S02 - Specs B28.pdf
PDF 1 MB Posted
- Attached to
- Z2DA--666-20-110 Building 28 Upgrade
- Solicitation number
- 36C25923R0019
About this file
This document is a solicitation for a construction project at a Veterans Affairs medical center. The solicitation requests general contractor services to upgrade and renovate Resident Quarters Building 28, including hazardous material abatement, demolition, construction of porches, flooring and bathroom upgrades, and mechanical, electrical, plumbing and other work. There is a base bid and two additive alternates involving front porch structures and HVAC work. The period of performance is 180 calendar days from notice to proceed. The solicitation specifies contractor qualification and safety requirements, tasks and deliverables including schedules, plans and documentation. It outlines standards for quality control, environmental protection, project management and technical requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| S05 - RFIs and Responses2.pdf | ||
| 36C25923R0019 0007.docx | DOCX document | |
| S04 - Site Visit Meeting Doc_B28 Upgrade.pdf | ||
| S04 - 1st Pre-bid Walkthru.pdf | ||
| S04 - 2nd Pre-bid Walkthru.pdf | ||
| 36C25923R0019 0006.docx | DOCX document | |
| S05 - RFIs and Responses.pdf | ||
| S04 - 3rd Pre-bid Walkthru.pdf | ||
| 36C25923R0019 0005.docx | DOCX document | |
| 36C25923R0019 0004.docx | DOCX document | |
| S06 - Updated B28 Upgrade 666-20-110 2-22-23 B28 Set.pdf | ||
| 36C25923R0019 0003.docx | DOCX document | |
| 36C25923R0019 0002.docx | DOCX document | |
| 36C25923R0019 0001.docx | DOCX document | |
| S02 - B28 Upgrade 666-20-110 - 7-28-22 - Combined.pdf | ||
| S02 - Building 28 Lead Based Paint Risk Assessment Report.pdf | ||
| S02 - AWC-DCA62015-DeckGuide-1804.pdf | ||
| S02 - Asbestos Report Quaters 28.pdf | ||
| S02 - 013526 Safety Requirements.pdf | ||
| 36C25923R0019.docx | DOCX document |
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheridan VAMC Aug 31, 2020 Building 28 Upgrade; 666-20-110 Sheridan, WY
05-01-17
Table of Contents
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
DIVISION 00 - SPECIAL SECTIONS DATE
00 01 15 List of Drawing Sheets 07-15
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 11-15 01 33 23 Shop Drawings, Product Data, and Samples 05-17 01 35 26 Safety Requirements 02-17 01 57 19 Temporary Environmental Controls 01-11 01 74 19 Construction Waste Management 09-13 List of Required Submittals
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 02-15 02 82 1313 Glove Bag Asbestos Abatement 02 82 3313 Lead-Based Paint Removal and Disposal
DIVISION 03 – CONCRETE – NOTE USED
DIVISION 04 – MASONRY
04 01 00 Maintenance of Masonry 02-16
DIVISION 05 – METALS – NOT USED
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
06 10 00 Rough Carpentry 10-15
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 92 00 Joint Sealants 10-15
DIVISION 08 – OPENINGS – NOT USED
DIVISION 09 – FINISHES
09 06 00 Finishes and Products 04-15
00 01 10-2
09 91 00 Painting 01-16
DIVISION 10 – SPECIALTIES NOT USED
DIVISION 11 – EQUIPMENT – NOT USED
DIVISION 12 – FURNISHINGS – NOT USED
DIVISION 13 - SPECIAL CONSTRUCTION – NOT USED
DIVISION 14– CONVEYING EQUIPEMENT – NOT USED
DIVISION 21- FIRE SUPPRESSION – NOT USED
DIVISION 22 – PLUMBING – NOT USED
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)-
23 31 00 HVAC Duct and Casings
DIVISION 25 – INTEGRATED AUTOMATION – NOT USED
DIVISION 26 – ELECTRICAL – NOT USED
DIVISION 27 – COMMUNICATIONS – NOT USED
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY – NOT USED
DIVISION 31 – EARTHWORK – NOT USED
DIVISION 32 – EXTERIOR IMPROVEMENTS – NOT USED
DIVISION 33 – UTILITIES – NOT USED
DIVISION 34 – TRANSPORTATION – NOT USED
00 01 10-3
DIVISION 48 – Electrical Power Generation – NOT USED
REPORTS AND ATTACHMENTS
Asbestos Report Quarters 28 Prescriptive Residential Wood Deck Construction Guide Lead Based Paint Risk Assessment Report for Quarters 28
THIS PAGE INTENTIONALLY LEFT BLANK
07-01-15
List of Drawing Sheets
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
G-0 COVER SHEET AND DRAWING INDEX
AD-1 Demolition Plans A-1 Architectural Plans A-2 Exterior Architectural Plan (Add Alternate No1) A-3 Cabinet Sections and Details A-4 Porch Details
ED-1 Electrical Demolition E-1 Electrical Plans
PD/MD-1 Plumbing and Mechanical Demolition P/M-1 Plumbing and Mechanical Plans M-1 Mechanical Plan(Add Alternate No2)
- - - END - - -
Sheridan, WY
GENERAL REQUIREMENTS
i
SECTION 01 00 00
GENERAL REQUIREMENTS
TABLE OF CONTENTS
1.1 GENERAL INTENTION
1.2 STATEMENT OF BID ITEM(S)
1.3 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
1.4 CONSTRUCTION SECURITY REQUIREMENTS
1.5 OPERATIONS AND STORAGE AREAS
1.6 DISPOSAL AND RETENTION
1.7 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,
UTILITIES, AND IMPROVEMENTS
1.8 RESTORATION
1.9 LAYOUT OF WORK
1.10 AS-BUILT DRAWINGS
1.11 USE OF ROADWAYS
1.12 FIELD OFFICE
1.13 TEMPORARY TOILETS
1.14 AVAILABILITY AND USE OF UTILITY SERVICES
1.15 HISTORIC PRESERVATION
Sheridan, WY
General Requirements 01 00 00 -1
SECTION 01 00 00
GENERAL REQUIREMENTS
PART 1 - GENERAL
1.0 SAFETY REQUIREMENTS
A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.1 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work on six historic front and rear porch structures and one garage structure as required by drawings and specifications.
B. The Sheridan VA Engineering Department will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by
Contracting Officer or his duly authorized representative.
C. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
D. The contractor will designate a competent person (CP) to serve as the sole point of contact responsible for safety management on the project site. Competent persons are defined as those capable of identifying existing and predictable hazards in the surroundings and working conditions which are unsanitary, hazardous, or dangerous, and who have the authority to take prompt corrective measures to eliminate them.
This CP designation is a formal, required submittal that requires approval by the contracting officer’s technical representative (COTR).
1. Federal acquisition regulation (FAR) 52.236-13, with alternate 1, requires submittal and approval of a safety plan, specific to the project and to the construction site. The contractor will submit a safety plan that includes detailed safety precautions and practices to mitigate identified hazards specific to this project and to this
Sheridan, WY
General Requirements 01 00 00 -2 construction site. This plan is a formal, required submittal that requires approval by the contracting officer’s technical representative (COTR).
E. Training:
1. The contractor will submit proof of a 30-hour OSHA safety course
(i.e., copies of documentation) for prime contractor-designated competent persons as well as any subcontractor-designated competent persons that will work on the site. This proof is a formal, required submittal that requires approval by the contracting officer’s technical representative (COTR).
2. The contractor will submit proof of 10-hour OSHA safety course
(i.e., copies of documentation) for all other prime contractor employees as well as any subcontract employees that will work on the site. This proof is a formal, required submittal that requires approval by the contracting officer’s technical representative
(COTR).
Submittals must include the names, qualifications, and training dates for the prime contractor-designated competent person (CP) designated to administer the site-specific safety program, as well as the CP (if different) for high risk activities as required by
OSHA regulations, such as ladders, excavations, trenching, etc.
3. Submit training records of all such employees for approval before
F. Working Time:
1. The Contractor shall follow all the Sheridan’s VAHCS rules, memorandums and policies. The contractor will observe and not work during all Federal Holidays. Federal Holidays are: New Year’s Day, Martin Luther King Day, Washington’s Birthday, Memorial Day, Independence Day, Labor Day, Columbus Day, Veteran’s Day, Thanksgiving Day and Christmas Day. Normal times of work at the
Sheridan Wyoming VA Health Care System are Monday through Friday from 7:30am to 4:00pm.
the start of work.
Sheridan, WY
General Requirements 01 00 00 -3
1.2 STATEMENT OF BID ITEM(S)
A. ITEM 1 BASE BID, GENERAL CONSTRUCTION: Building 28: Work includes general demolition, hazardous material abatement, construction of porch, flooring, bathroom and kitchen upgrades, construction, mason, painting, plumbing, electrical and other work as required by construction drawings and these specifications.
B. ADDITIVE ALTERNATE NO.1: Building 28: Partial demolition and general construction and alteration work to the front porch structures and replacement of exterior windows and other work as shown on contract documents. Work does require hazardous material abatement.
C. ADDITIVE ALTERNATE NO.2: Building 28: Will eliminate the work to replace the cast iron radiators and replace them with steam finned tubs. It will install a residential heating and cooling system through the building and other work as shown on contract documents. Work does require hazardous material abatement.
1.3 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. AFTER AWARD OF CONTRACT, 1 set of specifications and drawings will be furnished.
B. Sets of drawings and specifications may be made by the Contractor, at
Contractor's expense, from reproducible PDF furnished by Issuing
Office.
1.4 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer.
Sheridan, WY
General Requirements 01 00 00 -4
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
1.5 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the
Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the
Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the
Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting
Officer, the buildings and utilities may be abandoned and need not be removed. See contract drawings for location of Contractor job trailer, near main entrance adjacent to building 31.
C. The Contractor shall, under regulations prescribed by the Contracting
Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting
Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The
Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
(FAR 52.236-10)
D. Working space and space available for storing materials shall be as shown on the drawings. Verify location(s) of stored materials with
Contracting Officer prior to mobilization.
Sheridan, WY
General Requirements 01 00 00 -5
E. Workmen are subject to rules of Medical Center applicable to their conduct.
F. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of
Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.
G. Phasing and Schedule:
1. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:
a. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the
Resident Engineer two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such dates to ensure accomplishment of this work in successive phases mutually agreeable to Medical Center
Director, COR and Contractor, as follows:
Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and
Sheridan, WY
General Requirements 01 00 00 -6 affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of
Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc to facilitate patient and staff access.
Coordinate alteration work in areas occupied by Department of
Veterans Affairs so that Medical Center operations will continue during the construction period.
2. Construction start date: Within 10 days after the Notice of Proceed has been issued.
H. Construction Fence: Not Required
I. Utilities Services: Maintain existing utility services for Medical
Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.
When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval.
2. Contractor shall submit a request to interrupt any such services to
COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
Sheridan, WY
General Requirements 01 00 00 -7
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of Resident Engineer COTR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
J. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
K. To minimize interference of construction activities with flow of
Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
L. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
1.6 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.
Sheridan, WY
General Requirements 01 00 00 -8
3. Items of portable equipment and furnishings located on the porch structures and spaces in which work is to be done under this contract shall remain the property of the Government. When areas are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with
Contractor's operation.
1.7 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the
Contractor fails or refuses to repair the damage promptly, the
Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
C. During demolition work, contractor shall use 2 layers of 6 mil poly sheeting on grade to cover the existing soil, grasses, and vegetation from hazardous materials. Extend poly sheeting 8 inches up exterior walls and extend outwards min of 10 feet from the construction area.
All poly sheeting shall be kept free of debris at the end of each workday.
Sheridan, WY
General Requirements 01 00 00 -9
(FAR 52.236-9)
D. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and
"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.
1.8 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the
COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"
(FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR
52.236-2).
1.9 LAYOUT OF WORK
A. The Contractor shall lay out the work from Government established base lines and benchmarks, indicated on the drawings, and shall be
Sheridan, WY
General Requirements 01 00 00 -10 responsible for all measurements in connection with the layout. The
Contractor shall furnish, at Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the Contracting Officer. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the Contracting Officer until authorized to remove them.
If such marks are destroyed by the Contractor or through Contractor's negligence before their removal is authorized, the Contracting Officer may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor.
(FAR 52.236-17)
B. Establish and plainly mark center lines for each building and corner of column lines and/or addition to each existing building, and such other lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations established for each such structure and/or addition are in accordance with lines and elevations shown on contract drawings.
1.10 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To insure compliance, as-built drawings shall be made available for the COR review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.11 USE OF ROADWAYS
A. For hauling, use only established public roads and roads on Medical
Center property and, when authorized by the COR, such temporary roads
Sheridan, WY
General Requirements 01 00 00 -11 which are necessary in the performance of contract work. Temporary roads shall be constructed, and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
1.12 RESIDENT ENGINEER'S FIELD OFFICE
A. The Contractor shall, within fifteen (15) days after receipt of Notice to Proceed, provide where shown on the drawings a temporary field office, furniture, and two inch deep gravel surfaced area for use of the contractor.
1.13 TEMPORARY TOILETS
A. Provide where directed, (for use of all Contractor's workmen) ample temporary sanitary toilet accommodations, provide suitable dry closets where directed. Keep such places clean and free from flies, and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.
1.14 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract.
B. Heat: Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted. Maintain minimum temperatures as specified for various materials:
C. Electricity (for Construction and Testing): Furnish all temporary electric services.
1. Obtain electricity by connecting to the Medical Center electrical distribution system. Electrical connections will be available for the Contractors use on the exterior of each facility being renovated. The Contractor shall pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat. Electricity for all other uses is available at no cost to the Contractor.
D. Water (for Construction and Testing): Furnish temporary water service.
Sheridan, WY
General Requirements 01 00 00 -12
1. Obtain water by connecting to the Medical Center water distribution system. Provide reduced pressure backflow preventer at each connection as per code. Water is available at no cost to the
Contractor.
2. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes will be cause for revocation (at COR’S discretion) of use of water from Medical Center's system.
1.15 HISTORIC PRESERVATION
A. Where the Contractor or any of the Contractor's employees, prior to, or during the construction work, are advised of or discover any possible archeological, historical and/or cultural resources, the Contractor shall immediately notify the COR verbally, and then with a written follow up.
- - - E N D - - -
Sheridan VAMC November 27, 2022
Sheridan, WY 02-01-17
Safety Requirements 01 35 26 -1
SECTION 01 35 26
SAFETY REQUIREMENTS
TABLE OF CONTENTS
1.1 APPLICABLE PUBLICATIONS
1.2 DEFINITIONS
1.3 REGULATORY REQUIREMENTS
1.4 PRECONSTRUCTION CONFERENCE
1.5 “SITE SAFETY AND HEALTH OFFICER” (SSHO) and “COMPETENT PERSON”
(CP)
1.6 TRAINING
1.7 INSPECTIONS
1.8 ACCIDENTS, OSHA 300 LOGS, AND MAN-HOURS
1.9 PERSONAL PROTECTIVE EQUIPMENT (PPE)
1.10 INFECTION CONTROL……………………………………….……………………………………………….…………………………….8
1.11 FIRE SAFETY
1.12 FALL PROTECTION
1.13 SCAFFOLDS AND OTHER WORK PLATFORMS
1.14 CRANES
1.15 CONFINED SPACE ENTRY
1.16 WELDING AND CUTTING
1.1 LADDERS
01 35 26 -2
SECTION 01 35 26
SAFETY REQUIREMENTS
1.1 APPLICABLE PUBLICATIONS:
A. Latest publications listed below form part of this Article to extent referenced. Publications are referenced in text by basic designations only.
B. American Society of Safety Engineers (ASSE):
A10.1-2011...........Pre-Project & Pre-Task Safety and Health Planning
A10.34-2012..........Protection of the Public on or Adjacent to Construction Sites
A10.38-2013..........Basic Elements of an Employer’s Program to Provide a Safe and Healthful Work Environment American National Standard Construction and Demolition Operations
C. American Society for Testing and Materials (ASTM):
E84-2013.............Surface Burning Characteristics of Building Materials
D. The Facilities Guidelines Institute (FGI):
FGI Guidelines-2010Guidelines for Design and Construction of
Healthcare Facilities E. National Fire Protection Association (NFPA):
10-2013..............Standard for Portable Fire Extinguishers 30-2012..............Flammable and Combustible Liquids Code 51B-2014.............Standard for Fire Prevention During Welding, Cutting and Other Hot Work 70-2014..............National Electrical Code 70B-2013.............Recommended Practice for Electrical Equipment
Maintenance 70E-2015 ............Standard for Electrical Safety in the Workplace 99-2012..............Health Care Facilities Code 241-2013.............Standard for Safeguarding Construction, Alteration, and Demolition Operations F. The Joint Commission (TJC)
TJC Manual ..........Comprehensive Accreditation and Certification Manual
G. U.S. Nuclear Regulatory Commission 10 CFR 20 ...........Standards for Protection Against Radiation
H. U.S. Occupational Safety and Health Administration (OSHA):
29 CFR 1904 .........Reporting and Recording Injuries & Illnesses
01 35 26 -3
29 CFR 1910 .........Safety and Health Regulations for General Industry
29 CFR 1926 .........Safety and Health Regulations for Construction Industry
CPL 2-0.124..........Multi-Employer Citation Policy I. VHA Directive 2005-007
1.2 DEFINITIONS:
A. Critical Lift. A lift with the hoisted load exceeding 75% of the crane’s maximum capacity; lifts made out of the view of the operator (blind picks); lifts involving two or more cranes; personnel being hoisted; and special hazards such as lifts over occupied facilities, loads lifted close to power-lines, and lifts in high winds or where other adverse environmental conditions exist; and any lift which the crane operator believes is critical.
B. OSHA “Competent Person” (CP). One who is capable of identifying existing and predictable hazards in the surroundings and working conditions which are unsanitary, hazardous or dangerous to employees, and who has the authorization to take prompt corrective measures to eliminate them (see 29 CFR 1926.32(f)).
C. "Qualified Person" means one who, by possession of a recognized degree, certificate, or professional standing, or who by extensive knowledge, training and experience, has successfully demonstrated his ability to solve or resolve problems relating to the subject matter, the work, or the project.
D. High Visibility Accident. Any mishap which may generate publicity or high visibility.
E. Accident/Incident Criticality Categories:
No impact – near miss incidents that should be investigated but are not required to be reported to the VA;
Minor incident/impact – incidents that require first aid or result in minor equipment damage (less than $5000). These incidents must be investigated but are not required to be reported to the VA;
Moderate incident/impact – Any work-related injury or illness that results in:
1. Days away from work (any time lost after day of injury/illness onset);
2. Restricted work;
3. Transfer to another job;
4. Medical treatment beyond first aid;
5. Loss of consciousness;
6. A significant injury or illness diagnosed by a physician or other licensed health care professional, even if it did not result in (1) through (5) above or,
7. Any incident that leads to major equipment damage (greater than $5000).
These incidents must be investigated and are required to be reported to the VA;
01 35 26 -4
Major incident/impact – Any mishap that leads to fatalities, hospitalizations, amputations, and losses of an eye as a result of contractors’ activities. Or any incident which leads to major property damage (greater than $20,000) and/or may generate publicity or high visibility. These incidents must be investigated and are required to be reported to the VA as soon as practical, but not later than 2 hours after the incident.
F. Medical Treatment. Treatment administered by a physician or by registered professional personnel under the standing orders of a physician. Medical treatment does not include first aid treatment even through provided by physician or registered personnel.
1.3 REGULATORY REQUIREMENTS:
A. In addition to the detailed requirements included in the provisions of this contract, comply with 29 CFR 1926, comply with 29 CFR 1910 as incorporated by reference within 29 CFR 1926, comply with ASSE A10.34, and all applicable [federal, state, and local] laws, ordinances, criteria, rules and regulations. Submit matters of interpretation of standards for resolution before starting work. Where the requirements of this specification, applicable laws, criteria, ordinances, regulations, and referenced documents vary, the most stringent requirements govern except with specific approval and acceptance by the
Contracting Officer or Contracting Officer Representative.
1.4 PRECONSTRUCTION CONFERENCE:
A. Contractor representatives who have a responsibility or significant role in implementation of the accident prevention program, as required by 29 CFR 1926.20(b)(1), on the project shall attend the preconstruction conference to gain a mutual understanding of its implementation. This includes the project superintendent, subcontractor superintendents, and any other assigned safety and health professionals.
1.5 “SITE SAFETY AND HEALTH OFFICER” (SSHO) AND “COMPETENT PERSON” (CP):
A. The Prime Contractor shall designate a minimum of one SSHO at each project site that will be identified as the SSHO to administer the
Contractor's safety program and government-accepted Accident Prevention
Plan. Each subcontractor shall designate a minimum of one CP in compliance with 29 CFR 1926.20 (b)(2) that will be identified as a CP to administer their individual safety programs.
01 35 26 -5
B. Further, all specialized Competent Persons for the work crews will be supplied by the respective contractor as required by 29 CFR 1926 (i.e.
Asbestos, Electrical, Cranes, & Derricks, Demolition, Fall Protection, Fire Safety/Life Safety, Ladder, Rigging, Scaffolds, and
Trenches/Excavations).
C. These Competent Persons can have collateral duties as the subcontractor’s superintendent and/or work crew lead persons as well as fill more than one specialized CP role (i.e. Asbestos, Electrical, Cranes, & Derricks, Demolition, Fall Protection, Fire Safety/Life
Safety, Ladder, Rigging, Scaffolds, and Trenches/Excavations).
D. The SSHO or an equally-qualified Designated Representative/alternate will maintain a presence on the site during construction operations in accordance with FAR Clause 52.236-6: Superintendence by the Contractor.
CPs will maintain presence during their construction activities in accordance with above mentioned clause. A listing of the designated
SSHO and all known CPs shall be submitted prior to the start of work as part of the APP with the training documentation and/or AHA as listed in
Section 1.8 below.
E. The repeated presence of uncontrolled hazards during a contractor’s work operations will result in the designated CP as being deemed incompetent and result in the required removal of the employee in accordance with FAR Clause 52.236-5: Material and Workmanship, Paragraph (c).
1.6 TRAINING:
A. The designated Prime Contractor SSHO must meet the requirements of all applicable OSHA standards and be capable (through training, experience, and qualifications) of ensuring that the requirements of 29 CFR 1926.16 and other appropriate Federal, State and local requirements are met for the project. As a minimum the SSHO must have completed the OSHA 30-hour
Construction Safety class and have five (5) years of construction industry safety experience or three (3) years if he/she possesses a
Certified Safety Professional (CSP) or certified Construction Safety and Health Technician (CSHT) certification or have a safety and health degree from an accredited university or college.
01 35 26 -6
B. All designated CPs shall have completed the OSHA 30-hour Construction
Safety course within the past 5 years.
C. In addition to the OSHA 30 Hour Construction Safety Course, all CPs with high hazard work operations such as operations involving asbestos, electrical, cranes, demolition, work at heights/fall protection, fire safety/life safety, ladder, rigging, scaffolds, and trenches/excavations shall have a specialized formal course in the hazard recognition & control associated with those high hazard work operations. Documented “repeat” deficiencies in the execution of safety requirements will require retaking the requisite formal course.
D. All other construction workers shall have the OSHA 10-hour Construction
Safety Outreach course and any necessary safety training to be able to identify hazards within their work environment.
E. Submit training records associated with the above training requirements to the Contracting Officer or Government Designated Authority for review for compliance with contract requirements in accordance with
Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA AND SAMPLES 15 calendar days prior to the date of the preconstruction conference for acceptance.
F. Prior to any worker for the contractor or subcontractors beginning work, they shall undergo a safety briefing provided by the SSHO or his/her designated representative. As a minimum, this briefing shall include information on the site-specific hazards, construction limits, VAMC safety guidelines, means of egress, break areas, work hours, locations of restrooms, use of VAMC equipment, emergency procedures, accident reporting etc... Documentation shall be provided to the
Resident Engineer that individuals have undergone contractor’s safety briefing.
G. Ongoing safety training will be accomplished in the form of weekly documented safety meeting.
1.7 INSPECTIONS:
A. The SSHO shall conduct frequent and regular safety inspections (weekly) of the site and each of the subcontractors CPs shall conduct frequent and regular safety inspections (weekly) of their work operations as
01 35 26 -7 required by 29 CFR 1926.20(b)(2). Each week, the SSHO shall conduct a formal documented inspection of the entire construction areas with the subcontractors’ “Trade Safety and Health CPs” present in their work areas. Coordinate with, and report findings and corrective actions weekly to Contracting Officer.
1.8 ACCIDENTS, OSHA 300 LOGS, AND MAN-HOURS:
A. The prime contractor shall establish and maintain an accident reporting, recordkeeping, and analysis system to track and analyze all injuries and illnesses, high visibility incidents, and accidental property damage (both government and contractor) that occur on site.
Notify the Contracting Officer as soon as practical, but no more than four hours after any accident meeting the definition of a Moderate or
Major incidents, High Visibility Incidents, or any weight handling and hoisting equipment accident. Within notification include contractor name; contract title; type of contract; name of activity, installation or location where accident occurred; date and time of accident; names of personnel injured; extent of property damage, if any; extent of injury, if known, and brief description of accident (to include type of construction equipment used, PPE used, etc.). Preserve the conditions and evidence on the accident site until the Contracting Officer determine whether a government investigation will be conducted.
B. Conduct an accident investigation for all Minor, Moderate and Major incidents as defined in paragraph DEFINITIONS, and property damage accidents resulting in at least $20,000 in damages, to establish the root cause(s) of the accident. Complete the VA Form 2162 (or equivalent), and provide the report to the Contracting Officer or
Government Designated Authority within 5 calendar days of the accident.
The Contracting Officer will provide copies of any required or special forms.
C. A summation of all man-hours worked by the contractor and associated sub-contractors for each month will be reported to the Contracting
Officer monthly.
D. A summation of all Minor, Moderate, and Major incidents experienced on site by the contractor and associated sub-contractors for each month will be provided to the Contracting Officer monthly. The contractor
01 35 26 -8 and associated sub-contractors’ OSHA 300 logs will be made available to the Contracting Officer as requested.
1.9 PERSONAL PROTECTIVE EQUIPMENT (PPE):
A. PPE is governed in all areas by the nature of the work the employee is performing. For example, specific PPE required for performing work on electrical equipment is identified in NFPA 70E, Standard for Electrical
Safety in the Workplace.
B. Mandatory PPE includes:
1. Hard Hats – unless written authorization is given by the Officer in circumstances of work operations that have limited potential for falling object hazards such as during finishing work or minor remodeling. With authorization to relax the requirement of hard hats, if a worker becomes exposed to an overhead falling object hazard, then hard hats would be required in accordance with the OSHA regulations.
2. Safety glasses - unless written authorization is given by the
Contracting Officer in circumstances of no eye hazards, appropriate safety glasses meeting the ANSI Z.87.1 standard must be worn by each person on site.
3. Appropriate Safety Shoes – based on the hazards present, safety shoes meeting the requirements of ASTM F2413-11 shall be worn by each person on site unless written authorization is given by the
Contracting Officer Representative in circumstances of no foot hazards.
4. Hearing protection - Use personal hearing protection at all times in designated noise hazardous areas or when performing noise hazardous tasks.
1.10 INFECTION CONTROL
A. Infection Control is critical in all medical center facilities.
Interior construction activities causing disturbance of existing dust, or creating new dust, must be conducted within ventilation-controlled areas that minimize the flow of airborne particles into other residential areas. Exterior construction activities causing
01 35 26 -9 disturbance of soil or creates dust in some other manner must be controlled.
B. An AHA associated with infection control will be performed by VA personnel in accordance with FGI Guidelines (i.e. Infection Control
Risk Assessment (ICRA)). The ICRA procedure found on the American
Society for Healthcare Engineering (ASHE) website will be utilized.
Risk classifications of Class II or lower will require approval by the Contracting Officer Representative (COR). Risk classifications of Class III or higher will require a permit before beginning any construction work. Infection Control permits will be issued by the
Sheridan VA Infection Control Service. The Infection Control
Permits will be posted outside the appropriate construction area.
More than one permit may be issued for a construction project if the work is located in separate areas requiring separate classes. The primary project scope area for this project is: Class I, however, work outside the primary project scope area may vary. The required infection control precautions with each class are as follows:
1. Identify these areas where dust and contamination might be generated and work with Medical Center personnel to achieve desired level of isolation suited to the scope of risk involved.
5. Other considerations.
1. Class I requirements:
a. During Construction Work:
1) Notify the Contracting Officer Representative
2) Execute work by methods to control raising dust from construction operations.
b. Upon Completion:
1) Clean work area upon completion of task
2) Notify the Contracting Officer Representative
2. Class II requirements:
a. During Construction Work:
01 35 26 -10
1) Notify the Contracting Officer Representative
2) Provide active means to prevent airborne dust from dispersing into atmosphere such as wet methods or tool mounted dust collectors where possible.
3) Water mist work surfaces to control dust while cutting.
4) Seal unused doors with duct tape.
5) Block off and seal air vents.
6) Remove or isolate HVAC system in areas where work is being performed.
b. Upon Completion:
1) Wipe work surfaces with cleaner/disinfectant.
2) Contain construction waste before transport in tightly covered containers.
3) Wet mop and/or vacuum with HEPA filtered vacuum before leaving work area.
4) Upon completion, restore HVAC system where work was performed
5) Notify the Contracting Officer Representative
3. Class III requirements:
a. During Construction Work:
1) Obtain permit from the Contracting Officer Representative
2) Remove or Isolate HVAC system in area where work is being done to prevent contamination of duct system.
3) Complete all critical barriers i.e. sheetrock, plywood, plastic, to seal area from non-work area or implement control cube method (cart with plastic covering and sealed connection to work site with HEPA vacuum for vacuuming prior to exit) before construction begins.
Install construction barriers and ceiling protection carefully, outside of normal work hours.
01 35 26 -11
4) Maintain negative air pressure, 0.01 inches of water gauge, within work site utilizing HEPA equipped air filtration units and continuously monitored with a digital display, recording and alarm instrument, which must be calibrated on installation, maintained with periodic calibration and monitored by the contractor.
5) Contain construction waste before transport in tightly covered containers.
6) Cover transport receptacles or carts. Tape covering unless solid lid.
b. Upon Completion:
1) Do not remove barriers from work area until completed project is inspected by the Contracting Officer Representative and thoroughly cleaned by the VA Environmental Services Department.
2) Remove construction barriers and ceiling protection carefully to minimize spreading of dirt and debris associated with construction, outside of normal work hours.
3) Vacuum work area with HEPA filtered vacuums.
4) Wet mop area with cleaner/disinfectant.
5) Upon completion, restore HVAC system if effected where work was performed.
6) Return permit to the Contracting Officer Representative
4. Class IV requirements:
a. During Construction Work:
1) Obtain permit from the Contracting Officer Representative
2) Isolate HVAC system in area where work is being done to prevent contamination of duct system.
3) Complete all critical barriers i.e., sheetrock, plywood, plastic, to seal area from non-work area or implement control cube method (cart with plastic covering and sealed connection to work site with HEPA vacuum for vacuuming prior to exit) before construction begins.
01 35 26 -12
Install construction barriers and ceiling protection carefully, outside of normal work hours.
4) Maintain negative air pressure, 0.01 inches of water gauge, within work site utilizing HEPA equipped air filtration units and continuously monitored with a digital display, recording and alarm instrument, which must be calibrated on installation, maintained with periodic calibration and monitored by the contractor.
5) Seal holes, pipes, conduits, and punctures.
6) Construct anteroom and require all personnel to pass through this room so they can be vacuumed using a HEPA vacuum cleaner before leaving work site or they can wear cloth or paper coveralls that are removed each time they leave work site.
7) All personnel entering work site are required to wear shoe covers.
Shoe covers must be changed each time the worker exits the work area.
b. Upon Completion:
1) Do not remove barriers from work area until completed project is inspected by the Contracting Officer Representative with thorough cleaning by the VA Environmental Services Dept.
2) Remove construction barriers and ceiling protection carefully to minimize spreading of dirt and debris associated with construction, outside of normal work hours.
3) Contain construction waste before transport in tightly covered containers.
4) Cover transport receptacles or carts. Tape covering unless solid lid.
5) Vacuum work area with HEPA filtered vacuums.
6) Wet mop area with cleaner/disinfectant.
7) Upon completion, restore HVAC system where work was performed.
8) Return permit to the Contracting Officer Representative
01 35 26 -13
C. Barriers shall be erected as required based upon classification
(Class III & IV requires barriers) and shall be constructed as follows:
1. Class III and IV - closed door with masking tape applied over the frame and door is acceptable for projects that can be contained in a single room.
2. Construction, demolition or reconstruction not capable of containment within a single room must have the following barriers erected and made presentable on hospital occupied side:
a. Class III & IV (where dust control is the only hazard, and an agreement is reached with the Resident Engineer and Medical Center)
- Airtight plastic barrier that extends from the floor to ceiling.
Seams must be sealed with duct tape to prevent dust and debris from escaping
b. Class III & IV - Drywall barrier erected with joints covered or sealed to prevent dust and debris from escaping.
c. Class III & IV - Seal all penetrations in existing barrier airtight
d. Class III & IV - Barriers at penetration of ceiling envelopes, chases and ceiling spaces to stop movement air and debris
e. Class IV only - Anteroom or double entrance openings that allow workers to remove protective clothing or vacuum off existing clothing
f. Class III & IV - At elevators shafts or stairways within the field of construction, overlapping flap minimum of two feet wide of polyethylene enclosures for personnel access.
D. Products and Materials:
1. Sheet Plastic: Fire retardant polyethylene, 6-mil thickness meeting local fire codes
2. Barrier Doors: Self Closing fire-rated solid core wood in steel frame, painted
01 35 26 -14
4. High Efficiency Particulate Air-Equipped filtration machine rated at
95% capture of 0.3 microns including pollen, mold spores and dust particles. HEPA filters should have ASHRAE 85 or other prefilter to extend the useful life of the HEPA. Provide both primary and secondary filtrations units. Maintenance of equipment and replacement of the HEPA filters and other filters will be in accordance with manufacturer’s instructions.
5. Exhaust Hoses: Heavy duty, flexible steel reinforced; Ventilation
Blower Hose
6. Adhesive Walk-off Mats: Provide minimum size mats of 24 inches x 36 inches
7. Disinfectant: Hospital-approved disinfectant or equivalent product
8. Portable Ceiling Access Module
E. Before any construction on site begins, all contractor personnel…
This is the start of the file's text. The full file is on GovTribe.