About this file

36C25919Q0738 SIM EQ009 Serenity Headwall Install Requirments_.pdf

View the file

Other files for this federal contract opportunity

Other files attached to RFQ - AmicoHeadwall Assemblies, newest first.
File Type Posted
36C25919Q0738-0001001.docx DOCX document
36C25919Q0738-0001000.docx DOCX document
36C25919Q0738-001.docx DOCX document
36C25919Q0738-000.docx DOCX document
36C25919Q0738-003.pdf PDF
36C25919Q0738-002.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Installation lnstructions

Surface Mounted

Serenity Series Panel Wall

User Responsibility

The installation instructions provided are for the Amico standard products. Slight modifications to the installations may be required. The product shipped to the job site may not be exactly as shown on the installation drawings. See additional sheets for project specifics where required.

IMPORTANT: PLEASE READ CAREFULLY PRIOR TO START

• Review and understand all instructions before commencing work.

• Panel Wall installation should conform to the local building codes.

All on-site preparations must be done prior to the delivery of the panel wall units. Please contact Amico to confirm and review all information listed below. Failing to do so may result in discrepancies/misalignments during installation.

Please Note These Keywords and Symbols:

WARNING: Steps where extra care should be taken to prevent injuries and damage.

NOTE: Steps that point out helpful information.

IMPORTANT: Be sure to observe this instruction.

2 Amico Corporation

Preparation Before Installation

1. Review a copy of the final approved shop drawing(s) and/or submittal package. These documents will provide you with technical information specific to your installation, such as:

• Equipment types and quantities

• Room numbers and locations

• Shop drawings of each unit type

• Wiring diagrams and rough-in locations

• Blocking locations

IMPORTANT: Before installation of units, make sure the blocking required for mounting the headwall is installed at locations indicated on shop drawings.

2. Locate the panel wall from the shipping boxes that you wish to install. The contents of each shipping box are listed on the shipping document(s). Product is shipped in multiple sections. Please see pictures below for reference:

• Type A Design – top access panels

• Type B Design – full length panels

Type B Design 3 Sections Unit with full length panels

Type A Design 3 Sections Unit with top access panels

NOTE: Please choose one of the following methods for installation:

A) Typical Method (Positive Mount on Top and Bottom). Pages 4-6.

B) Alternate Method (Positive Mount on Top, Direct Mount at the Bottom). Page 7.

C) Single Hanging Bracket. Pages 8-9.

www.amico.com 3

A) Typical Method (Positive Mount on Top and Bottom)

1. Mark two horizontal lines to locate drilling for mounting of hanging bracket on the wall as follows:

a. First Line: 7" below the ceiling line for the top set of mounting brackets.

b. Second Line (lower location): Refer to the height indicated on shop drawings.

2. Set up hanging brackets as indicated in technical drawing provided with the units. Brackets are located at the top of each section for ease of identification.

3. Mount the brackets on the wall using hardware compliant to local building codes, as per setup diagram. (Figure 2).

NOTE: Hardware used to mount bracket to the wall is supplied by others.

Installation

Figure 2

Ceiling Line

Floor Line

Stud

Blocking

Units secured to the wall;

hardware by others

First Line: 7" Below finished ceiling

Optional blocking based on configuration, see approved shop drawings

Figure 1

Hanging Brackets

Hanging Brackets

Second Line: As per approved shop drawings

Blocking required behind drywall

Ceiling Line

Floor Line

Setup

4 Amico Corporation

Figure 3

Installation

IMPORTANT: Ensure hanging brackets are secured to the wall studs or blocking behind the drywall using screws (provided by others).

4. Remove access panels (using tool provided).

IMPORTANT: See Page 10 for panel removal and handling instructions.

5. Align the sections and connect in 4 places along the vertical edges of each section, using the hardware provided as shown in (Figure 3).

Bolt & Nut Connections

Figure 5

6. Lift the assembly and hang it over the brackets which are already installed on the wall.

NOTE: Make sure the assembly unit is fully engaged into the hanging brackets at all locations (Figure 6).

7. Connect the hanging bracket to the headwall support using the provided self-drilling screws. (Figure 7). Use the number of screws listed below based on section size:

a. 19" to 32" wide section = 2 screws

b. 32.1" to 48" wide section = 4 screws

NOTE: The positive mount will be at the top hanging bracket location (Figure 6).

0.750"

Figure 4

1/4" - 20 Hex Head Bolt

Washer

Nylon-Insert Locknut

Top View Detail/Cross Section www.amico.com 5

8. Make all electrical and piping connections. Electrical services are terminated at junction boxes. Medical gas pipes are terminated as per shop drawing.

9. Attach all removed items:

• Panels (must clip in properly where applicable)

• Devices, extension rings and cover plates

IMPORTANT: Do not overtighten the medgas cover plates.

10. Reinstall the rails.

IMPORTANT: Must use the hardware provided to reinstall the rails.

Installation

Ceiling Line

Screws (provided by others)

Floor Line

Figure 6 Figure 7 Figure 8

Stud

1"

0.164"

Setup Setup #8-Self Drilling/Flat Head Screw

6 Amico Corporation

Installation

B) Alternate Method (Positive Mount on Top, Direct Mount at the Bottom)

Use Alternate Method when Ceiling Grid is in Place

IMPORTANT: Ceiling tiles must be removed during installation to allow for electrical and medgas piping to pass through.

1. Remove Laminate panels from Headwall (Using tool provided).

2. Connect sections using bolt nut connections (see Step 5 of Typical Method Installation).

3. Attach the hanging brackets to the top crosses designated for hanging brackets. Use the number of screws listed below based on section size:

a. 19" to 32" wide section = 2 screws

b. 32.1" to 48" wide section = 4 screws

IMPORTANT: Do not overtighten the screws – these screws will be tightened more once the unit is attached to the wall.

4. Set the unit in the final location on the wall.

5. Secure the unit to the wall through the hanging brackets on the top.

6. Use hardware compliant to local building codes to mount brackets to the wall, as per Figure 9 diagram.

Figure 9

Ceiling Line

Floor Line

Stud

Blocking

Units secured to the wall;

hardware by others

Setup www.amico.com 7

7"

C) Single Hanging Bracket

1. Remove panels (using tool provided) by lifting panels vertically until resistance is felt, then rotate bottom of panel out and pull down. Be careful not to drop panel.

IMPORTANT: See Page 10 for panel removal and handling instructions.

2. Mark horizontal line 7" below finished ceiling line. This line will be used to locate drilling for mounting of hanging bracket on the wall.

3. Align bracket horizontally according to flatwall mounting location (Refer to drawings). Mount the bracket on the wall using hardware compliant to local building codes (Supplied by others). Use mounting line from step 2 to locate mounting holes vertically.

IMPORTANT: Ensure hanging bracket is secured to the wall studs or blocking behind the drywall using screws (provided by others).

4. Hang the unit over the hanging bracket. Secure the unit through lower rear headwall support to the wall as per Figure 11 and Figure 12 diagrams.

IMPORTANT: Ensure headwall support is secured to the wall studs or blocking behind the drywall at the bottom.

Use similar hardware as previously used to secure hanging bracket. (Hardware provided by others).

Installation

Stud

Units secured to the wall;

hardware by othersBlocking

Figure 10

Hanging Bracket Setup

8 Amico Corporation

NOTE: Dimensions above finished floor for lower Headwall support vary for each type of headwall. Please contact Amico if exact dimensions are required for blocking purposes.

5. Make all electrical and piping connections. Electrical services are terminated at junction boxes. Medical gas pipes are terminated as per shop drawing.

6. Attach all removed items:

• Panels (must clip in properly where applicable)

• Devices, extension rings and cover plates

IMPORTANT: Do not overtighten the medgas cover plates.

7. Reinstall the rails.

IMPORTANT: Must use the hardware provided to reinstall the rails.

Installation

Figure 12Figure 11

Ceiling Line

Floor Line

Stud

Blocking

Units secured to the wall;

hardware by others

Hanging Bracket Setup www.amico.com 9

Access Panels

1. Use the provided suction cup to remove the middle panel then the left panel, prior to removing the right panel. Be careful not to drop the panels.

Panels with vertical rails and services

1. Remove vertical rails, where applicable:

• Remove Bottom plate

• Remove Insert strip

• Remove screws

2. Remove device cover plate and loosen electrical devices.

3. Remove panels (using the provided suction cup)

WARNING:

• Stack panels face to face to prevent damage.

• Keep panels as flat as possible when handling or storing.

• Do not drag panels on other panels in order to prevent scratch or scuff.

• Remove the device’s cover plates /extension rings

• Panels must be stored in controlled environment

Panel Removal/Handling

Figure 13

Insert Strip

Rail

Figure 14

10 Amico Corporation

Notes www.amico.com 11 www.amico.com

Amico Corporation | 85 Fulton Way, Richmond Hill, ON L4B 2N4, Canada 71 East Industry Court, Deer Park, NY 11729, USA Toll Free Tel: 1.877.462.6426 | Tel: 905.764.0800 | Fax: 905.764.0862 Email: info@amico.com | www.amico.com

ACA-IM-SERENITY-SURFACE 05.07.2019