that resulted in any of the following dispositions:

(i) In a criminal proceeding, a conviction.

(ii) In a civil proceeding, a finding of fault and liability that results in the payment of a monetary fine, penalty, reimbursement, restitution, or damages of $5,000 or more.

(iii) In an administrative proceeding, a finding of fault and liability that results in—

(A) The payment of a monetary fine or penalty of $5,000 or more; or

(B) The payment of a reimbursement, restitution, or damages in excess of $100,000.

(iv) In a criminal, civil, or administrative proceeding, a disposition of the matter by consent or compromise with an acknowledgment of fault by the Contractor if the proceeding could have led to any of the outcomes specified in paragraphs (c)(1)(i), (c)(1)(ii), or (c)(1)(iii) of this provision.

(2) If the offeror has been involved in the last five years in any of the occurrences listed in (c)(1) of this provision, whether the offeror has provided the requested information with regard to each occurrence.

(d) The offeror shall post the information in paragraphs (c)(1)(i) through (c)(1)(iv) of this provision in FAPIIS as required through maintaining an active registration in the System for Award Management, which can be accessed via https://www.sam.gov (see 52.204-7).

(End of Provision)

2.2 52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.

(End of Provision)

2.3 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of Provision)

2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers.