36C25920R0095 0002.docx
DOCX document 18 KB Posted
- Solicitation number
- 36C25920R0095
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sign-in sheet and notes.pdf | ||
| 36C25920R0095 0001.docx | DOCX document | |
| Drawings-Cart-Wash-Full-Set 7-6-20.pdf | ||
| S02 - Drawings Cart Wash Full Set 7-8-19.pdf | ||
| S02 - 666-17-02s specs.pdf | ||
| Past Performance Questionnaire.docx | DOCX document | |
| 36C25920R0095_1.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 666-17-02s 36C259 Department of Veterans Affairs Network Contracting Office
NCO 19
6162 South Willow Drive, Suite 300 Greenwood Village
CO
80111 36C259 Department of Veterans Affairs Network Contracting Office
NCO 19
6162 South Willow Drive, Suite 300 Greenwood Village
CO
80111 To all Offerors/Bidders
36C25920R0095 07-23-2020
X x x
Solicitation due 7/30/2020 1:00 PM MT x The Purpose of this amendment is to:
a. Post the questions and answers and sign in sheets see attached.
b. extend the closing date form 7/28/2020 1:00PM MT to 7/30/2020 1:00PM MT
c. All other terms and conditions remain the same.
1. Please provide HVAC Demo Plans.
Answer. HVAC Demo plans do not exist. Windows removed for duct installation shall be replaced with white aluminum metal panel insulated with 2” rigid fiberglass.
2. Currently there is a temporary HVAC system that might interfere with the new system, what is the contractor to do with the temporary HVAC system?
Answer. Contractor shall remove temporary air handler and duct system and turn over to VA Maintenance.
3. P100 Plumbing Note 9 – Please provide a detailed drawing of the connection of the existing condensate drain line into the drain pipe inside the wall. The existing connection has an air gap into the existing utility sink.
Answer. In lieu of routing condensate inside wall provide ¾” type L rigid copper from above ceiling, through inside of wall, out a chrome escutcheon, to existing floor drain with air gap. Mount piping on floor with galvanized Unistrut. Cut pipe outlet at 45 degrees.
4. In regards to the waterproofing, does the concrete need to be waterproofed to a 100% RH?
Answer: concrete waterproofing shall meet or exceed minimum manufacturers requirements for flooring to be installed.
5. Document A102 floor finish plan calls for waterproofing in corridor only but not in room 103A and 103. Is that correct?
Answer: refer to sheet A101. All areas designated with hatch pattern, including rooms 103/103A will need waterproofing for cart wash project.
6. In the corridor where there are brick walls, the base installation is going to be rough. A possible solution would be to switch to Millwork base which is much thicker and would provide a better finished product. Please advise.
Interior Designer Answer: Millwork base would not work well in an area where waterproofing is needed. A profile rubber base may be an alternate option (this will likely increase your cost), or our standard rubber base. The flooring/base installer would need to account for the product adhering to brick and provide us a solution for being able to utilize that product. Whether that is skim-coating the portion of the brick where the base would adhere to, or specifying a glue that would suffice, I’m not sure what the right solution would be.
See attached document: Sign-in sheet and notes.