S04 - Site Visit Meeting Doc.docx

DOCX document 19 KB Posted

Attached to
Z2DA--660-22-108 Replace Propane Tanks Federal contract opportunity
Solicitation number
36C25924R0013
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 19

About this file

This document outlines requirements for a pre-bid meeting and site visit for solicitation number 36C25924R0013 to replace propane tanks at the Salt Lake City VA Medical Center. The contractor will be responsible for providing all labor, materials, equipment, and supervision to replace the propane tanks in accordance with the statement of work and associated documents, handling all debris and waste in compliance with applicable regulations. The pre-bid meeting is not mandatory but any questions from prospective bidders during the site visit must be submitted in writing to the contracting officer. Questions are due by November 20, 2023 before 1:00 PM MT and bids are due December 6, 2023 by 11:00 AM MT via email. Attendees must stay together as a group during the site visit and leave once complete. The construction cost is estimated between $1,000,000 and $2,000,000 and bid guarantees, payment and performance bonds, OSHA ratings, and a signed Davis-Bacon wage compliance clause are required with submissions. The contractor must begin within 10 days of notice to proceed and complete within 120 days.

View the file

Other files for this federal contract opportunity

Other files attached to Z2DA--660-22-108 Replace Propane Tanks, newest first.
File Type Posted
SOW Replace Propane Tanks 660-22-108 Revision1.docx DOCX document
36C25924R0013 0006.docx DOCX document
sds-odorized-propane.pdf PDF
SPECS Replace Propane Tanks Project REV1.pdf PDF
Solicitation QA 1-24-2024.docx DOCX document
36C25924R0013 0005.docx DOCX document
36C25924R0013 0004.docx DOCX document
S04 - Site Visit Meeting Doc 12.13.docx DOCX document
36C25924R0013 0003.docx DOCX document
SITE VISIT ATTENDANCE 12.13.pdf PDF
36C25924R0013 0002.docx DOCX document
Site Visit Attendance.pdf PDF
36C25924R0013 0001.docx DOCX document
SPECS Replace Propane Tanks Project 660-22-108.pdf PDF
Past Performance Questionnaire.docx DOCX document
S22- 852.219-75 LOS Certificaiton.docx DOCX document
ICRA 660-22-108 Replace Propane Tanks.docx DOCX document
36C25924R0013_1.docx DOCX document
Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pre-Bid Meeting

FOR

660-22-108 Replace Propane Tanks

The contractor is to provide all labor, tools, materials, equipment, and supervision required to replace propane tanks of the Salt Lake City VA Medical Center as outlined in the Statement of Work and associated documents.

All work must be done in compliance with applicable OSHA, EPA and federal/state environmental regulations and policies. Contractor is responsible for proper handling and disposal of debris, waste and excess fuel generated during completion of this work.

Location: Salt Lake City VA Medical Center.

Introductions: Christina Beeler-Blackburn CO, Sylwia Zak CS, and Brandon Watson COR Site Visit:

· The pre-bid meeting/site walk is not mandatory.

· Questions during site visit must be written down and submitted to the Contracting Officer to provide answers in an amendment to all interested parties.

Pertinent Dates:

· Questions are due by November 20, 2023, before 1 pm, MT. Any questions submitted after this time will not be reviewed or answered. Please submit to Sylwia.Zak@va.gov

· Bids are due on December 6, 2023, no later than 11:00 AM MT. Submit via email to Sylwia.Zak@va.gov.

Site Visit Guidelines:

· Prospective bidders are prohibited from attempting to gain information by inquiring with VA employees about project other than through written questions submitted to Contracting Officer.

· Prospective bidders are prohibited from visiting site other than through formal invitation by Contracting Officer.

· Attendees of walk-through are to stay as a group while walking to various locations and are to leave the future project site once the walk-through is concluded.

Solicitation Information:

· Confirmation of construction range: between $1,000,000 and $2,000,000.

· Bid Guarantee & Payment/Performance Bonds: are required as outlined in the solicitation.

· Special Standards of Responsibility: Please note solicitation requirements for submittal of OSHA and EMR ratings.

· VAAR clause 852.219-75 Limitation on Subcontracting: please ensure you provide a signed copy of this clause with your bid package.

· Contractor shall begin performance within 10 days after Notice to Proceed (NTP) and complete within 120 days.

Post Award Compliance:

· Compliance with Davis Bacon Wages and Application wage determination shall be expected of the contractor. The contractor shall submit their weekly certified payrolls with their monthly invoice.