S05 - RFI Upper Tramway Repair.pdf

PDF 95 KB Posted

Attached to
Z2DA--Upper Tramway Repair Project Between Buildings 6 & 7 Federal contract opportunity
Solicitation number
36C25923Q0014
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 19

About this file

This document outlines a federal solicitation for general construction services for an upper tramway repair project at a Department of Veterans Affairs medical center. The solicitation requires removal and replacement of the upper tramway decking between Buildings 6 and 7 per the provided plans and specifications. Key details include a 180-day period of performance from notice to proceed, OSHA and safety compliance, site-specific plans, material submittals and approvals, inspection and testing requirements, and a one-year warranty on all workmanship and materials. The contractor will be responsible for safety, cleaning, coordination and minimal disruption to the facility and occupants.

View the file

Other files for this federal contract opportunity

Other files attached to Z2DA--Upper Tramway Repair Project Between Buildings 6 & 7, newest first.
File Type Posted
S04 - Site Visit Sign In.pdf PDF
S04 - Site Visit.pdf PDF
36C25923Q0014 0001.docx DOCX document
S02 - 6A Upper Tramway Repairs Drawings.pdf PDF
S02 - 666-22-113 Specifications.pdf PDF
P11_ Template-Specs Gaurantee Period.pdf PDF
36C25923Q0014_1.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project: 666‐22‐113 Upper Tramway Repair RFI

RFI#1 Products in this project require warmer weather so there will be either an admin NTP or a start then Winter shut down till early spring.

RFI#2 This project is under 180 days so a PIV access card will not be issued but it is more than 15 days so there will be fingerprints taken for all contractor staff. They must be able to pass the fingerprint background check to stay on station. Please be ready for this process.

Delays due to contractor staff not passing the background check will not be a mod to the contract since it was known during the bidding phase.

File details come from the government source that posted it. Updated .