J041--Chiller Plant Preventative Maintenance, Service, Inspection, and Operational Checks
Solicitation number
36C25922Q0550
Issued by

About this file

This document is an amendment to a solicitation for chiller plant preventative maintenance, inspection, and operational checks services. The Department of Veterans Affairs is seeking these services for various locations in Veterans Integrated Service Network 19. The amendment changes the set-aside requirement from Service-Disabled Veteran-Owned Small Business to general Small Business set-aside. It extends the offer due date to September 5, 2022 and clarifies that all small businesses capable of providing the services are eligible to submit quotes. The solicitation seeks annual inspection and maintenance services for chillers, cooling towers, pumps, variable frequency drives, and related equipment for a one-year base period of performance starting September 20, 2022, with four one-year option periods to extend through September 19, 2027. Pricing is requested for the recurring inspection and maintenance services as well as corrective maintenance and emergency services.

View the file

Other files

File Type Posted
Sol Amendment 36C25922Q0550 0003.docx DOCX document
Sol Amendment 36C25922Q0550 0001.docx DOCX document
P07 Wage Determination.pdf PDF
36C25922Q0550_1.docx DOCX document
S01 Solicitation 36C25922Q0550.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

36C259 Department of Veterans Affairs Network Contracting Office

NCO 19

6162 South Willow Drive, Suite 300 Greenwood Village CO 80111

36C259 Department of Veterans Affairs Network Contracting Office

NCO 19

6162 South Willow Drive, Suite 300 Greenwood Village CO 80111 To all Offerors/Bidders

36C25922Q0550 08-10-2022

X

See CONTINUATION Page

1) The purpose of this amendment is to change the SET-ASIDE requirement from SDVOSB to SMALL BUSINESS SET-ASIDE

2) ALL SMALL BUSINESSES under NAICS CODE 238220 and are capable of providing the services requested could submit quotes for this RFQ.

3) The due date for offers is hereby extended to September 05, 2022 at 1:00PM MT.

4) All other terms and conditions remain the same.

Timothy Myers Contracting Officer

CONTINUATION PAGE

A.1 PRICE/COST SCHEDULE

ITEM INFORMATION

ITEM NUMBER
DESCRIPTION OF SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1.00
EA
__________________
__________________

Semi-annual inspection maintenance and service Chiller 9 EChiller Plant Preventative Maintenance, Service, Inspection, and Operational Checks Contract Period: Base POP Begin: 09-20-2022 POP End: 09-19-2023

2.00
EA
__________________
__________________

Semi-annual Inspection Maintenance and Service Chiller 9 CCU2

2.00
EA
__________________
__________________

Semi-Annual Inspection Maintenance and Service Chiller 9 ACU1

2.00
EA
__________________
__________________

Semi-Annual Inspection Maintenance and Service Cooling Tower CT1

2.00
EA
__________________
__________________

Semi-Annual Inspection Maintenance and Service cooling Tower 9 CT2

2.00
EA
__________________
__________________

Semi-Annual Inspection Maintenance and Service Cooling Tower 9 CT3

4.00
EA
__________________
__________________

Semi-annual inspection maintenance and service BMSC System Controller

POP Begin: 09-20-2022

LOCAL STOCK NUMBER: 3340.6

2.00
EA
__________________
__________________

Semi-annual inspection maintenance and service condenser water pump 9 P4

2.00
EA
__________________
__________________

Semi-annual inspection maintenance and service condenser water pump 9 P5

4.00
EA
__________________
__________________

Semi-annual inspection maintenance and service VFD 9 P4

4.00
EA
__________________
__________________

Semi-annual inspection maintenance and service VFD 9 P5

4.00
EA
__________________
__________________

Semi-annual inspection maintenance and service VFD Cooling Tower 1

4.00
EA
__________________
__________________

Semi-annual Inspection VFD Cooling Tower 2

4.00
EA
__________________
__________________

Semi-annual inspection maintenance and service VFD Cooling Tower 3

2.00
EA
__________________
__________________

Semi-annual inspection maintenance and service Pump Skid 1

2.00
EA
__________________
__________________

Semi-annual inspection maintenance and service Pump Skid 2

2.00
EA
__________________
__________________

Semi-annual Inspection maintenance and service Pump skid 7

2.00
EA
__________________
__________________

Semi-annual inspection maintenance and service Pump Skid 8

2.00
EA
__________________
__________________

Corrective Maintenance by modification

2.00
EA
__________________
__________________

Emergency Services

1.00
EA
__________________
__________________

Semi-annual inspection maintenance and service Chiller 9 EChiller Plant Preventative Maintenance, Service, Inspection, and Operational Checks Contract Period: Option 1 POP Begin: 09-20-2023 POP End: 09-19-2024

2.00
EA
__________________
__________________

Semi-annual Inspection Maintenance and Service Chiller 9 CCU2

2.00
EA
__________________
__________________

Semi-Annual Inspection Maintenance and Service Chiller 9 ACU1

2.00
EA
__________________
__________________

Semi-Annual Inspection Maintenance and Service Cooling Tower CT1

2.00
EA
__________________
__________________

Semi-Annual Inspection Maintenance and Service cooling Tower 9 CT2

2.00
EA
__________________
__________________

Semi-Annual Inspection Maintenance and Service Cooling Tower 9 CT3

4.00
EA
__________________
__________________

Semi-annual inspection maintenance and service BMSC System Controller

POP Begin: 09-20-2023

2.00
EA
__________________
__________________

Semi-annual inspection maintenance and service condenser water pump 9 P4

2.00
EA
__________________
__________________

Semi-annual inspection maintenance and service condenser water pump 9 P5

4.00
EA
__________________
__________________

Semi-annual inspection maintenance and service VFD 9 P4

4.00
EA
__________________
__________________

Semi-annual inspection maintenance and service VFD 9 P5

4.00
EA
__________________
__________________

Semi-annual inspection maintenance and service VFD Cooling Tower 1

4.00
EA
__________________
__________________

Semi-annual Inspection VFD Cooling Tower 2

4.00
EA
__________________
__________________

Semi-annual inspection maintenance and service VFD Cooling Tower 3

2.00
EA
__________________
__________________

Semi-annual inspection maintenance and service Pump Skid 1

2.00
EA
__________________
__________________

Semi-annual inspection maintenance and service Pump Skid 2

2.00
EA
__________________
__________________

Semi-annual Inspection maintenance and service Pump skid 7

2.00
EA
__________________
__________________

Semi-annual inspection maintenance and service Pump Skid 8

2.00
EA
__________________
__________________

Corrective Maintenance by modification

2.00
EA
__________________
__________________

Emergency Services

1.00
EA
__________________
__________________

Semi-annual inspection maintenance and service Chiller 9 EChiller Plant Preventative Maintenance, Service, Inspection, and Operational Checks Contract Period: Option 2 POP Begin: 09-20-2024 POP End: 09-19-2025

2.00
EA
__________________
__________________

Semi-annual Inspection Maintenance and Service Chiller 9 CCU2

2.00
EA
__________________
__________________

Semi-Annual Inspection Maintenance and Service Chiller 9 ACU1

1.00
EA
__________________
__________________

Semi-annual inspection maintenance and service Chiller 9 EChiller Plant Preventative Maintenance, Service, Inspection, and Operational Checks

2.00
EA
__________________
__________________

Semi-annual Inspection Maintenance and Service Chiller 9 CCU2

2.00
EA
__________________
__________________

Semi-Annual Inspection Maintenance and Service Chiller 9 ACU1

2.00
EA
__________________
__________________

Semi-Annual Inspection Maintenance and Service Cooling Tower CT1

2.00
EA
__________________
__________________

Semi-Annual Inspection Maintenance and Service cooling Tower 9 CT2

2.00
EA
__________________
__________________

Semi-Annual Inspection Maintenance and Service Cooling Tower 9 CT3

4.00
EA
__________________
__________________

Semi-annual inspection maintenance and service BMSC System Controller

POP Begin: 09-20-2024

2.00
EA
__________________
__________________

Semi-annual inspection maintenance and service condenser water pump 9 P4

2.00
EA
__________________
__________________

Semi-annual inspection maintenance and service condenser water pump 9 P5

4.00
EA
__________________
__________________

Semi-annual inspection maintenance and service VFD 9 P4

4.00
EA
__________________
__________________

Semi-annual inspection maintenance and service VFD 9 P5

4.00
EA
__________________
__________________

Semi-annual inspection maintenance and service VFD Cooling Tower 1

4.00
EA
__________________
__________________

Semi-annual Inspection VFD Cooling Tower 2

4.00
EA
__________________
__________________

Semi-annual inspection maintenance and service VFD Cooling Tower 3

2.00
EA
__________________
__________________

Semi-annual inspection maintenance and service Pump Skid 1

2.00
EA
__________________
__________________

Semi-annual inspection maintenance and service Pump Skid 2

2.00
EA
__________________
__________________

Semi-annual Inspection maintenance and service Pump skid 7

2.00
EA
__________________
__________________

Semi-annual inspection maintenance and service Pump Skid 8 Contract Period: Option 3 POP Begin: 09-20-2025 POP End: 09-19-2026

2.00
EA
__________________
__________________

Corrective Maintenance by modification

2.00
EA
__________________
__________________

Emergency Services

2.00
EA
__________________
__________________

Semi-Annual Inspection Maintenance and Service cooling Tower 9 CT2

2.00
EA
__________________
__________________

Semi-Annual Inspection Maintenance and Service Cooling Tower 9 CT3

4.00
EA
__________________
__________________

Semi-annual inspection maintenance and service BMSC System Controller

POP Begin: 09-20-2025

2.00
EA
__________________
__________________

Semi-annual inspection maintenance and service condenser water pump 9 P4

2.00
EA
__________________
__________________

Semi-annual inspection maintenance and service condenser water pump 9 P5

4.00
EA
__________________
__________________

Semi-annual inspection maintenance and service VFD 9 P4

4.00
EA
__________________
__________________

Semi-annual inspection maintenance and service VFD 9 P5

4.00
EA
__________________
__________________

Semi-annual inspection maintenance and service VFD Cooling Tower 1

4.00
EA
__________________
__________________

Semi-annual Inspection VFD Cooling Tower 2

4.00
EA
__________________
__________________

Semi-annual inspection maintenance and service VFD Cooling Tower 3

2.00
EA
__________________
__________________

Semi-annual inspection maintenance and service Pump Skid 1

2.00
EA
__________________
__________________

Semi-annual inspection maintenance and service Pump Skid 2

2.00
EA
__________________
__________________

Semi-annual Inspection maintenance and service Pump skid 7

2.00
EA
__________________
__________________

Semi-annual inspection maintenance and service Pump Skid 8

2.00
EA
__________________
__________________

Corrective Maintenance by modification

2.00
EA
__________________
__________________

Emergency Services

2.00
EA
__________________
__________________

Semi-Annual Inspection Maintenance and Service Cooling Tower CT1

1.00
EA
__________________
__________________

Semi-annual inspection maintenance and service Chiller 9 EChiller Plant Preventative Maintenance, Service, Inspection, and Operational Checks Contract Period: Option 4 POP Begin: 09-20-2026 POP End: 09-19-2027

2.00
EA
__________________
__________________

Semi-annual Inspection Maintenance and Service Chiller 9 CCU2

2.00
EA
__________________
__________________

Semi-Annual Inspection Maintenance and Service Chiller 9 ACU1

2.00
EA
__________________
__________________

Semi-Annual Inspection Maintenance and Service Cooling Tower CT1

2.00
EA
__________________
__________________

Semi-Annual Inspection Maintenance and Service cooling Tower 9 CT2

2.00
EA
__________________
__________________

Semi-Annual Inspection Maintenance and Service Cooling Tower 9 CT3

4.00
EA
__________________
__________________

Semi-annual inspection maintenance and service BMSC System Controller

POP Begin: 09-20-2026

2.00
EA
__________________
__________________

Semi-annual inspection maintenance and service condenser water pump 9 P4

2.00
EA
__________________
__________________

Semi-annual inspection maintenance and service condenser water pump 9 P5

4.00
EA
__________________
__________________

Semi-annual inspection maintenance and service VFD 9 P4

4.00
EA
__________________
__________________

Semi-annual inspection maintenance and service VFD 9 P5

4.00
EA
__________________
__________________

Semi-annual inspection maintenance and service VFD Cooling Tower 1

4.00
EA
__________________
__________________

Semi-annual Inspection VFD Cooling Tower 2

4.00
EA
__________________
__________________

Semi-annual inspection maintenance and service VFD Cooling Tower 3

2.00
EA
__________________
__________________

Semi-annual inspection maintenance and service Pump Skid 1

2.00
EA
__________________
__________________

Semi-annual inspection maintenance and service Pump Skid 2

2.00
EA
__________________
__________________

Semi-annual Inspection maintenance and service Pump skid 7

2.00
EA
__________________
__________________

Semi-annual inspection maintenance and service Pump Skid 8

2.00
EA
__________________
__________________

Corrective Maintenance by modification

2.00
EA
__________________
__________________

Emergency Services

GRAND TOTAL