S04- Site Visit Meeting Doc.docx
DOCX document 18 KB Posted
- Solicitation number
- 36C25921Q0366
View the file
Other files
| File | Type | Posted |
|---|---|---|
| S04- Site Visit Meeting Attendance_proj 554-21-132.pdf | ||
| 36C25921Q0366 0002.docx | DOCX document | |
| 36C25921Q0366 0001.docx | DOCX document | |
| 36C25921Q0366_1.docx | DOCX document | |
| Drawings 554-21-132 Install DI Water.pdf | ||
| Specifications 554-21-132 Install DI Water.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pre-Proposal Site Visit Meeting 36C25921Q0366 DI Water Drops for Lab Analyzer and Sinks at Rocky Mountain Regional VAMC
The contractor is to provide all labor, tools, materials, equipment, and supervision required to complete the construction of the DI Water Drops for Lab Analyzer and Sinks installation at the RMR VA Medical Center. Work to include installing deionized (DI) water to new laboratory equipment and sinks in the Pathology and Medical Laboratory.
Location: Rocky Mountain Regional VA Medical Center
AGENDA:
· Introduction of Christina Beeler-Blackburn CS, Steve Manciagli COR
· The pre-offer meeting/site walk is not mandatory
· QUESTIONS During site visit MUST BE WRITTEN DOWN
· Address where to send RFP:
· Electronic submissions to Christina.Beeler-Blackburn@va.gov
· Pertinent Dates:
· Questions due April 29, 2021 no later than 1:00 PM MT prior to closing of RFQ, any questions submitted after this time will not be reviewed or answered! Submit to Christina.Beeler-Blackburn@va.gov
· We’ll get the answers back to you timely
· Proposals due on 5/12/2021 at 10:30 AM MT via email
· Prospective offerors are prohibited from attempting to gain information by inquiring with VA employees about project other than through written questions submitted to Contracting Officer.
· Prospective offerors are prohibited from visiting site other than through formal invitation by Contracting Officer.
· Attendees of walk-through are to stay as a group while walking to various locations and are to leave the future project site once the walk-through is concluded.
· All VA campuses are Tobacco Free, including but not limited to, smokeless tobacco and vaping.
· Masks are to be worn at all times while on VA property.
· Confirmation of construction range is between $25,000 and $100,000.
· Bid Guarantee & Payment/Performance Bonds: Bonds are required for any offers over $150,000 threshold.
· Contractor shall begin performance within 10 days after Notice To Proceed (NTP) and complete within 150 days. This project will be completed in two phases with a 90 day period between each phase.
· Post Award Compliance:
· Compliance with Davis Bacon Wages and Application wage determination shall be expected of the contractor. The contractor can submit their weekly certified payrolls with their monthly invoice.
File details come from the government source that posted it. Updated .