S05 - RFIs Site Visit- Responses - ICU Endo Window Replacement - 436-24-120.docx

DOCX document 20 KB Posted

Attached to
Z2DA--ICU-ENDO Window Replacement (436-24-120) Federal contract opportunity
Solicitation number
36C25924R0048
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 19

About this file

This document provides questions and answers related to a solicitation for ICU and endoscopy window replacement at a Department of Veterans Affairs medical center. The solicitation seeks a general contractor to remove 15 existing casement windows on the third floor of Building 154 and replace them with fixed aluminum windows, along with installing roller shades and completing related masonry work. One window opening will be infilled with brick. The work must be completed over a 90-day period of performance in accordance with infection control requirements for construction in occupied healthcare facilities. Questions addressed scheduling constraints, scope clarification, and infection control measures.

View the file

Other files for this federal contract opportunity

Other files attached to Z2DA--ICU-ENDO Window Replacement (436-24-120), newest first.
File Type Posted
S04 - Site Visit Log Attendance - 14 Feb 24_FE.pdf PDF
S04 - Site Visit Meeting Doc_FE.docx DOCX document
36C25924R0048 0003.docx DOCX document
S02 - 2_436.436-05-102.154.AE102.BUILDINGS 154 - FIRST FLOOR PLAN WINDOW DETAILS.pdf PDF
36C25924R0048 0002.docx DOCX document
36C25924R0048 0001.docx DOCX document
PCRA - 436-24-120 Bldg 154 ICU-ENDO Window Replacement.pdf PDF
SPECS BUILDING ICU-ENDO WINDOW REPLACEMENT.pdf PDF
DWG SCHEM ICU-ENDO 3rd Floor.pdf PDF
S02 - ICRA ICU-ENDO WINDOW REPLACEMENT.docx DOCX document
SPECS 040531 DIVISION 04 _ MASONRY - TUCK POINTING.docx DOCX document
SPECS 040513 DIVISION 04 _ MASONRY - MORTARING.docx DOCX document
36C25924R0048.docx DOCX document
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF VETERANS AFFAIRS VHA Network Contracting Office 19 Rocky Mountain Acquisition Center 6162 South Willow Drive, Suite 300 Greenwood Village, CO 80111

CONTRACTOR Q&A’s

ICU Endo Window Replacement 436-24-120 Solicitation 36C25924R0048

Question No. 1: Project documents show no windows to be replaced in Procedure #2. Please confirm there is (1) window added to scope of work for that room. Please confirm an additional window is required to be replaced.

Answer No. 1: Yes, the window in the plan view southwest corner of Procedure Room #2 (363A) is required to be replaced as part of this project. This window is included in the count of eight called out in the scope of work.

Question No. 2: Please confirm if work can be done during normal business hours.

Answer No. 2: The windows in the endoscopy area will have to be coordinated with the VA for afterhours and weekend work. ICRA measures will have to be put into place at the start of each work shift and removed at the end of each work shift. After contractor cleanup is complete, VA housekeeping will need to be notified in order to perform terminal clean in this area. All clean-up will need to be complete and ready for patient care prior to start of business on the morning following.

Question No. 3: Specifications include specification 08 56 53. Please confirm blast resistant windows and frames are not required.

Answer No. 3: Windows shall be provided as described in the scope of work Section III. Paragraph A. General Contractor Requirements. So long as these window manufacture standards are met, blast analysis based on W1 and GP2 are not required given the scope of this project.

Question No. 4: Due to the locations of the replacement windows; Are there any other requirements for window treatments not shown in project documents? Are the shades to match previous project on 4th floor?

Answer No. 4: There are no requirements for any window treatments other than shades to be provided. Shades to match previous work except that two shades, one each, in procedure rooms #1 and #1 will be blackout shades of same manufacturer and style as the balance of the shades. Shades to match recent projects as follows:

Provide window shade:

SWF Contract Crosshatch R; R300 – 3% open Color: C8210 White/Cream Fire Classification: NFPA 701 Bacterial and Fungal Resistance: ASTM G21 & ASTM E2180

Provide blackout window shade:

SWF Contract Blackout Conceal Color: C2612 Wheat Fire Classification: NFPA 701 Bacterial and Fungal Resistance: ASTM G21 & ASTM E2180

Question No. 5: Can work be completed during normal business hours (i.e. Mon-Fri 7:00 AM – 5:00 PM)?

Answer No. 5: See Answer No. 2.

Question No. 6: Please indicate if contractor will be allowed to work in multiple rooms (minimum two recommended to meet infection control requirements).

Answer No. 6: In the ICU, ability to work in multiple rooms will be dependent on patient census at the time work is scheduled. In the endoscopy area, refer to Answer No. 2. Work schedule should reflect an appropriate number of rooms/windows per work shift to meet these requirements.

Question No. 7: Please confirm scope in Endoscopy Procedure Room #2 (363A). During the site walk, it was noted that the window called to be infilled with brick has already been covered with sheetrock. Does the other existing window in 363A need to be replaced? Does this window still need to be infilled with brick?

Answer No. 7: The drawing provided shows eight windows in endoscopy with seven of them marked for replacement. The scope of work statement is that there are eight windows in endoscopy to remove. This is count is correct. Seven endoscopy windows to be removed and replaced with new windows as described in the specifications and SOW. One window,as indicated on the drawing, to be removed and infilled with brick as described in the specifications. Access to this window opening may require partial removal of finished gypsum wallboard to properly weather seal the brick infill. If so, then the work will also include patching and painting to restore the wall to pre-construction condition.

Question No. 8: Do all shared interior walls in ICU & endoscopy go to deck?

Answer No. 8: As built drawings from previous projects would indicate that interior walls continuing to deck above should be the assumed existing condition. Field verification was not done.

Question No. 9: Will the ICU be shut down for the duration of the project?

Answer No. 9: No. Per the solicitation SOW Section III Paragraph A, “The project will take place in an occupied healthcare facility and the activities will require construction to be phased in such a way as to minimize impact to staff and patients.”

Question No. 10: Will endoscopy be shut down for the duration of the project?

Answer No. 10: No. Per the solicitation SOW Section III Paragraph A, “The project will take place in an occupied healthcare facility and the activities will require construction to be phased in such a way as to minimize impact to staff and patients.”

Question No. 11: Per ICRA, HEPA filtered air is required to be exhausted outside. Please confirm HEPA filtered air must be exhausted outside for this project. Project scope includes very minimal dust producing activities. Requiring HEPA filtered air to be exhausted outside will significantly increase project duration, cost, & impact to patients and staff. Recommend waiving HEPA filtered outside exhaust requirement for this project.

Answer No. 11: At this time, the facility Quality Management, Patient Safety, and Infection Prevention teams are not receptive to applying for waivers and are interpreting the ICRA requirements in favor of the most conservative measures for construction controls. When bidding, assume that the contractor will be held to providing all ICRA controls described in the provided document.

Question No. 12: Can the site superintendent simultaneously fulfill the CQCM and SSHO duties/roles (i.e. one person performs all three roles)?

Answer No. 12: If the contractor provides a full-time site superintendent who is dedicated to this project (i.e., NOT involved in any way with any other projects at this VA Facility or any other location) and is capable of being on site at all times that any work is being performed on this project, then these three roles can be performed by one individual. If there is any question that any one of these conditions can be met fully for the entirety of the project period of performance, then the contractor must provide at least two part time persons to share in fulfilling these three roles.

File details come from the government source that posted it. Updated .