36C25920R0095_1.docx
DOCX document 79 KB Posted
- Solicitation number
- 36C25920R0095
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25920R0095 0002.docx | DOCX document | |
| Sign-in sheet and notes.pdf | ||
| 36C25920R0095 0001.docx | DOCX document | |
| Drawings-Cart-Wash-Full-Set 7-6-20.pdf | ||
| S02 - Drawings Cart Wash Full Set 7-8-19.pdf | ||
| S02 - 666-17-02s specs.pdf | ||
| Past Performance Questionnaire.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. SOLICITATION NUMBER
2. TYPE OF SOLICITATION
3. DATE ISSUED
PAGE OF PAGES
4. CONTRACT NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
6. PROJECT NUMBER
7. ISSUED BY
CODE
8. ADDRESS OFFER TO
a. NAME
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014)
STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION
SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).
YES
NO
a.
Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b.
An offer guarantee is, is not required.
c.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d.
Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
36C25920R0095 X 07-02-2020 666-17-02s 36C259 Department of Veterans Affairs Network Contracting Office
NCO 19
6162 South Willow Drive, Suite 300 Greenwood Village
CO
80111 josiah.benton@va.gov
Josiah Benton josiah.benton@va.gov Contractor shall provide all labor, equipment, materials and supervision necessary to perform all work required for this project in accordance with all drawings and the scope of work. The project is located at the VA Medical Center located at 1898 Fort Road, Sheridan, WY 82801.
Project magnitude: between $100,000 and $250,000. The NAICS code is 236220 - Small Business size standard is $39.5 M.
In accordance with P.L. 109-461, this acquisition is 100% set aside for Service Disabled Veteran Owned Small Businesses concerns. See VAAR 852.219-10, Notice of Total Service Disabled Veteran Owned Small Business Set-Aside of this solicitation for information in regard to requirements in order to be considered. Offerors must be both VISIBLE and VERIFIED by the Department of Veterans Affairs Center for Verification and Evaluation (CVE) At the time of offers submission.
Failure to be both VERIFIED by CVE and VISIBLE on VetBiz prior to contract award will result in the offeror’s proposal being deemed non-compliant. All offerors are urgedto contact the CVE and submit the required documents to obtain CVE verification of their SDVOSB statusif they have not already done so.
In accordance with FAR 52.204-7, System for Award Management (SAM), prospective contractors shall be registered in the SAM database prior to award of a contract or agreement.
A site visit will be held on July 7, 2020 at 10:30 am MT. Please meet at building 5, room 108.
All questions in relation to this solicitation must be submitted in writing via e-mail to josiah.benton@va.gov and received no later than July 10, 2020 at 11:00 AM MT, to permit adequate time for the Government to reply to inquiries.
Proposals shall be received by 1:00 PM Mountain Time on July 28, 2020. There will be no public opening of the proposal Submit proposals to: Josiah.benton@va.gov.
52.228-13 ALTERNATIVE PAYMENT PROTECTIONS (JULY 2000)
Payment Bond; Irrevocable Letter of Credit (ILC)
X 52.211-10 X
1:00 PM
07-28-2020 X
14. NAME AND ADDRESS OF OFFEROR
15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE
FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (
26. ADMINISTERED BY
27. PAYMENT WILL BE MADE BY
PHONE:
FAX:
28. NEGOTIATED AGREEMENT
29. AWARD
Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code) (Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror) (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
36C259 Department of Veterans Affairs Network Contracting Office
NCO 19
6162 South Willow Drive, Suite 300 Greenwood Village
CO
80111 Department of Veterans Affairs Financial Service Center PO Box 149971 Austin
TX
78714-9971
Table of Contents
| PART I - THE SCHEDULE | 1 |
| SECTION A - SOLICITATION/CONTRACT FORM | 1 |
| A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair) | 1 |
| A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK | 2 |
| A.3 Bid Schedule | 5 |
| A.4 SCOPE OF WORK | 6 |
| INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS | 10 |
| 2.1 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) | 10 |
| 2.2 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014) | 10 |
| 2.3 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995) | 11 |
| 2.4 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) | 11 |
| 2.5 VAAR 852.252-70 SOLICITATION PROVISIONS OR CLAUSES INCORPORATED BY REFERENCE (JAN 2008) | 12 |
| REPRESENTATIONS AND CERTIFICATIONS | 13 |
| 3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2020) | 13 |
| GENERAL CONDITIONS | 17 |
| 4.1 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) | 17 |
| 4.2 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (MAY 2020) | 17 |
| 4.3 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (MAY 2014) | 20 |
| 4.4 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 23 |
| 4.5 SUPPLEMENTAL INSURANCE REQUIREMENTS | 25 |
| 4.6 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018) | 25 |
| 4.7 VAAR 852.219-10 VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (JUL 2019) (DEVIATION) | 25 |
| 4.8 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING AND COMPLIANCE (JUL 2018) | 27 |
| 4.9 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008) | 28 |
| 4.10 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018) | 28 |
| 4.11 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019) | 29 |
| 4.12 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019) | 30 |
| 4.13 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (APR 2019) | 31 |
| 4.14 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008) | 31 |
| 4.15 List of Attachments | 43 |
A.3 Bid Schedule
Bid Schedule The contractor shall furnish all labor, equipment, materials, and supervision to shall remodel building 9, room 103 into two separate rooms in order to provide a cart/wheelchair washing station and associated storage. The contractor shall install a new HVAC system for room 102 and the new cart washing rooms. The Contractor shall prepare and install new flooring in the corridor C103 directly adjacent to the Cart washing rooms, including the portion leading to building 71 first floor up to the double doors, per the proposed drawings. The location of work will be in building 9, first floor, at the VA Medical Center located at 1898 Fort Road, Sheridan, WY 82801.
All work must, as a minimum, be in accordance with all applicable codes indicated in the Department of Veterans Affairs (VA), specifications associated with this SOW, and VA PUBLICATIONS (Master Construction Specifications, Construction Standards, etc.).
The contractor shall include prices for all items listed in the pricing schedule and include all costs associated for work in the SOW, whether or not specifically listed in the pricing schedule. Work will be accomplished at the Department of Veterans Affairs, located at 1898 Fort Road, Sheridan, WY 82801.
| CLIN |
| Description |
| Qty |
| Unit of issue |
Firm Fixed Price Lump Sum Total amount
| 0001 |
| Base Pricing |
(SEE SOW FOR DETAILS)
Provide all work as described by attached SOW, Plans, Specifications, and Wage Determinations for Veterans Administration project VA Project 666-17-02S: B9 Cart Washing Station at the Department of Veterans Affairs, located at 1898 Fort Road, Sheridan, WY 82801. as described in the attached scope of work. Price includes all costs for construction. Cost shall include but not be limited to direct and indirect costs including profit, overhead, general and administration, insurance, labor, bonds, taxes, necessary for 100% completion of the project as indicated in the attached SOW. The construction performance period is 90 calendar days from receipt of notice to proceed.
| 1 |
| Job |
| $_________ |
Grand Total $_________________
A.4 SCOPE OF WORK
Page 1 of Page 1 of
SOW
a. The Contractor shall remodel building 9, room 103 into two separate rooms in order to provide a cart/wheelchair washing station and associated storage. The contractor shall install a new HVAC system for room 102 and the new cart washing rooms. The Contractor shall prepare and install new flooring in the corridor C103 directly adjacent to the Cart washing rooms, including the portion leading to building 71 first floor up to the double doors, per the proposed drawings. The location of work will be in building 9, first floor, at the VA Medical Center located at 1898 Fort Road, Sheridan, WY 82801.
b. All work must, as a minimum, be in accordance with all applicable codes indicated in the Department of Veterans Affairs (VA), specifications associated with this SOW, and VA PUBLICATIONS (Master Construction Specifications, Construction Standards, etc.).
II. Work includes, selective demolition, HVAC, construction of new walls, floors and finishes, electrical and plumbing changes, and installation of cart cleaning equipment:
a. PHASING
i. Due to room 102 being an IT Communications Closet, room 102 shall remain secured at all times. Room 103 can be separately secured for construction.
ii. Due to the heat loading of the IT equipment in room 102, and the inadequacy of the existing AC system in room 102, a temporary AC unit is to be installed, during construction, until the new HVAC system for rooms 102, 103, and 103A is installed and certified operational. Coordinate with COR and Station HVAC contractor prior to temporary unit installation for technical and operational acceptability.
b. HVAC
i. The contractor shall install a new 4-ton rooftop unit and associated equipment and ductwork as detailed in the drawings, to provide AC to room 102, 103 and 103A.
ii. Contractor shall provide and install new temperature sensors and control systems as detailed in the drawings.
iii. The contractor shall remove the condensate drain line from the existing HVAC unit in room 103 as a result of the sink move.
iv. The new HVAC system shall be third party balanced and commissioned.
c. Secure Room 102
i. The contractor shall relocate and reinstall the existing corridor door, VA provided from demolition, on room 102.
ii. The contractor shall plan on providing any necessary door hardware/latching systems.
d. Remodel Room 103
i. The contractor shall remodel and divide the existing room 103 into three rooms as detailed in the drawings.
1. Room 103 shall be a wet environment and shall be made to house the cart washing machine
2. Room 103A shall be a storage area for the cleaned equipment and house a desk/workspace for the cleaning machine operator.
3. A vestibule, C103, shall be created in order to allow access from both rooms 102 and 103A directly to the corridor.
ii. The contractor shall be provided the cart washing machine for installation by the VA.
1. The contractor shall be responsible for evaluating the operational status of the machine and making any necessary repairs.
2. The contractor shall provide all necessary plumbing and electrical connections to the machine.
3. The contractor shall verify that all electrical circuits in the wet room are GFI protected and shall make the necessary changes if they are not.
4. The cart washing machine is a Medco Equipment model 64x machine.
iii. The contractor shall relocate the existing sink in room 103 to the location shown on the drawings and shall make all necessary plumbing changes.
iv. The contractor shall open up the bricked in former room entryway behind the existing sink location and install a new door for room 103 to access the corridor, as detailed in the drawings.
v. The contractor shall change the existing exhaust fan in room 103 such that it exhausts moist air out of the room and to the exterior of adjoining structures.
1. The moist air shall not be exhausted under any existing structure.
vi. The contractor shall install new walls to create a new room 103A.
1. The contractor shall make necessary ceiling and lighting changes as detailed in the drawings.
2. The contractor shall make necessary plumbing, electrical, data, and other system changes as detailed in the drawings.
e. The contractor shall provide the VA with a red-lined set of construction drawings at the conclusion of the project, showing any as-built deviations from the plans.
III. Work will include:
a. Base Bid:
i. All work listed in drawings and specifications.
IV. Alternates:
a. Bid alternates shall be provided as deductive standalone bid prices. Alternates, if need be, will be removed from the base bid until the VA reaches a price that will meet the final project budget.
b. Deductive Alternate Number 1:
i. Lead Paint. Cart washing room and flooring project envelope does not contain Asbestos based upon the VA reports and re-inspections (2010 and 2015, respectively), however, the potential for lead based paint may be present in areas of construction activities and will need to be abated. Contractor to provide total separate line item for abatement and removal costs if lead is discovered within the project envelope. If, no lead is discovered, then the project will proceed with all other payments per contract, less the deductive alternate.
V. CONTRACT DOCUMENTS
a. Contract Documents have been provided in the form of existing building drawings and project specifications.
VI. Hazardous materials
1. Contractor Requirements:
a) The Contractor shall be responsible for performing all work and providing all materials required to achieve the work required above. The Government will not be responsible for any additional expense to the Contractor if the conditions causing those expenses could have been discovered in an on-site inspection prior to bid submittal.
b) Building 9, 1st floor (basement) has been involved in a hazardous materials report and reinspection (2010 and 2015, respectively), and indicates that there is no asbestos contained within the envelope of this projects work. Report will be provided to successful bidder.
c) Under government workplace safety regulations, the Contractor is responsible for the training of his employees. The Contractor is to ensure that its’ employees and the Competent Person have completed all necessary Safety Training. Contractors will have workers or sub-contractors that are licensed and certified in asbestos, lead paint and mold abatement through an EPA approved Federal or State program, if applicable.
d) If asbestos is suspected, Contractor is required to use a laboratory that shall be NVLAP accredited for Airborne Asbestos Analysis.
e) Contractor shall dispose of all asbestos-containing and/or contaminated material in an EPA-approved landfill. The Government’s asbestos-containing material shall not be mixed with asbestos-containing/contaminated waste generated by other entities. Manifests must reflect only material which was abated from this facility and its final disposal location.
f) PROOF OF LICENSE AND CERTIFICATION. The Contractor shall submit proof to the Contracting Officer that they are licensed in the appropriate state prior to the start of asbestos abatement. The Contractor shall also submit proof that each employee who will be involved in this project is certified in that state in accordance with the above regulations. Proof of their certificates shall be submitted prior to the start of the project.
g) PROOF OF EMPLOYEE TRAINING AND MEDICAL EXAMINATION. Prior to the start of asbestos abatement, the Contractor shall submit proof to the Contracting Officer that:
1. Employees and the Competent Person, as defined in 29 CFR 1926.1101, have been trained in accordance with the appropriate state regulations and as defined in all other applicable regulations.
2. The Competent Person will be continuously on-site during all asbestos abatement procedures.
3. The employees and the Competent Person have completed all medical examinations as required by the applicable federal, state, and local regulations.
h) WASTE MANIFESTS (if applicable). The Contractor shall obtain a list of approved sanitary landfills for asbestos disposal from the EPA and/or applicable State regulatory agencies. Prior to the start of asbestos abatement, the Contractor shall submit to the Contracting Officer a copy of the written notification that was sent to the disposal site operator/owner of the intent to dispose of the asbestos-containing materials, including the estimated quantity and the tentative date for disposal. Upon completion of asbestos abatement, the Contractor shall submit proof to the Contracting Officer that all of the asbestos-containing materials have been disposed of in accordance with all applicable regulations. This shall include acknowledgment from the disposal site operator/owner in writing that the waste has been delivered in a manner and condition acceptable to the disposal site operator/owner.
i) TEST RESULTS. All Test Results will be made available to the Contracting Officer through the COR:
1. Air Sampling and Analysis: All costs associated with air monitoring and analysis and all OSHA personnel air monitoring requirements shall be included in bid by the Contractor.
2. Air Monitoring Results: Shall be reported to the Contracting Officer and COR within 24 hours after the completion of a sampling period, with written results to be submitted to the Contracting Officer within five (5) working days. Test results shall indicate each sample's pump serial number, time weighted average (TWA) fiber count, pump start time, pump stop time, date, pump flow rate, and exact location of where the sample was taken.
Project POP: 90 days total from Notice to Proceed
End of Statement of Work
PART I - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS
PART I/SECTION A – REQUEST FOR QUOTE
This is a Request for Quote in accordance with FAR Part 13. Potential offerors must follow all instructions in order to be compliant with the solicitation.
It is the responsibility of the offeror to verify that their offer is complete. The offeror is responsible for submitting all required forms and documents with the offer.
The Government will award a single contract resulting from this solicitation to a responsible SDVOSB offeror whose offer conforming to the solicitation will be most advantageous to the Government based on Past Performance, Safety and Price.
I.1A JOINT VENTURES
If submitting an offer as a joint venture as defined by P.L. 109-461 AND Department of Veterans Affairs I.L. 049-06-4, http://www.vetbiz.gov/library/jtventure.pdf , an offeror must provide a copy of the joint venture agreement specific to the project that is consistent with the percentage of required work and net proceed. Additionally, the offeror must provide a breakdown or labor of which is to be performed by the SDVOSB firm and that which is performed by the small business joint venture firm and that which is sub-contracted. All Joint Ventures will be required to be registered and verified as an entity in VETBIZ.
I.3A SITE VISIT
A site visit will be held on July 7, 2020 at 10:30 AM Mountain Time (MT) at the VA Medical Center located at 1898 Fort Road, Sheridan, WY 82801 please meet at building 5, room 108. All offerors, consultants, subcontractors, manufacturers and suppliers are encouraged to attend this meeting to familiarize themselves with the project, and project site. See FAR Clause 52.236-3, Site Investigation and Conditions Affecting the Work, and FAR Provision 52.236-27, Site Visit (Construction) of this solicitation.
I.4A SELECTION CRITERIA/QUOTE PREPARATION INSTRUCTIONS
Quotes will be evaluated in accordance with FAR 13.106 Simplified Acquisition Procedures Award will be made based on the following factors:
Factor 1 – Past Performance Factor 2-- Price Offerors are encouraged to provide their best offers with the past performance information requested for evaluation. The Government, based on the offered material presented, will award to the offeror that best demonstrates to be most advantageous for the Government.
Factor 1 - Past Performance: Offerors shall provide past performance information on two (2) federal, state, local government or private contract of similar type, scope, size and complexity. For purposes of this evaluation, a relevant project is further defined as experience with sewer lines in a hospital environment. Project shall have a minimum amount of $25,000.00 or more and completed within the past five years from the date of issuance of this RFP. If a completed Contractor Performance Assessment Reporting System (CPARS) evaluation is available, it shall be submitted with the quote. The Government may also evaluate recent and relevant past performance, based upon sources available to the contracting officer that may include Past Performance Information Retrieval System (PPIRS), Federal Awardee Performance and Integrity Information System (FAPIIS) and Electronic Subcontract Reporting System (eSRS). IF THE OFFEROR CANNOT PROVIDE A CPARS FOR PROJECTS LISTED IN FACTOR 1, then the offeror shall submit Past Performance Questionnaires (PPQ).
Completed PPQs should be submitted directly from your client via email to Josiah Benton at josiah.benton@va.gov. If you have any questions, please contact Josiah Benton at josiah.benton@va.gov. If the offeror is unable to contact a client for a project(s) before closing date, the offeror should complete and submit with the quote the first page of the PPQ, which will provide contract and client information for the respective project(s). Offerors should follow-up with clients/references to ensure timely submittal of questionnaires.
Basis of Evaluation: Past Performance will be evaluated in accordance with FAR 13.106-2 and award will be made to the offeror presenting the best value to the Government.
Factor 2 - Price: Offerors shall provide pricing as requested in the Schedule of Service identified within the SF1442 Basis of Evaluation: The Government will evaluate price based on the total price. Total price consists of the basic requirements. Analysis will be performed by one or more of the following techniques to ensure a fair and reasonable price:
| • | Comparison of quoted prices received in response to the RFQ |
| • | Comparison of quoted prices with the IGCE. |
| • | Comparison of quoted prices with available historical information. |
The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered.
Special Standard of Responsibility Solicitation Submittal Requirements:
The Offeror shall submit the following information: (For a partnership or joint venture, the following submittal requirements are required for each Contractor who is part of the partnership or joint venture and for the entity itself. EMR shall not be submitted for subcontractors.)
(1) OSHA or EPA Violation(s):
Offerors shall provide Summary of Work-Related Injuries and Illnesses, affirming that the Offeror has no more than three serious, or one repeat, or one willful OSHA or EPA violation(s) in the past 3 years
(2) Experience Modification Rate (EMR):
Offerors shall provide documentation to show that the offeror has an Experience Modification Rate (EMR) of equal to or less than 1.0.
Offerors who fail to meet any special standard of responsibility will not be eligible to receive contract award.
PART I/SECTION B - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS
I.1B COST RANGE: Between $100,000 and $250,000 I.2B GENDER: Wherever the masculine gender is used in this solicitation and contract documents, it shall be considered to include both masculine and feminine.
I.3B METRIC PRODUCTS:
Products manufactured to metric dimensions will be considered on an equal basis with those manufactured using inch-pound units, providing they fall within the tolerance specified using conversion tables contained in the latest revision of Federal Standard No. 376, and all other requirements of this document are met.
If a product is manufactured to metric dimensions and those dimensions exceed the tolerance specified in the inch-pound units, a request should be made to the Contracting Officer to determine if the product is acceptable. The Contracting Officer, in concert with the Contracting Officer’s Representative (COR), will accept or reject the product.
I.4B REQUESTS FOR INFORMATION:
All requests for information must be submitted in writing to the Contracting Officer for action no later than the date shown in Block 10 of the Standard Form 1442, Solicitation, Offer and Award.
I.5B QUOTE REQUIREMENTS
General – Both technical and price shall be submitted in response to this solicitation. Quotes shall be submitted via email to josiah.benton@va.gov. Emails are limited to five (5) MB. The quote, in its entirety, shall not exceed two emails (one email for price, and one email for technical/past performance) of 5MB each. Technical (not including past performance questionnaires) is limited to 30 pages. Price shall be in a separate electronic document from the technical and past performance portions of the quote. The offeror’s technical response shall clearly address each evaluation factor listed in this solicitation. Failures to submit in the format required and clearly address those factors may result in rejection of the offer. Further details on electronic submission are outlined below. Offerors shall include all required Representations and Certifications and complete their registration in System for Award Management (SAM). See FAR 52.204-7 and 52.204-8, of this solicitation.
Quotes shall be received by 1:00 PM MT on July 28, 2020. There will be no public opening. Submit quotes to: josiah.benton@va.gov.
Important Notice: Apparent successful offerors must apply for and receive verification from the Department of Veterans Affairs Center for Verification and Evaluation (CVE) in accordance with 38 CFR Part 74 and VAAR 819.70 by submission of documentation of Veteran status, ownership and control sufficient to establish appropriate status, offerors must be both VISIBLE and VERIFIED by the Department of Veterans Affairs Center for Verification and Evaluation at the time of contract award. Failure to be both VERIFIED by CVE and VISIBLE on VetBiz at the time of contract award will result in the offeror’s proposal being deemed non-responsive. All offerors are urged to contact the CVE and submit the aforementioned required documents to obtain CVE verification of their SDVOSB status if they have not already done so.
I.6B REQUIREMENTS FOR ELECTRONIC SUBMISSION OF OFFER
Unless paper offers are specifically authorized in an individual solicitation, all responses to solicitations must be submitted electronically as described below. Responses submitted in a paper form are unacceptable. Failure to comply with this requirement may jeopardize the possibility of receiving an award for the contract due to noncompliance with the terms of the solicitation. You must submit your electronic offer, and any supplemental information (such as spreadsheets, backup data, technical information), using any of the electronic formats and media described below.
In addition, contractors are notified of the award via an electronic Notice of Award e-mail. The award document will be attached to the Notice of Award e-mail.
Acceptable Electronic Formats (Software) for Submission of Offers
1. Files readable using the current Microsoft© Office version Products: Word, Excel, PowerPoint, or Access. Print or scan images of spreadsheets are not acceptable. Please see security note below for caution regarding use of macros. When submitting construction drawings contractors are required to submit one set in AutoCAD and one set in Adobe PDF. (purpose: contracting can open the PDF version and engineering can open AutoCAD files)
1. Files in Adobe© PDF (Portable Document Format) Files: When scanning documents scanner resolution should be set to 200 dots per inch, or greater.
1. Other electronic format. If you wish to submit an offer using another format other than described in these instructions, e-mail the Contracting Officer who issued the solicitation. Please submit your request at least ten (10) calendar days before the scheduled closing date of the solicitation. Request a decision as to the format acceptability and make sure you receive approval of the alternate format before using it to send your offer.
1. Please note that we can no longer accept .zip files due to increasing security concerns.
1. E-mail Submission Procedures: For simplicity in this guidance, all submissions in response to a solicitation will be referred to as offers.
a. Subject Line: Include the solicitation number, name of company, and closing date of solicitation. Use only one of the terms Quotation, Offer, or Bid depending on the solicitation type.
b. Size: Maximum size of the e-mail message shall not exceed five (5) megabytes. Only one email is permitted unless otherwise stated in this solicitation or in writing by the Contract Officer submitting the solicitation.
c. Unless approved by the contracting officer: DO NOT submit a link to your PDF documents. Please submit your request in an email for other electronic format at least ten (10) calendar days before the scheduled closing date of the solicitation. Request a decision as to the format acceptability and ensure you receive approval of the alternate format before using it to send your offer.
Each electronic offer must also include a signed and scanned SF-1442, Solicitation, Offer, and Award (Construction, Alteration, or Repair)
The Microsoft Outlook © Email time/date stamp will be used to date and time stamp offers for the official record of receipt for the submission. The date and time stamp in recipients “inbox” is the official record of receipt.
Security Issues, Late Bids, Unreadable Offers
1. Late submission of offers is outlined at FAR 52.215-1(c)(3). Particular attention is warranted to the portion of the provision that relates to the timing of submission.
1. Please see FAR 15.207(c) for a description of the steps the Government shall take with regard to unreadable offers.
1. To avoid rejection of an offer, vendors must make every effort to ensure their electronic submission is virus-free. Submissions or portions thereof submitted and which the automatic system detects the presence of a virus or which are otherwise unreadable will be treated as “unreadable” pursuant to FAR 15.207(c).
1. The virus scanning software used by our e-mail systems cannot always distinguish a macro from a virus. Therefore, sending a macro embedded in an e-mail message or an e-mail attachment may cause the e-mail offer to be quarantined. You may send both the spreadsheet and the spreadsheet saved in PDF format to ensure that your quote is readable.
1. Password protecting your offer is not permitted. The Contracting Officer will file the offer electronically which will allow access only by designated individuals.
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
2.1 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
(End of Provision)
2.2 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)
(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers.
(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
(End of Provision)
2.3 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for— July 7, 2020 10:30 AM MT
(c) Participants will meet at— Meet at bldg room 108 (End of Provision)
2.4 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
http://www.acquisition.gov/far/index.html http://www.va.gov/oal/library/vaar/
(End of Provision)
| FAR Number |
| Title |
| Date |
| 52.204-7 |
| SYSTEM FOR AWARD MANAGEMENT |
| OCT 2018 |
| 52.204-16 |
| COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING |
| JUL 2016 |
| 52.204-22 |
| ALTERNATIVE LINE ITEM PROPOSAL |
| JAN 2017 |
| 52.215-1 |
| INSTRUCTIONS TO OFFERORS—COMPETITIVE ACQUISITION |
| JAN 2017 |
| 52.222-23 |
| NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION |
| FEB 1999 |
| 52.236-28 |
| PREPARATION OF PROPOSALS—CONSTRUCTION |
| OCT 1997 |
2.5 VAAR 852.252-70 SOLICITATION PROVISIONS OR CLAUSES INCORPORATED BY REFERENCE (JAN 2008) The following provisions or clauses incorporated by reference in this solicitation must be completed by the offeror or prospective contractor and submitted with the quotation or offer. Copies of these provisions or clauses are available on the Internet at the Web sites provided in the provision at FAR 52.252-1, Solicitation Provisions Incorporated by Reference, or the clause at FAR 52.252-2, Clauses Incorporated by Reference. Copies may also be obtained from the contracting officer.
[Contracting officer shall list all FAR and 48 CFR Chapter 8 (VAAR) provisions and clauses incorporated by reference that must be completed by the offeror or prospective contractor and submitted with the quotation or offer.] (End of Provision)
REPRESENTATIONS AND CERTIFICATIONS
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2020)
(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 236220.
(2) The small business size standard is $39.5 Million.
(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.
(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.
(2) If the provision at 52.204–7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:
[ ] (i) Paragraph (d) applies.
[ ] (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.
(c)(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:
(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—
(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;
(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or
(C) The solicitation is for utility services for which rates are set by law or regulation.
(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.
(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements—Representation. This provision applies to all solicitations.
(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.
(v) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—
(A) Are not set aside for small business concerns;
(B) Exceed the simplified acquisition threshold; and
(C) Are for contracts that will be performed in the United States or its outlying areas.
(vi) 52.204-26, Covered Telecommunications Equipment or Services—Representation. This provision applies to all solicitations.
(vii) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations—Representation.
(viii) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.
(ix) 52.209-11, Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law. This provision applies to all solicitations.
(x) 52.214-14, Place of Performance—Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.
(xi) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.
(xii) 52.219-1, Small Business Program Representations (Basic, Alternates I, and II). This provision applies to solicitations when the contract will be performed in the United States or its outlying areas.
(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.
(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.
(C) The provision with its Alternate II applies to solicitations that will result in a multiple-award contract with more than one NAICS code assigned.
(xiii) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract will be performed in the United States or its outlying areas.
(xiv) 52.222-22, Previous Contracts and Compliance Reports. This provision applies to solicitations that include the clause at 52.222-26, Equal Opportunity.
(xv) 52.222-25, Affirmative Action Compliance. This provision applies to solicitations, other than those for construction, when the solicitation includes the clause at 52.222-26, Equal Opportunity.
(xvi) 52.222-38, Compliance with Veterans' Employment Reporting Requirements. This provision applies to solicitations when it is anticipated the contract award will exceed the simplified acquisition threshold and the contract is not for acquisition of commercial items.
(xvii) 52.223-1, Biobased Product Certification. This provision applies to solicitations that require the delivery or specify the use of USDA-designated items; or include the clause at 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts.
(xviii) 52.223-4, Recovered Material Certification. This provision applies to solicitations that are for, or specify the use of, EPA-designated items.
(xix) 52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals--Representation. This provision applies to solicitations that include the clause at 52.204-7.)
(xx) 52.225-2, Buy American Certificate. This provision applies to solicitations containing the clause at 52.225-1.
(xxi) 52.225-4, Buy American—Free Trade Agreements—Israeli Trade Act Certificate. (Basic, Alternates I, II, and III.) This provision applies to solicitations containing the clause at 52.225-3.
(A) If the acquisition value is less than $25,000, the basic provision applies.
(B) If the acquisition value is $25,000 or more but is less than $50,000, the provision with its Alternate I applies.
(C) If the acquisition value is $50,000 or more but is less than $83,099, the provision with its Alternate II applies.
(D) If the acquisition value is $83,099 or more but is less than $100,000, the provision with its Alternate III applies.
(xxii) 52.225-6, Trade Agreements Certificate. This provision applies to solicitations containing the clause at 52.225-5.
(xxiii) 52.225-20, Prohibition on Conducting Restricted Business Operations in Sudan—Certification. This provision applies to all solicitations.
(xxiv) 52.225-25, Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran—Representation and Certifications. This provision applies to all solicitations.
(xxv) 52.226-2, Historically Black College or University and Minority Institution Representation. This provision applies to solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions.
(A) Solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions; and
(B) For DoD, NASA, and Coast Guard acquisitions, solicitations that contain the clause at 52.219-23, Notice of Price Evaluation Adjustment for Small Disadvantaged Business Concerns.
(2) The following representations or certifications are applicable as indicated by the Contracting Officer:
[X](i) 52.204-17, Ownership or Control of Offeror.
[X](ii) 52.204-20, Predecessor of Offeror.
[](iii) 52.222-18, Certification Regarding Knowledge of Child Labor for Listed End Products.
[](iv) 52.222-48, Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment—Certification.
[](v) 52.222-52, Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services—Certification.
[](vi) 52.223-9, with its Alternate I, Estimate of Percentage of Recovered Material Content for EPA-Designated Products (Alternate I only).
[](vii) 52.227-6, Royalty Information.
[](A) Basic.
[](B) Alternate I.
[](viii) 52.227-15, Representation of Limited Rights Data and Restricted Computer Software.
(d) The Offeror has completed the annual representations and certifications electronically in SAM accessed through https://www.sam.gov. After reviewing the SAM information, the Offeror verifies by submission of the offer that the representations and certifications currently posted electronically that apply to this solicitation as indicated in paragraph (c) of this provision have been entered or updated within the last 12 months, are current, accurate, complete, and applicable to this solicitation (including the business size standard applicable to the NAICS code referenced for this solicitation), as of the date of this offer and are incorporated in this offer by reference (see FAR 4.1201); except for the changes identified below [offeror to insert changes, identifying change by clause number, title, date]. These amended representation(s) and/or certification(s) are also incorporated in this offer and are current, accurate, and complete as of the date of this offer.
| FAR Clause # |
| Title |
| Date |
| Change |
Any changes provided by the offeror are applicable to this solicitation only, and do not result in an update to the representations and certifications posted on SAM.
(End of Provision)
GENERAL CONDITIONS
4.1 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the…