This document is a Statement of Work for a design-build contract to remodel multiple rooms in the Acute Psychiatric Unit (APU) at the Sheridan VA Medical Center in Sheridan, Wyoming. The Department of Veterans Affairs is seeking a design-build contractor to provide all labor, materials, equipment, permitting, design, and construction services necessary for the project. The project includes selective demolition, installation of new doors with access control, painting, flooring, lighting, and wall construction in rooms 202, 207, 263, 232, 233, and 234. The work will be performed in multiple phases. The design period is 90 calendar days and the construction period is 120 calendar days. The project magnitude is estimated between $500,000 and $1,000,000. This is a Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside procurement. Proposals are due by August 19, 2024.

View the file

Other files

File Type Posted
S05 - RFIs and Responses-July-2024-COR Responses.pdf PDF
36C25924R0091 0001.docx DOCX document
S02 - DB Construction Experience Sheet.docx DOCX document
S02 - Remodel Plan.pdf PDF
S02 - Specs - Reduced.pdf PDF
S22- 852.219-75 LOS Certificate - GC.docx DOCX document
S02 - Past Performance Questionnaire.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C25924R0091

1. SOLICITATION NUMBER

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

6. PROJECT NUMBER

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

a. NAME

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)

STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES

NO

a.

Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b.

An offer guarantee is, is not required.

c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

36C25924R0091 X 07-1 -2024 666-22-128 36C259 Department of Veterans Affairs Network Contracting Office

NCO 19

6162 South Willow Drive, Suite 300 Greenwood Village CO 80111 Jason Rankin Jason.Rankin@va.gov

Jason Rankin 303-712-5755 The contractor shall furnish all labor, equipment, materials, and supervision to complete the following project at the Sheridan VA Medical Center located at 1898 Fort Road, Sheridan, WY 82801.

Project: 666-22-128 Design Build Sally Port-Nurse Exam Remodel.

This project is described in the Statement of Work - see page 5.

Project Magnitude of the requirement is estimated between $500,000.00 and $1,000,000.00.

The NAICS code is 236220 with a business size standard of $45M.

All questions in relation to Phase I of this solicitation are due no later than 10:00 AM MT July 30, 2024.

Please address questions to jason.rankin@va.gov

The closing date for Phase I of this solicitation is 10:00 AM MT on August 19, 2024. Email proposals to Jason.Rankin@va.gov.

Important Notice: Apparent successful offerors must apply for and receive verification from the Small Business Administration (SBA) through the SBA certification database via 13 CFR Part 128, VAAR 819.7011, and VAAR 819.7003 by submission of documentation of Veteran status, ownership, and control enough to establish appropriate status. Offerors must be both VISIBLE and VERIFIED by the SBA certification database at the time of offer submission. Failure to be both VERIFIED by SBA and VISIBLE on the SBA certification database at the time of offer submission and contract award will result in the offeror’s proposal being deemed non-compliant. All offerors are urged to contact the SBA and submit the required documents to obtain verification of their SDVOSB status if they have not already done so.

In accordance with FAR 52.204-7, System for Award Management (SAM), Prospective contractors shall be registered in the SAM database prior to close of solicitation.

X X 52.211-10 X

10:00 AM

MDT

08-19-2024 X 120 days

14. NAME AND ADDRESS OF OFFEROR

15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (

26. ADMINISTERED BY

27. PAYMENT WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

36C259 Department of Veterans Affairs Network Contracting Office

NCO 19

6162 South Willow Drive, Suite 300 Greenwood Village CO 80111 Department of Veterans Affairs Financial Service Center PO Box 149971 Austin TX 78714-9971

Table of Contents

PART I - THE SCHEDULE1
SECTION A - SOLICITATION/CONTRACT FORM1
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)1
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK2
A.3 PRICE/COST SCHEDULE5
ITEM INFORMATION5
A.4 Statement of Work5
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS14
2.1 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)24
2.2 52.216-1 TYPE OF CONTRACT (APR 1984)25
2.3 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014)25
2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)26
2.5 52.233-2 SERVICE OF PROTEST (SEP 2006)27
2.6 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)27
2.7 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)28
2.8 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018)28
2.9 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)29
2.10 PARTNERING29
REPRESENTATIONS AND CERTIFICATIONS29
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAY 2024)29
3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)33
3.3 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—CERTIFICATION (NOV 2021)36
GENERAL CONDITIONS37
4.1 52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS (NOV 2021)37
4.2 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)39
4.3 52.219-14 LIMITATIONS ON SUBCONTRACTING (OCT 2022)39
4.4 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (FEB 2024)41
4.5 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022)44
4.6 SUPPLEMENTAL INSURANCE REQUIREMENTS48
4.7 52.252-6 AUTHORIZED DEVIATIONS IN CLAUSES (NOV 2020)48
4.8 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)49
4.9 VAAR 852.201-70 CONTRACTING OFFICER'S REPRESENTATIVE (DEC 2022)51
4.10 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)52
4.11 VAAR 852.204-70 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL (MAY 2020)52
4.12 VAAR 852.204-71 INFORMATION AND INFORMATION SYSTEMS SECURITY (FEB 2023)52
4.13 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (JAN 2023) (DEVIATION)60
4.14 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (JAN 2023) (DEVIATION)63
4.15 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008)65
4.16 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009)65
4.17 VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (WITHOUT NAS– CPM) (NOV 2018)65
4.18 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)68
4.19 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019)69
4.20 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)70
4.21 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)70
4.22 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020)70
4.23 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019)71
DESIGN BUILD SPECIFICATIONS73
4.24 GENDER73
4.25 CONTRACTOR’S COST BREAKDOWN73
4.26 SCHEDULE OF PAYMENTS FOR DESIGN SERVICES73
4.27 OWNERSHIP OF ORIGINAL DOCUMENTS73
4.28 RETENTION OF REVIEW DOCUMENTS74
4.29 CONTRACT DRAWINGS AND SPECIFICATIONS GOVERNMENT FURNISHED PLANNING INFORMATION74
4.30 COORDINATION WITH MEDICAL CENTER74
4.31 RESPONSIBILITY OF THE DESIGN-BUILD CONTRACTOR74
ATTACHMENTS75
ATTACHMENT 1 - RELEASE OF CLAIMS75
4.32 Wage determination75
4.33 List of Attachments81

A.3 PRICE/COST SCHEDULE

ITEM INFORMATION

ITEM NUMBER
DESCRIPTION OF SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
0.00
JB
__________________
__________________

666-22-128 | Sally Port-Nurse Exam Remodel | Design Build Contract Period: Base POP Begin:

POP End:

PRINCIPAL NAICS CODE: 236220 - Commercial and Institutional Building Construction PRODUCT/SERVICE CODE: Z2DA - Repair or Alteration of Hospitals and Infirmaries

GRAND TOTAL
__________________

A.4 Statement of Work

DESIGN-BUILD REMODEL

OF MULTIPLE ROOMS OF THE ACUTE PSYCHIATRIC UNIT (APU)

PROJECT NUMBER 666-22-128

SHERIDAN VAMC

1898 FORT ROAD, SHERIDAN, WY 82801

PROJECT OVERVIEW

PURPOSE:

The U.S. Department of Veterans Affairs (VA) is seeking a design-build contractor to provide all labor, materials, equipment, permitting, design, and construction services necessary to Remodel multiple rooms in building 8. Design-Build (DB) team must provide complete design and construction services within the Acute Psychiatric Unit (APU). Design shall include development of a full set of 100% design documents (construction and demo drawings and specifications) and supporting calculations. Contractor is expected to present the standard schematic design, design development, and final design submittals.

Construction will include submittal process and all other requirements defined in VA specifications. All materials are to be submitted and approved by COR before ordering. Project shall comply with all VA specifications, design manuals, directives, and all other applicable requirements. See also Section 00 11 21 Request for Proposal for Design/Build for additional information.

PROJECT DESCRIPTION:

The following is a general overview of the project. The selected contractor shall use the 35% design provided as the basis of design, shall verify all existing building and utility information, provide full set of construction documents as required by VA standard and shall comply with all VA specifications, design manuals, and requirements.

1. The basis of the project is to design and remodel rooms 202, 207, 263, 232, 233, 234 to varying requirements based upon the 35% plans and specs as provided by the VA.

· This project is located on the Acute Psychiatric Unit (APU) which is a patient critical mental health unit. APU policies and procedures will be ALWAYS followed upon entering, leaving, and conducting construction or design activities on the unit. Sign in procedures, Tool control, and designated observers are mandated by policy and shall be adhered to without exception.

2. Design work will encompass selective demolition, installation of new complete door(s) with access control (Dynamic Controls), door frame(s) suitable for access control as required, any camera installations required (Hanwa Cameras currently in use at Sheridan VA), painting in all designated rooms, flooring installation in all designated rooms (ALL Luxury vinyl Tile (LVT)), required lighting additions or relocations, and new wall construction as indicated on plans for the Acute Psychiatric Unit (anti-Ligature), Nurse Call (Beacon Communications) relocation to new intake rooms as required by VA design policy, cabinetry installations (Furniture preferred over millwork).

· All final room configurations will be determined in design Charrette meetings.

3. Building 8 has been identified to contain non friable Asbestos in the most recent Asbestos Management Survey Report Dated July 2019 in some of the rooms involved in this project. A mitigation plan shall be developed as a part of this construction project.

· The Sheridan VA will provide the latest Asbestos report.

4. Design work to be in phases per more detailed 35% plans and per below:

· Phase One – sally port room 202 and room 263 and selective painting in room 207 (wall Chalkboards 4-foot high, maximum width as space allows).

· Phase Two – nurse’s station rooms 232 (clear wall with pass through window, will require construction wall) and 233 per construction plans.

· Phase three – convert rooms 240, 265 and 231 (exam room, remove sink) to office space, assess and replace current nurse call systems in patient bathrooms, as required and install access control to two (2) outer tramway gates.

PROJECT ACTIVITIES:

· Pre-proposal Site Visit(s) as required.

· Submit Proposal.

· Award Contract.

· Bonding/Insurance.

· Notice to Proceed.

· Post-award site visit - confirm basis of design parameters – provide analysis using VA provided data verifying general parameters of the design and construction. Site visit(s) are required.

· Design reviews at design development and final design - Design reviews including all submittals and construction schedules as required by PG-18-15 Minimum Requirements for A/E Submissions.

· VA Approval for final Design Documents – plans and specifications as required by PG-18- 15.

· Design document development.

· Materials Procurement – as soon as possible to avoid construction delays.

· Submissions as required for construction (Hot work permits, Safety Plans, ICRA, Quality Control Plans, utility interruption requests, etc.).

· Construction.

· Verification.

· Commissioning as required.

· Training as required.

· Acceptance by VA.

· Final Payment.

· Warranty periods begin.

DRAFT SCHEDULE:

Predesign Meeting with VA staff: Day 0 Design Submit 65% Design Development (DD) Review Package:

VA review:

Submit 95% Construction Document (CD) Review Package:

VA Technical and Constructability reviews:

Submit 100% Construction Document (CD) Review Package:

Construction NTP and Multi-Phased Construction:

The Contractor shall be responsible for the verification of existing site conditions that may affect required Phasing, construction walls, power, data communication, room configuration and federal, state, and local requirements of the contract. This project is located on the APU unit, will require compete anti-ligature installations throughout and will progress while patients and staff reside on the unit. Contractor shall also be responsible for constant communication, obtaining permissions, permits, coordination with the Mental health staff, station facilities and safety representatives as necessary to meet the requirements of the contract. Stringent tool and materials control will be always enforced while working on the APU unit. Violations of tool control, material control, or unsafe patient construction activities, while working on the unit, may result in immediate cessation of work, safety standdowns up to and including removal from the unit or station, if deemed necessary. Safety will be strictly always enforced, no exceptions. The period of performance for design is 90 calendar days, and construction 120 calendar days from NTP.

SCOPE OF WORK:

2. GENERAL: Contractor shall provide engineering, design, commissioning, permitting, and construction services to meet the project objectives and requirements and to provide the required outcome in terms of overall quality, timeliness, and documentation. The Contractor shall be responsible for obtaining, monitoring, including but not limited to dedicated safety observers, and coordinating the services of all third-party Contractors performing other services on site and other entities as part of the contract to ensure the expected safety, quality, timely, and documented final product.

2.1 Normal work hours shall be 8:00AM to 4:00PM Monday through Friday except for Federal Holidays. If the Contractor desires to work on Saturday, Sunday, holidays, or outside the project site’s normal working days the contractor shall submit a written request for approval to the VA-COR at least seven (7) working days prior to the proposed start of such work. Due to the sensitive nature of the APU, no work will be allowed in the evening or overnight hours of the day.

2.2 Acceptable outages: This project should not require outages. Communicate with COR for any eventualities that may arise requiring outages.

2.3 DB Team must provide design period services to include drawings, specifications, and cost estimate reflecting specific tasks identified herein, in addition to on-site meetings with professional and administrative staff, site investigative work, review of supplementary documents. DB Team must provide competent design period services with staff and consultants adequately knowledgeable in healthcare design and construction, the various subordinate design disciplines, including but not limited to mechanical, electrical, plumbing, structural, fire protection, life safety, and other building/utility systems as required.

2.4 DB Team must develop plans from field verification on site and VA-provided supplementary drawings. DB Team is responsible for on-site verification of existing conditions affecting design which may include crawling, use of ladders, selective disruptive research (coordinate with VA), and discussions with engineering personnel. DB Team must consider adjacent systems and components (architectural as well as utility systems) to avoid unforeseen site condition construction change orders. DB Team must verify necessary building architectural and utility system components to provide for a full and complete design of replacement architectural elements and utility system components. This includes, but is not limited to items such as:

Coordination of requirements for Owner provided furniture scope.

Existing conditions verification – upgrades to meet current codes.

ABAA/ADA accessibility requirements Above ceiling verification – conflicts/interstitial space Verification of spare circuits on electrical panels Mechanical systems and distribution verification Plumbing verification (dead legs existing conditions) Fire sprinkler reconfigurations/change in pendant type/elevation to meet current code.

Fire alarm upgrades to current code Low Voltage access control capacity on existing panels Structural conflicts - through floor penetrations, etc.

2.5 DB Team must attend interim review project meetings on site with various VA staff. Record and provide meeting minutes within 36 hours to all attendees for review, comment, and concurrence. Incorporate appropriate comments, finalize the meeting minutes, and submit the final meeting minutes within one week of meetings.

2.6 VA design period services to include Design Development (DD), Construction Documents (CD). All submissions and related work for each design phase must conform to the requirements in this document and Program Guide (PG)-18-15.

2.7 Accomplish design using 1/4" scale plans to provide enough area on plans to clearly delineate required work. Use of 1/8" scale drawings may be utilized for hazardous materials, phasing, floor pattern, finish patterns, life safety and fire protection.

2.8 Provide a cost estimate for each design review meeting, subject to DB Team development as design progresses.

DESIGN DEVELOPMENT (DD):

Design Development includes initial work of DB Team required to represent the project as a set of drawings conveying the major intent of the project work. At this stage of project design, the physical layout of the new work should be shown.

CONSTRUCTION DOCUMENTS:

Submission Requirements: Refer to VA TIL for submission requirements.

Construction Documents submission must combine updates of all earlier sets of specifications and drawings and any other relevant project information (meetings, other discussions, etc.) making up a complete set of project documents. The quality of and level of detail of the CD submission should be such that no further or minimal changes are needed. The CD submission must incorporate all changes needed from earlier reviews and that a quick review must show all information is presented in clear and concise format. Discussion of Contractor staging/parking/exterior space usage, management of phasing activities such as control of dust and debris (infection control), etc. must occur during development of the CD submission. A/E must submit the following in a single package and at one time per date identified in contract Special Provisions:

A/E Provided Project Checklists: DB Team must provide a checklist of all submittals, certifications, tests, and inspections required per drawing and specification section. This checklist will show all products requiring submittals in the form of shop drawings, data sheets, manufacturer cut sheets, etc. as well as all other items shown as required submittal items including, but not limited to, reports, system evaluations, testing, operating and maintenance manuals, etc.

Provide 100% drawings in .pdf and specifications in Word electronic formats for construction period use by VA. The drawings must be combined into VA approved named files (not DB Team identified project numbers), generally no greater than 5-6mb size. A share-point site or email with hyperlink click and download such as Newforma is encouraged for ease of transfer.

COST ESTIMATE:

Provide construction cost estimates, submitted along with the design analysis, drawings, and specifications, for each design review submission required by the contract.

Cost estimates must be developed in strict conformance with VA’s Manual for Preparation of Cost Estimates & Related Documents for VA Facilities. https://www.cfm.va.gov/cost/index.asp.

PROJECT MANAGEMENT:

The Contractor shall exercise proven project management methodologies and practices during performance of this contract. The key contractor personnel listed in item F, below, shall attend a one-day kick-off meeting with the VA Contracting Officer, VA- COR, VA, and other VA invited attendees. The 65% design submittal must be approved by both local Station COR/engineers prior to the start of any demolition.

Project Manager. The Contractor shall have a project manager (PM) assigned during the project (reference spec section 01 45 00). The Contractor PM shall be responsible for all deliverables including maintaining the project schedule (reference spec section 01 32 16.16), price control and safety compliance. The Contractor PM shall assist VA in meeting the financial and operating goals of the project and adjust for potential deductive alternates to comply with approved budget.

Project Plan. The Project Plan and update shall include an overview of the VA project scope, objectives, and methodology, as well as a Microsoft Project outline of tasks (see Specification 01 32 16 Network Analysis). The project plan shall also include quality management procedures and a contactor team reporting organization chart. The updated Project Plan and schedule shall be approved by the VA-COR prior to start of construction.

Contractor Quality Control Plan (QCP) shall be in accordance with specification sections 01 45 00 Quality Control Plan Requirements and 01 45 29 Testing Lab. Note the Contractor’s Quality Control System Manager and specialized assisting personnel qualification requirements.

Commissioning Plan shall be written to assist the Commissioning Agent hired by the VA to accomplish the goals stated in the U.S. Department of Veterans Affairs Whole Building Commissioning Process Manual. The VA’s Commissioning agent shall establish acceptance Criteria for the project that are clear and measurable and provide a clearly defined methodology for establishing substantial completion and final acceptance of the project. Commissioning, at every stage of a project, is a collaborative effort between all parties to the construction project.

Accident Prevention Plan. The Contractor shall submit an Accident Prevention Plan to the VA-COR for review and approval, in accordance with Specification Section 01 35 16 Safety.

Security Plan. The contractor shall submit a Security plan for VA-COR approval that meets the requirements described in Specification 01 00 00 General Conditions.

Key Personnel. The following individuals have been designated as key personnel under the contract:

· Overall Project Manager – To be completed at award. Architect Design Project Manager – To be completed at award.

· Architect Engineer Field representative – To be completed at award. Construction Project Manager – To be completed at award.

· Project Site Construction Superintendent - To be completed at award. Trainer/Instructors – To be completed at award, if required.

· The Contractor agrees that such personnel shall not be removed, diverted, or replaced from the contract without prior written approval from the Contracting Officer. Any personnel the Vendor offers as substitutes shall have abilities and qualifications equal to or better than the Key Personnel that is being replaced. All Requests for substitutions in personnel shall be submitted through the VA COR to the Contracting Officer at least 30 days prior to making any change in Key Personnel. The request shall be in writing, providing an explanation of the circumstances necessitating the proposed substitution and contain a complete resume for the proposed substitute with any change to the labor rate/firm fixed price specified in the contract. The Contracting Officer shall evaluate such requests and notify the contractor in writing of approval or disapproval within 10 business days of receipt of the request.

ICRA. Level IV is required for this project.

ENGINEERING:

Sample list of reference specs that contractor must follow:

01 00 00

General Requirements 2020-03

01 32 16.16
Network Analysis Schedules (Design-Build Only)
2020-03
01 33 23
Shop Drawings, Product Data, and Samples
2017-05
01 35 26
Safety Requirements
2020-07
01 42 19
Reference Standards
2020-11
01 45 00
Quality Control
2020-05
01 45 29
Testing Laboratory Services
2018-11
01 45 35
Special Inspections
2019-03
01 57 19
Temporary Environmental Controls
01 58 16
Temporary Interior Signage
2015-07
01 74 19
Construction Waste Management
2013-09
01 81 13
Sustainable Construction Requirements
2017-10
01 91 00
General Commissioning Requirements
2015-10
02 21 13
Site Surveys
2016-08
02 41 00
Demolition
2017-08
02 65 00
Underground Storage Tank Removal
2016-08
02 82 11
Traditional Asbestos Abatement
2019-04
02 82 13.13
Glove bag Asbestos Abatement
2015-09
02 82 13.19
Asbestos Floor Tile and Mastic Abatement
2015-09
02 82 13.21
Asbestos Roofing Abatement
2015-09
02 82 13.31
Asbestos Transite Abatement
2015-09
02 82 13.41
Asbestos Abatement for Total Demolition Project
2015-04
02 83 33.13
Lead-Based Paint Removal and Disposal
2016-08

· Full set of drawings and specs in accordance with PG-18-15

· Narrative providing documentation that design/build team is complying with the requirements.

· Load analysis – notes about structural member sizing, if required.

· Construction documents must be approved by VA prior to continuing into construction.

· PG-18-15

WARRANTY:

The contractor shall provide a warranty. All warranty information, including item description, warranty start date, warranty ending date, and contact information of the warranty shall be prominently identified at the beginning of the O&M Manual. All equipment that is reused will be covered under warranty by the contractor for the 12-month period after acceptance.

The contractor shall respond to warranty support within a maximum of twenty-four (24) business hours of written VA Contracting Officer/VA-COR requests.

The contractor shall correct defects within a maximum of five (5) business days after approval of the VA-COR.

COMMISSIONING AND VERIFICATION:

Intent: Verify that the intended design as reflected in the contract documents has been achieved.

Contractor shall work cooperatively with VA’s Commissioning Agent so that a full range of checks and tests can be carried out to determine if all components, subsystems, systems, and interfaces between systems function in accordance with the design intent, as identified in the contract documents. In this context, “function” includes all modes of operations, and all specified responses to abnormal emergency conditions, if applicable.

ACCEPTANCE:

For the purposes of Warranty and payment for the work performed at a location, government “Acceptance” shall be provided by the VA upon the completion of all the following:

· The Contractor has demonstrated/ verified that the operational function of installed components as intended at commissioning. All punch list items identified during the commissioning have been resolved.

· The Contractor has provided O&M manuals.

· The Contractor has provided Record drawings.

CONFIDENTIALITY AND NONDISCLOSURE:

· The preliminary and final deliverables and all associated working papers, application source code, and other material deemed relevant by the VA which has been generated by the contractor in the performance of this Order are the exclusive property of the U.S. Government and shall be submitted to the VA-COR at the conclusion of the contract.

· The Contracting Officer shall be the sole authorized official to release verbally or in writing, any data, the draft deliverables, the final deliverables, or any other written or printed materials pertaining to this contract. No information shall be released by the contractor. Any request for information relating to this contract presented to the contractor shall be submitted to the CO for response.

· Press releases, marketing material or any other printed or electronic documentation related to this project, shall not be publicized without the written approval of the CO.

· To the extent that the work under this contract requires that the contractor be given access to proprietary business, technical or financial information belonging to the Government or other companies, the contractor shall treat such information as proprietary business sensitive and agrees not to appropriate such information to its own use or to disclose such information to third parties unless specifically authorized by the CO in writing. A mutually agreed to agreement for exchange of sensitive information or nondisclosure agreement may be required.

SPECIAL PROVISIONS FOR CONSTRUCTION DOCUMENTS:

DB Team is responsible for professional quality and technical accuracy in providing VA with documents. Services include but are not necessarily limited to:

1. Contract administration

2. Structural design documents and calculations for seismic design reinforcement in detail of construction documents including all structural plans, elevations, sections, details, schedules, calculations to size all structural components.

3. Electrical design documents in detail of construction documents including all plans, elevations, sections, details, diagrams, schedules, showing power distribution systems, lighting, and signal systems.

4. Cost estimates at each review submittal phase showing detail quantities. Advise VA at earliest opportunity when project is over budget. No provision will occur for additional expense for redesign in later reviews.

5. Specifications for all sections of the work utilizing VA Master Specifications from website. Coordinate specs and edit for project application.

6. Presentation and review submissions. Meetings with VA representatives, and field technical personnel.

7. Project phasing must be developed to coordinate work with other construction activities, and to minimize disruption of normal operations of VA.

8. Quality Assurance and Quality Control (QA/QC). Develop and execute and demonstrate to VA the project plans and specifications have gone through QA/QC review with all disciplines and partners.

DRAWINGS:

Drawings must be based on standard VA guidelines. Drawings must be normal in plan view, at a scale where work required is clear, legible, and easy to interpret.

All original drawings must be based on standard VA guidelines. Drawings must be done in plan view at a minimum scale of 1/4" = 1'. Details must have a minimum scale of 3/4" = 1'-0", and if possible, larger. Drawings must be independent for demolition, architectural, mechanical, electrical, structural, civil, etc., and must show, on separate views, required demolition and reconstruction details for each function. Drawings must be prepared using AutoCAD 2018 or newer and plotted on 30" x 42” sheets.

Final drawings must bear VA title block and nomenclature. Drawings must be on the same type and size sheets. All views, elevations, sections, etc., must be complete to ensure total contractor compliance without any ambiguities, or subject to various interpretations. All drawings are required to show existing conditions as of the date of the design submission.

All sheets of drawings must contain A/E official stamp with professional seal and signature along with the name and address of the firm.

SPECIFICATIONS:

Specifications must be based on VA Master Construction Specifications. Specifications must be prepared and submitted individually in latest version of Microsoft Word. DB Team must review and edit applicable sections of the specifications for completeness, relevance, and correctness. The intent is to provide specifications suitable for the project intention and detailed enough to enable the contractor to perform the work in the simplest and practical manner. Where a particular item is referenced in the specifications, consult with Engineering for direction on which item to select. The contractor must not be provided options or choices to make selections but must be provided the specific selection. DB Team must obtain the name and type of specialty materials and equipment required for use on the project. All items shown in the specifications must, if named specifically by brand or trade name, carry the statement "or approved equal" with salient characteristics listed. Exception may occur due to previously purchased or installed items interacting with new construction. In this situation, items used should be the same as existing or matched accordingly. Information on such items must be provided by VA.

Construction tolerances must be specified in detail in all specification sections or identified on plans. Legal precedence of "specifications over drawings" must not be used to resolve design ambiguities between drawings and specifications, or to justify omission of drawings or notes required for clarity. Contradiction, ambiguity, or statements subject to various interpretations, must be corrected to reflect a single clear intention.

DESIGN-BUILD TEAM CONTRACT CLOSE-OUT:

DB Team must submit the record drawings showing any changes or modifications to the Bid Documents reflected on the hard-copy set of “as-builts”; Drawings must be individually marked “Record Drawing” and submitted in a single package as follows.

1. Drawings in AutoCAD (DWG) format of the entire project on CD.

2. All drawing objects must be removed. (e.g., Revit, Desktop, etc.).

3. All drawings must plot properly using the NCS.ctb plot file.

4. Drawings must represent final project with all demolished and/or removed items deleted from the .dwg files.

5. All drawings must be on the VA Cad Standard Layering convention.

6. Drawings in (PDF) format of the entire project in addition to 1 set of full size 30 x 42" drawings.

END OF STATEMENT OF WORK

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

PART I - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS

PART I/SECTION A – REQUEST FOR PROPOSAL

I.1A JOINT VENTURES

If submitting an offer as a joint venture as defined by P.L. 109-461 AND Department of Veterans Affairs I.L. 049-06-4. Certified SDVOSB/VOSB listed in the SBA certification database at https://veterans.certify.sba.gov/ (see 13 CFR 128). A joint venture may be considered eligible if it meets the requirements in 13 CFR part 128, and the managing joint venture partner makes the representations under VAAR 819.7003 paragraph (b). An offeror must provide a copy of the joint venture agreement specific to the project that is consistent with the percentage of required work and net proceed. Additionally, the offeror must provide a breakdown or labor of which is to be performed by the SDVOSB firm and that which is performed by the small business joint venture firm and that which is sub-contracted. All Joint Ventures will be required to be registered and verified as an entity in VETCERT.

I.2A SELECTION PROCEDURES

This acquisition will utilize the two-phase design-build selection procedures in accordance with FAR 36.301. Phase I shall include the scope of work, evaluation factors as stated in FAR 36.303-1, and Phase II evaluation factors. A maximum number of five (5) offerors will proceed to Phase II. Once the Contracting Officer selects the most highly qualified offerors, they will be asked to submit Phase II proposals. Phase II of the solicitation shall be prepared in accordance with FAR Part 15, with evaluation criteria developed in accordance with FAR 15.304. The Government will award a contract resulting from this solicitation to the offeror whose offer conforming to the solicitation is determined by the Source Selection Authority to provide the best overall value to the Government. It is the intent of the Government to award without discussions; however, the Government reserves the right to have discussions if such are needed.

In addition to the general standards of responsibility found at FAR 9.104-1, in accordance with FAR 9.104-2, the special standards of responsibility described below apply to this procurement. Offerors who fail to meet any special standard of responsibility may not be eligible to receive contract award.

I.3A PRE-PROPOSAL SITE VISIT

A pre-proposal site visit will be conducted in Phase II. The most highly rated firms selected to proceed to Phase II will be invited to attend the pre-proposal site visit. The Contracting Officer will establish the date and time and notify Phase II offerors in writing. See FAR Clause 52.236-3, Site Investigation and Conditions Affecting the Work, and FAR Provision 52.236-27, Site Visit (Construction) of this solicitation.

I.4 Selection Criteria I.4.1 General: Phase I proposals will be evaluated to determine the most highly qualified offerors to advance to Phase II. Factors 1 and 2 are of equal importance when selecting the most highly qualified offerors in the Phase I evaluation. Phase II Proposals will be evaluated, and award will be made based on both price and technical considerations most advantageous to the Government per FAR Part 15.101(a), Tradeoff Process. The Government may consider award to other than the lowest priced offeror or other than the highest technically rated offeror if it is in the best interest of the Government.

I.4.2 Offerors who are selected to move on to Phase II will be requested to submit a Phase II proposal. Factors 3-4 will be evaluated in Phase II and are of equal value. The non-price factors, when combined, are significantly more important than price. Offers will be evaluated using the following evaluation factors:

Phase I:

Factor 1 – Past Performance Factor 2 – Technical Approach

Phase II:

Factor 3 – Technical Solution Factor 4 – Schedule Factor 5 – Price

In addition to the general standards of responsibility found at FAR 9.104-1, in accordance with FAR 9.104-2, the special standards of responsibility described below apply to this procurement. Offerors are to submit documentation with their Phase I proposal.

Offerors who fail to meet any special standard of responsibility may not be eligible to receive contract award.

Solicitation Submittal Requirements:

The Offeror shall submit the following information: (For a partnership or joint venture, the following submittal requirements are required for each Contractor who is part of the partnership or joint venture and for the entity itself. EMR shall not be submitted for subcontractors.)

1. OSHA or EPA Violation(s):

Offerors shall provide Summary of Work-Related Injuries and Illnesses, affirming that the Offeror has no more than three serious, or one repeat, or one willful OSHA or EPA violation(s) in the past 3 years.

2. Experience Modification Rate (EMR):

Offerors shall provide documentation to show that the offeror has an Experience Modification Rate (EMR) of equal to or less than 1.0.

Factor 1-Past Performance

(a) Aspects of Past Performance Evaluation. The past performance evaluation is an assessment based on the offeror’s record of relevant and recent past performance information that pertain to the products and/or services outlined in the solicitation requirements. There are two aspects of the past performance evaluation.

(1) The first is to evaluate whether the offeror’s past performance is relevant or not relevant to the effort to be acquired. The criteria to establish what is relevant is unique to each source selection.
(2) The second aspect of the past performance evaluation is to determine how well the contractor performed on the contracts. The past performance evaluation performed in support of a current source selection does not establish, create, or change the existing record and history of the offeror’s past performance on past contracts; rather, the past performance evaluation process gathers information from customers on how well the offeror performed those past contracts. In addition, the Government reserves the right to obtain information for use in the evaluation of past performance from all sources including sources outside of the Government. Other sources may include, but are not limited to, past performance information retrieved through the Past Performance Information Retrieval System (PPIRS) using all CAGE/DUNS numbers of Contractors who are part of a partnership or joint venture identified in the Offeror’s proposal, inquiries of owner representative(s), Federal Awardee Performance, and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by the Offeror.

(b) Source Selection Evaluation Board (SSEB) members will review past performance information to determine the quality and usefulness as it applies to the performance confidence assessment.

Adverse past performance is defined as past performance information that supports a less than satisfactory rating on any evaluation element or any unfavorable comments received from sources without a formal rating system.

(a) Solicitation Submittal Requirements:

Offerors shall submit up to five (5) recent and relevant projects where the offeror performed Architecture and Engineering services, and up to five (5) recent and relevant construction projects as defined below. If a completed Contractor Performance Assessment Reporting System (CPARS) evaluation is available, it shall be submitted. The Government will evaluate past performance based upon sources available to the contracting officer that may include Past Performance Information Retrieval System (PPIRS), Federal Awardee Performance and Integrity Information System (FAPIIS) and Electronic Subcontract Reporting System (eSRS). IF THERE IS NOT A PAST PERFORMANCE EVALUATION IN PPIRS or FAPPIIS, then the offeror shall submit Past Performance Questionnaires (PPQ) for each project. Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other RFPs. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation. If the offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the offeror shall complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the respective project(s). An incomplete questionnaire will not be considered. The Government may make reasonable attempts to contact the client noted for that project(s) to obtain the PPQ information. However, offerors should follow-up with clients/references to help ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government’s point of contact, Jason.Rankin@va.gov.

Recency – a recent project is defined as being completed within five years of the due date of this solicitation.

Relevant – includes performance of efforts involving general construction and renovation within an active medical facility that are similar or greater in scope, magnitude, and complexity of the effort described in this solicitation. Construction project(s) shall have a minimum value of $500,000, AE project(s) shall have a minimum value of $50,000.

The offeror may utilize experience of a design subcontractor to demonstrate design experience under this evaluation factor. The Offer must provide a supporting joint venture agreement, partnership agreement, teaming agreement, or letter of commitment and an explanation of the involvement for the design subcontractor.

Offerors are cautioned to submit enough information in the format specified in the solicitation. Offerors may be asked to clarify certain aspects of their proposal (for example, the relevance of past performance information) or respond to adverse past performance information to which the offeror has not previously had an opportunity to respond. Adverse past performance is defined as past performance information that supports a less than satisfactory rating on any evaluation element or any unfavorable comments received from sources without a formal rating system. Communication conducted to resolve minor or clerical errors will not constitute discussions and the contracting officer reserves the right to award a contract without the opportunity for proposal revision.

(b) – Basis of Evaluation:

The purpose of the past performance evaluation is to allow the government to assess the offeror’s ability to perform the effort described in this RFP, based on the offeror’s demonstrated past performance. Past performance regarding predecessor companies, key personnel who have relevant experience, or sub-contractors that will perform major or critical aspects of the requirement will not be considered as highly as past performance information for the principal offeror. Design Build Projects will be rated more favorably. Offerors with no relevant past or present performance history or the offeror’s performance record is so limited that no confidence assessment rating can be reasonably assigned shall receive the rating "Unknown Confidence," meaning the rating is treated neither favorably nor unfavorably.

Factor 2 – Technical Approach:

(a) Solicitation Submittal Requirements:

Provide a brief narrative (page limitation: two (2) page (in 12-point Times New Roman font) for brief narrative) describing the offeror’s method to manage the project to achieve design and construction objectives as described in the RFP. If the page limits are exceeded, the pages more than the limit will not be read or considered. Include at minimum all aspects covered in the scope of work. The following shall be included in the narrative:

1) Design Approach:

· Describe the techniques and methods for completing the design within an Acute Psychiatric Unit and Sally-Port.

2) Construction Approach:

· Describe the techniques and methods for construction including coordination with the design packages, projected timelines, and all aspects of the phasing.

· Describe your approach to coordinate the design and construction teams.

(b) Basis of Evaluation:

The basis of evaluation will include reviewing the offeror’s proposed technical approach for this design-build project as defined in the solicitation submittal requirements. The assessment of the offeror’s method to manage the project shall be used as a means of evaluating the offeror’s ability to successfully meet the requirements of the solicitation.

Factor 3 – Technical Solution

1. Solicitation Submittal Requirements:

Provide a narrative describing the technical solution to the project that meets the requirements of the RFP. Include the following:

· Describe your approach to working in the acute psychiatric unit to maintain VA standards for construction within the Technical Information Library (TIL).