SOW Replace Propane Tanks 660-22-108 Revision1.docx

DOCX document 526 KB Posted

Attached to
Z2DA--660-22-108 Replace Propane Tanks Federal contract opportunity
Solicitation number
36C25924R0013
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 19

About this file

This solicitation and statement of work are for a construction contract to replace two underground propane tanks at the George E. Wahlen Department of Veterans Affairs Medical Center in Salt Lake City, Utah. The scope of work includes demolishing and removing two existing 30,000 gallon propane tanks, installing two new tanks with associated concrete pads and piping, upgrading the cathodic protection system, repaving surfaces, and other site work. Contractors must provide designs, equipment, labor, materials and supervision to excavate the existing tanks, install shoring, test the new tanks, backfill with sand and flowable fill, reconnect piping, and complete other tasks in accordance with specifications. The period of performance is 120 days. Subcontractors must designate competent persons and the prime contractor a site safety and health officer to oversee safety programs.

View the file

Other files for this federal contract opportunity

Other files attached to Z2DA--660-22-108 Replace Propane Tanks, newest first.
File Type Posted
36C25924R0013 0006.docx DOCX document
sds-odorized-propane.pdf PDF
SPECS Replace Propane Tanks Project REV1.pdf PDF
Solicitation QA 1-24-2024.docx DOCX document
36C25924R0013 0005.docx DOCX document
36C25924R0013 0004.docx DOCX document
SITE VISIT ATTENDANCE 12.13.pdf PDF
S04 - Site Visit Meeting Doc 12.13.docx DOCX document
36C25924R0013 0003.docx DOCX document
36C25924R0013 0002.docx DOCX document
36C25924R0013 0001.docx DOCX document
S04 - Site Visit Meeting Doc.docx DOCX document
Site Visit Attendance.pdf PDF
Past Performance Questionnaire.docx DOCX document
S22- 852.219-75 LOS Certificaiton.docx DOCX document
ICRA 660-22-108 Replace Propane Tanks.docx DOCX document
36C25924R0013_1.docx DOCX document
SPECS Replace Propane Tanks Project 660-22-108.pdf PDF
Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VA Salt Lake City Health Care System Replace Propane Tanks Project Date: 1/24/2024

STATEMENT OF WORK

CONSTRUCTION SERVICES

Project Title: Replace Propane Tanks Date: 24 January 2024 Location: Bldg. 38 Propane Yard, Salt Lake City, UT, George E. Wahlen, Depart. of Veteran Affairs Medical Center

I. SCOPE OF WORK:

A. Furnish all necessary design/engineering, services, equipment, labor, materials, supervision, and tools to perform construction services for the Project, entitled Replace Propane Tanks, located at 500 Foothill Drive, Salt Lake City, UT 84148 on the George E. Wahlen Department of Veterans Affairs Medical Center campus.

The project is located behind Bldg. 38 in the fenced in propane yard. There are three existing underground 30,000-gallon propane tanks. Two of the existing propane tanks shall be emptied, cleaned, removed, demolished, and replaced. The aboveground piping/pumps will need to be disconnected, and temporarily removed during demolition and installation of the two new propane tanks. The piping is on skids which will all need to be put back into place upon installation of the new underground propane tanks. When installing the new propane tanks, sand and flowable fill shall be used to backfill. The existing cathodic protection system is operational and shall be tied into the two new tanks. The contractor shall be careful as to not destroy the existing cathodic protection system during construction & excavation. The contractor shall be required to retrofit the existing cathodic protection system as needed for a properly working system with the propane tanks. The new propane tanks will require level sensors, and gas leak detectors, etc. The existing sensors should be evaluated, salvaged, and re-used on the new tanks, if possible. The contractor will need to remove a section of the surrounding fence to perform the work. The contractor shall replace the fence that was removed with an equal or better fence. During construction, the contractor shall provide a temporary construction area fence. The contractor shall follow all manufacturers guidelines in the installation of the new propane tanks. A lift plan will be needed and submitted to the COR for review & approval.

Contractor shall be responsible for filling the new 30,000 gallon tanks with propane. Contractor shall also be responsible for the following inspections prior to installation of the new tanks: subgrade/foundation testing, concrete testing, tank pressure testing, & holiday testing on tank coating.

A Storm Water Pollution Prevention Plan (SWPPP) permit is required to be provided to the COR and kept on-site. Regardless of project size or proximity to surface water, due to proximity to Red Butte Creek the Contractor shall file a Notice of Intent (NOI) and obtain coverage for the project under the Utah Pollutant Discharge Elimination System (UPDES) General Permit for Storm Water Discharge from Construction Activities (CGP). A “Low Erosivity Waiver (LEW) Certification” for this project is not acceptable. The Contractor shall provide a Storm Water Pollution Prevention Plan (SWPPP) prepared by a “qualified SWPPP writer”, as defined in the UPDES CGP. The Contractor shall provide a “qualified person” as defined in UPDES CGP to conduct weekly inspections of the project and provide weekly inspection reports to the COR. Any deficiencies noted during weekly inspections shall be verbally reported immediately to the COR and in writing within 2 hours. The Contractor shall install and maintain any erosion and sediment controls and pollution prevention Best Management Practices (BMPs) described in the SWPPP to prevent the discharge of pollutants to surface water. Upon completion of the project and approval from the COR, the Contractor shall file a Notice of Termination (NOT) with Utah DEQ to cease coverage under the UPDES CGP.

In addition, the Contractor shall have the existing propane and natural gas meter at Bldg. 6 calibrated. The Contractor shall insure that we are getting the proper LP & NG readings on the Hays Cleveland System.

The work shall be done during normal business hours of Monday – Friday 7:00 a.m. to 4:30 p.m. Any work outside these hours will require an advance written request from the contractor to the COR, and approval by the COR in writing. Requests shall be submitted a minimum of 1 week in advance.

Basic Outline of work:

A. Contractor shall provide all necessary design/engineering, equipment, labor, materials, supervision, and tools to excavate the two existing propane tanks that are in the propane yard. The contractor will be required to remove all excavated materials off campus for appropriate disposal.

B. The contractor will install OSHA approved and engineered shoring & trench box(s) to protect personnel and equipment.

C. The contractor shall bring in trained personnel to test the new tanks for structural integrity and to make sure the outer coating has not been degraded. The outer coating shall protect the Underground Storage Tank (UST) from moisture & corrosion and have a minimum of a 30-year warranty.

D. The contractor will be required to salvage the existing piping and pumps and reconnect to the new UST’s.

E. The contractor will be required to keep the backup fuel online to the boiler plant at all times in the wintertime, however, this will not be required if the work is done in the warmer months upon approval by the COR (Risk assessment will be done by the Government). The max down time at any point in this and the existing project is 4 hrs. Max.

F. The contractor shall construct a new approx. 16’ x 40’ x 1’ rebar (#4), 12-inch on center, both ways (2 layers) reinforced concrete pad for each tank to sit on. A rubber base shall be installed on top of the concrete pad.

G. After the contractor has full reports in regard to the tanks, he/she install existing cathodic protection and test wells and back fill the tank with appropriate sand fill (to cover a minimum of 2 ft. around the tank). Then Flowable Fill shall be designed & installed by the contractor.

H. The contractor will pour concrete pads around the piping hub and provide new 4” asphalt over the new tanks, to match existing asphalt thickness with a minimum of 3.5”.

I. The contractor will permanently install the piping and pumps. Replace any gaskets, and miscellaneous piping items that may need replaced.

The SOW & Drawings for this project constitute the project requirements, with details called out in one, and not in both shall be interpreted by the Contractor as though called out in both. The Contractor shall field verify all existing conditions, dimensions, equipment, etc. as needed to gain a full understanding of the project to deliver and execute a complete and quality project to the government.

The contractor shall adhere to NFPA 58, NFPA 54, along with all other required codes & standards. Use dielectric flanges to minimize corrosion. Any Electrical shall meet Class 1, Div II National Electric Code (NFPA 70), and be explosion proof. The new LPG vessel(s) shall be designed, constructed, and installed to ASME, Section VIII, Division I and NFPA 58 “Liquefied Petroleum Gas Code” underground stationary use. Minimum spacing between propane tanks shall be 5 feet. The propane tanks shall be 50 feet away from any building, or property line.

In regards to shoring, all excavation shall be OSHA approved. In addition, any bracing needed shall be approved by a Professional Engineer P.E. registered in the state of Utah.

The actual project demolition & new construction will need to take place while the 3rd propane tank is kept available and active for use to the VA for the boilers it feeds, if construction happens to be during the winter. The contractor shall work with the COR & VA Facilities Division to ensure that piping from the 3rd propane tank is kept intact or rerouted temporarily. The Contractor shall coordinate any utility outages with the COR, a minimum of 2 weeks in advance. The Contractor shall communicate through the COR, with the Facility Division Utilities Systems Operations Supervisor as needed. Thorough attention to keeping a secure site (temporary fencing) and keeping all items that could pose a self-harm risk or be used to hurt others must be always kept in locked construction site. Extra attention will be paid to working in a confined space; this extra focus should not result in slippage of adherence to general safety requirements. Any welding will require a Hot-Work permit. Any digging with require an Excavation Permit.

Contractor shall review all specifications and drawings and shall identify any issues to the contracting officer (CO), and COR before solicitation deadline. Contractor shall perform work as specified and shall adhere to Federal and State requirements, including standard practices for the industry and the State of Utah. The contractor shall meet the International Plumbing Code (IPC), and the National Electric Code (NFPA 70, NEC), NFPA 58, NFPA 70E, and all VA Specifications.

The contractor shall adhere to the following VA Specifications:

DIVISION 01 GENERAL REQUIREMENTS

01 00 00 General Requirements 01 33 23 Shop Drawings, Product Data, and Samples

01 35 26Safety Requirements
01 45 00Quality Control
01 45 35Special Inspections

DIVISION 02 – EXISTING CONDITIONS

02 21 13Site Surveys
02 41 00Demolition

02 65 00 Underground Storage Tank Removal

DIVISION 03 – CONCRETE

03 30 00Cast-in-Place Concrete
03 30 53(Short-Form) Cast-in-Place Concrete

DIVISION 13 - SPECIAL CONSTRUCTION

13 05 41 Seismic Restraint Requirements for Non-Structural Components

DIVISION 22 – PLUMBING

22 05 11Common Work Results for Plumbing
22 05 19Meters and Gages for Plumbing Piping
22 05 23General-Duty Valves for Plumbing Piping

DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 10 00Facility Fuel Systems
23 11 23Facility Natural-Gas Piping

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 26 05 26 Grounding and Bonding for Electrical Systems 26 05 41 Underground Electrical Construction 26 42 00 Cathodic Protection

DIVISION 31 – EARTHWORK

31 20 00 Earthwork 31 23 23.33 Flowable Fill

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 05 23Cement and Concrete for Exterior Improvements
32 12 16Asphalt Paving
32 31 13Chain Link Fences and Gates

The Prime Contractor shall designate a minimum of one Site Safety and Health Officer (SSHO) to administer the contractor’s safety program and government-accepted Accident Prevention Plan. Each subcontractor shall designate a minimum of one Competent Person (CP) in compliance with 29 CFR 1926.20 (b)(2) that will be identified as a CP to administer their individual safety programs. Also, The SSHO or an equally-qualified designated representative/alternative will maintain a presence on the site during construction operations in accordance with FAR Clause 52.236-6: Superintendence by the Contractor. CPs will maintain presence during their construction activities in accordance with above mentioned clause. A listing of the designated SSHO and all known CPs shall be submitted prior to the start of work as part of the APP with the training documentation and/or AHA.

In order to comply with above, please do NOT bid for same SSHO that would or would potentially cover multiple projects on the campus.

B. The scope of work includes, but is not limited to, performing construction including but not limited to civil/structural, electrical, mechanical, plumbing, site investigation, and testing/special inspection services.

The contractor shall review all drawings, with the assigned VA COR (Contracting Officer’s Representative), to verify the project area/s and what the project entails. The contractor shall be required to lead meetings to discuss progress and problems with the VA staff. The contractor shall be required to take meeting minutes and distribute to the VA for approval and as documentation of what was covered within the meeting.

The contractor shall show a detailed containment plan for infection control and hazmat control. This plan shall be detailed showing locations and what infection and hazmat control requirements are to be used for each area. Safety and infection control requirements shall be enforced for the duration of the project, regardless of any disruptions, to protect patients, visitors, VA staff, and contractors/subcontractors. The contractor shall be responsible for the site during construction and shall ensure all contractor employees and subcontractors always adhere to all safety and infection control requirements.

The contractor shall supply submittals on all designs/engineering, materials, equipment, and tests to the COR, for approval/disapproval prior to procuring or installing and new equipment. The contractor shall also provide final as-builts, O&M manuals, Tests (pressure, operational, leak test, disinfection, flushing, startup), and final test with the VA Utility technicians, and COR present. Also include 4 hours of training for the VA to maintain and operate. Final As-Built drawings shall be in AutoCAD and PDF formats electronically.

C. SUBMITTALS

· SWPPP

i. Notice of Intent (NOI) filed with Utah Division of Water Quality (UDWQ)

ii. Storm Water Pollution Prevention Plan (SWPPP) prepared by a “qualified SWPPP writer”, as defined in UPDES GCP Section 7.2

iii. Weekly Site Inspection Reports completed by “qualified persons” as defined in the UPDES GCP Section 4.1(a).

iv. Any SWPPP Deficiency Resolution Reports

v. Notice of Termination (NOT) filed with UDWQ.

· PROPANE TANKS

· ASPHALT

· CONCRETE

· PIPE/FLANGES/GASKETS, ETC.

· SENSORS

· CATHODIC PROTECTION EQUIPMENT

· DESIGNS

· CUT SHEETS

· ENGINEERED SHORING

· OSHA COMPLIANCE

· O&M

· AS BUILT / RECORD DRAWINGS

Figure 1: Existing Propane Yard

Figure 2: New Propane Tank (Conceptual), for reference only

Figure 3: Existing Site Plan

Figure 4: Tank Install Detail

Figure 5: Piping and Manway Access Portal Detail

Figure 6: Typical Pavement Replacement Section Detail

Total Period of Performance: 120 Days

VA INFORMATION AND INFORMATION SYSTEM SECURITY/PRIVACY LANGUAGE

VA INFORMATION CUSTODIAL LANGUAGE:

a. If VA determines that the contractor has violated any of the information confidentiality, privacy, and security provisions of the contract, it shall be sufficient grounds for VA to withhold payment to the contractor or third party or terminate the contract for default or terminate for cause under Federal Acquisition Regulation (FAR) part 12.

BADGING:

a. All employees of general contractor and subcontractors shall comply with VA security management program and obtain temporary VA badges. This will require fingerprinting and background checks of each individual. The employees of the general contractor will obtain permission of the VA Human Resources, be identified by project and employer, and restricted from unauthorized access.

TRAINING:

a. All contractor employees and subcontractor employees requiring access to VA information and VA information systems shall complete VA Privacy and Information Security Awareness and Rules of Behavior Training.

***************End of Construction Services SOW****************