36C25919Q0587 36C25919Q0587.docx
DOCX document Posted
- Solicitation number
- 36C25919Q0587
About this file
36C25919Q0587 36C25919Q0587.docx
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25919Q0587-001.docx | DOCX document | |
| 36C25919Q0587 36C25919Q0587_1.docx | DOCX document | |
| 36C25919Q0587-000.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C25919Q0587
PAGE 1 OF
1. REQUISITION NO.
2. CONTRACT NO.
3. AWARD/EFFECTIVE DATE
4. ORDER NO.
5. SOLICITATION NUMBER
6. SOLICITATION ISSUE DATE
a. NAME
b. TELEPHONE NO. (No Collect Calls)
8. OFFER DUE DATE/LOCAL
TIME
9. ISSUED BY
CODE
10. THIS ACQUISITION IS
UNRESTRICTED OR
SET ASIDE:
% FOR:
SMALL BUSINESS
HUBZONE SMALL
BUSINESS
SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
WOMEN-OWNED SMALL BUSINESS
(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
VOSB
8(A)
NAICS:
SIZE STANDARD:
11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
12. DISCOUNT TERMS
13a. THIS CONTRACT IS A
RATED ORDER UNDER
DPAS (15 CFR 700)
13b. RATING
14. METHOD OF SOLICITATION
RFQ
IFB
RFP
15. DELIVER TO
CODE
16. ADMINISTERED BY
CODE
17a. CONTRACTOR/OFFEROR
CODE
FACILITY CODE
18a. PAYMENT WILL BE MADE BY
CODE
TELEPHONE NO.
DUNS:
DUNS+4:
PHONE:
FAX:
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER 18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW IS CHECKED
SEE ADDENDUM
19.
20.
21.
22.
23.
24.
ITEM NO.
SCHEDULE OF SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
(Use Reverse and/or Attach Additional Sheets as Necessary)
25. ACCOUNTING AND APPROPRIATION DATA
26. TOTAL AWARD AMOUNT (For Govt. Use Only) 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA
ARE
ARE NOT ATTACHED.
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA
ARE
ARE NOT ATTACHED
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN _______________
29. AWARD OF CONTRACT: REF. ___________________________________ OFFER
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
DATED ________________________________. YOUR OFFER ON SOLICITATION
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED
SET FORTH HEREIN IS ACCEPTED AS TO ITEMS:
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER) 30b. NAME AND TITLE OF SIGNER (TYPE OR PRINT) 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (TYPE OR PRINT) 31c. DATE SIGNED
AUTHORIZED FOR LOCAL REPRODUCTION
(REV. 2/2012)
PREVIOUS EDITION IS NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.212
7. FOR SOLICITATION
INFORMATION CALL:
STANDARD FORM 1449
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
36C25919Q0587 09-06-2019 Mitchael
Purdom 918-577-4435 09-13-2019
14:00 CST
623/90c Department of Veterans Affairs Network Contracting Office
NCO 19
1011 Honor Heights Drive Muskogee OK 74401-1318 X x x 541350 $7.5 Million N/A X 623/90c Department of Veterans Affairs Oklahoma City VA Medical Center 921 NE 13th. St Oklahoma City OK
OK 74401-1318
623/90c Department of Veterans Affairs Network Contracting Office
NCO 19
1011 Honor Heights Drive Muskogee OK 74401-1318
623/04 Department of Veterans Affairs Financial Services Center PO Box 149971 Austin TX 78714-9971 See CONTINUATION Page Respond to Solicitation:
Preferred: e-mail to mitchael.purdom@va.gov 100% Set-Aside to VOSB which includes SDVOSB Acceptable: mail to (see block 9 above) must be received on/before due date/time (see block 8) **Faxes will not be accepted.** See CONTINUATION Page X X Lance Davis
NCO16L2L2-5045
Table of Contents
| SECTION A | 1 |
| A.1 SF 1449 SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS | 1 |
| SECTION B - CONTINUATION OF SF 1449 BLOCKS | 4 |
| B.1 CONTRACT ADMINISTRATION DATA | 4 |
| B.2 PRICE/COST SCHEDULE | 14 |
| ITEM INFORMATION | 14 |
| SECTION C - CONTRACT CLAUSES | 23 |
| C.1 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL ITEMS (OCT 2018) | 23 |
| C.2 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 29 |
| C.3 52.204-9 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL (JAN 2011) | 29 |
| C.4 52.204-13 SYSTEM FOR AWARD MANAGEMENT MAINTENANCE (OCT 2018) | 29 |
| C.5 52.216-22 INDEFINITE QUANTITY (OCT 1995) | 32 |
| C.6 52.217-8 OPTION TO EXTEND SERVICES (NOV 1999) | 32 |
| C.7 52.217-9 OPTION TO EXTEND THE TERM OF THE CONTRACT (MAR 2000) | 32 |
| C.8 52.219-14 LIMITATIONS ON SUBCONTRACTING (JAN 2017) | 33 |
| C.9 52.222-41 SERVICE CONTRACT LABOR STANDARDS (AUG 2018) | 33 |
| C.10 52.222-55 MINIMUM WAGES UNDER EXECUTIVE ORDER 13658 (DEC 2015) | 40 |
| C.11 52.223-2 AFFIRMATIVE PROCUREMENT OF BIOBASED PRODUCTS UNDER SERVICE AND CONSTRUCTION CONTRACTS (SEP 2013) | 44 |
| C.12 52.232-18 AVAILABILITY OF FUNDS (APR 1984) | 45 |
| C.13 52.232-19 AVAILABILITY OF FUNDS FOR THE NEXT FISCAL YEAR (APR 1984) | 45 |
| C.14 52.232-40 PROVIDING ACCELERATED PAYMENTS TO SMALL BUSINESS SUBCONTRACTORS (DEC 2013) | 45 |
| C.15 VAAR 852.215-71 EVALUATION FACTOR COMMITMENTS (DEC 2009) | 46 |
| C.16 VAAR 852.219-11 VA NOTICE OF TOTAL VETERAN-OWNED SMALL BUSINESS SET-ASIDE (JUL 2016)(DEVIATION) | 46 |
| C.17 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING AND COMPLIANCE (JUL 2018) | 47 |
| C.18 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018) | 48 |
| C.19 VAAR 852.237-70 CONTRACTOR RESPONSIBILITIES (APR 1984) | 49 |
| C.20 VAAR 852.219-10 VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (JUL 2016)(DEVIATION) | 49 |
| C.21 52.212-5 CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT STATUTES OR EXECUTIVE ORDERS—COMMERCIAL ITEMS (MAY 2019) | 50 |
| SECTION D - CONTRACT DOCUMENTS, EXHIBITS, OR ATTACHMENTS | 58 |
| D.1 Wage Determination (Rev 18) OKC OK | 58 |
| SECTION E - SOLICITATION PROVISIONS | 76 |
| E.1 52.212-1 INSTRUCTIONS TO OFFERORS—COMMERCIAL ITEMS (OCT 2018) | 76 |
| E.2 52.212-2 EVALUATION—COMMERCIAL ITEMS (OCT 2014) | 80 |
| E.3 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) | 80 |
| E.4 52.209-5 CERTIFICATION REGARDING RESPONSIBILITY MATTERS (OCT 2015) | 81 |
| E.5 52.217-5 EVALUATION OF OPTIONS (JUL 1990) | 83 |
| E.6 VAAR 852.215-70 SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESS EVALUATION FACTORS (JUL 2016)(DEVIATION) | 83 |
| E.7 VAAR 852.252-70 SOLICITATION PROVISIONS OR CLAUSES INCORPORATED BY REFERENCE (JAN 2008) | 84 |
| E.8 52.212-3 OFFEROR REPRESENTATIONS AND CERTIFICATIONS—COMMERCIAL ITEMS (OCT 2018) | 84 |
SECTION B - CONTINUATION OF SF 1449 BLOCKS
B.1 CONTRACT ADMINISTRATION DATA
1. Contract Administration: All contract administration matters will be handled by the following individuals:
a. CONTRACTOR:
b. GOVERNMENT: Contracting Officer 36C259
Department of Veterans Affairs Network Contracting Office
NCO 19
1011 Honor Heights Drive Muskogee OK 74401-1318
2. CONTRACTOR REMITTANCE ADDRESS: All payments by the Government to the contractor will be made in accordance with:
| [X] |
| 52.232-33, Payment by Electronic Funds Transfer—System For Award Management, or |
| [] |
| 52.232-36, Payment by Third Party |
3. INVOICES: Invoices shall be submitted in arrears:
| a. Quarterly | [] |
| b. Semi-Annually | [] |
| c. Other | [X] within 30 days of completion of each inspection/testing |
4. GOVERNMENT INVOICE ADDRESS: All Invoices from the contractor shall be submitted electronically in accordance with VAAR Clause 852.232-72 Electronic Submission of Payment Requests.
Department of Veterans Affairs Financial Services Center PO Box 149971 Austin TX 78714-9971
ACKNOWLEDGMENT OF AMENDMENTS: The offeror acknowledges receipt of amendments to the Solicitation numbered and dated as follows:
| AMENDMENT NO |
| DATE |
Performance Work Statement (PWS) Boiler Safety Testing/Inspection Services Oklahoma City VA Medical Center 921 NE 13th. Street Oklahoma City, Ok 73104-5007
The contractor shall provide Boiler Safety Testing/Inspection/services and Feedwater Deaerator Tank inspection/services in accordance with the terms and conditions stated within this Statement of Work (SOW). All work shall be coordinated with the Oklahoma City VA Health Care System’s COR.
1. INSPECTION SERVICES:
a. General:
i. Contractor shall perform combustion analysis and tuning, safety device testing, and boiler inspections on three (3) fire tube boilers as specified within all updated manufacturer specifications and requirements and provide inspections of two (2) feedwater deaerator tanks. Technicians shall have adequate experience, training, and applicable licensing, to perform required preventative maintenance.
ii. Contractor shall provide all labor, materials, and equipment necessary for protection of VAMC personnel, furnishings, equipment and buildings from damage, and shall replace or repair any damage due to work performed under this contract equal to its original construction and finish. Contractor must have adequate insurance protection against negligent work and other forms of liability and follow all federal, state, local, and VA Regulations related to this requirement.
iii. Upon request, contractor shall provide proof of certification attesting that all gauging and measurement equipment used has been currently calibrated either according to the manufacturer’s specifications or a standard traceable to the National Bureau of Standards.
b. Introduction:
i. (VA) Oklahoma City medical center has a central high-pressure boiler plant to provide steam for heating and air conditioning, domestic hot water, sterilizing services, and laundry equipment.
ii. The VA has a requirement for:
1. Annual internal and external inspections on three (3) (listed below) high pressure (over 15 psig) steam boilers
2. A semi-annual requirement to perform burner and instrument inspecting, testing, calibrating burners and controls, and testing of all safety devices on the three (3) (listed below) high pressure (over 15 psig) steam boilers and two (2) (listed below) deaerator tanks
3. A semi-annual internal/external inspection of two (2) (listed below) feedwater deaerator tanks.
4. A 6 year inspection and magnetic particle testing of welds of pressure vessel interior of the feedwater deaerator tank (listed below). To be completed in base year of contract only.
iii. List of Equipment:
1. Boiler #1 manufactured by: Cleaver-Brooks, Model number 4WI-200-600-200 SN: T-1246-1-2
2. Boiler #2 manufactured by: Cleaver-Brooks, Model number 4WI-200-600-200 SN: T-1246-1-3
3. Boiler #3 manufactured by: Cleaver-Brooks, Model number 4WI-200-600-200 SN: T-1246-1-1
4. Feedwater Deaerator Tank: manufactured by: Wheeler Tank Mfg, Model number: 12309, SN: 07387
5. Condensate Tank: manufactured by: Wheeler Tank Mfg, Model number 12291, SN: 07384
iv. Qualifications of Testing Personnel:
1. Boiler Inspectors shall be a “Qualified Professional Inspector”. Proof of qualification shall be provided to the COR upon request. They shall be versed with and have access to the current versions of “reference materials” defined below. A “Qualified Professional Inspector” is defined as one who possess one or combination of below requirements:
a. A boiler inspector who has a valid commission from the National Board of Boiler and Pressure Vessel Inspectors (NB).
b. A boiler inspector who has qualified by passing a written examination under the laws, rules and regulations of a jurisdiction of a state.
c. A boiler inspector who is regularly employed as a boiler inspector by a jurisdiction which has adopted and administers one or more sections of the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code as a legal requirement, and has a representative serving as a member of the ASME Conference Committee.
d. A boiler inspector who is regularly employed by an insurance company which has been licensed or registered by the appropriate authority of a State of the United States to write boiler or pressure vessel insurance.
v. Combustion Analysis and Safety Device Testing personnel shall be qualified for boiler plant burner, control and instrumentation testing. Proof of qualification shall be provided to the COR upon request. Qualifications include completing at least a one-year trade school and five years successful experience in this field. The experience shall be largely with institutional and industrial boiler plants similar in design to the VAMC plants.
vi. “Reference Materials” are comprised of the latest versions of the below, plus any other materials/manufacture reference materials needed to complete all contract requirements:
1. ASME Boiler and Pressure Vessel Code
2. ASME B31.1, Power Piping Code
3. ASME CSD-1, Controls and Safety Devices for Automatically Fired Boilers
4. ANSI/NB-23, National Board Inspection Code
5. NFPA 85, Boiler and Combustion Systems Hazards Code
6. VHA Boiler Plant Safety Device Testing Manual, 5th Ed.
7. Utilize National Board Forms NB-6 and NB-7
8. NATIONAL BOARD INSPECTION CODE,
a. Part RB, In-service Inspection of Pressure-Retaining Items,
vii. The testing personnel shall be equipped with portable electronic flue gas analyzers and all other test instruments necessary for the required tests and calibrations, all currently calibrated either according to the manufacturer’s specifications or a standard traceable to the National Bureau of Standards.
c. Inspection and Testing Requirements:
i. At least two weeks’ notice to the Contracting Officer’s Representative (COR) is required prior to an inspection. Work cannot be scheduled during heavy steam load periods. Only one boiler at a time can be out of service for the inspection, testing and calibration procedures. Work must be conducted when the COR or his/her representative is available on site to monitor the work.
ii. The contractor is required to prepare the boilers for inspection by opening, cleaning watersides and firesides, and preparing the boiler for inspection following National Board, ASME, Veterans Administration and industry requirements/guidelines. The contractor will also be required to restore the boiler for service.
iii. Each burner and the burner control, monitoring and safety interlock systems shall be inspected and tested and adjusted as necessary.
iv. VA will have the boilers that are to be serviced prepared for the test personnel upon their scheduled arrival. This includes having the boilers clean of soot and loose scale; fully warmed and at normal steam pressure; steam exhaust silencer system operable; all boiler, burner and fuel train pressure gages and thermometers calibrated; fuel meters in accurate operation (pressure/temperature correction factors provided, if applicable); boiler steam flow, stack temperature and flue gas oxygen instruments operating.
v. VA will comply with any other requirements of the test personnel that are considered reasonable by VA and have been presented in writing at least two weeks prior to the scheduled testing.
vi. The COR or his/her representative will observe the work.
d. Combustion Analysis/Tuning and Safety Device Testing summary of requirements:
i. The inspections, testing, and adjustments shall comply with:
1. The recommendations and requirements of VHA Boiler Plant Safety Devices Testing Manual.
2. The written recommendations of the equipment manufacturers.
3. The requirements and recommendations of NFPA 85 Boiler and Combustion Systems Hazard Code including applicable appendices.
4. Burner performance requirements in this document.
ii. A summary of the work is as follows:
1. Review boiler plant log sheets and alarm and trouble reports.
2. Review records that show combustion performance (flue gas oxygen).
3. Perform overall visual inspection of systems. Verify that systems comply with referenced codes and VA requirements stated in this contract.
4. Test the operation and set points of all burner/boiler safety interlock devices. Refer to list below. Record the settings and compare with required settings. Make adjustments as necessary and record the new settings. The operation of a device must result in burner shutdown and/or proper alarm operation.
5. Operate burner(s) on each fuel from low fire to high fire and back to low fire in at least six increments and record combustion performance (flue gas oxygen, carbon monoxide, NOx where applicable), fuel train pressures, atomizing train pressures, burner pressures, stack temperatures, boiler steam output.
6. Compare the combustion performance data with VA requirements (see below) and previous readings. If necessary, make adjustments to the fuel flow and combustion air controllers, control valves and dampers to obtain the required performance. Record the new performance data. If further work, such as repairs or burner modifications, is needed to correct any problems, provide recommendations to the COR.
7. Verify accuracy of instrumentation listed below. Verify that all devices are properly selected for the application in terms of type, size, set point range, performance, and code approval. Calibrate all instruments that are not within manufacturer’s specifications for accuracy.
8. Immediately inform COR of any recommended repairs, modifications, or safety related problems.
iii. List of interlocks and safety devices to be inspected and tested on each boiler/burner:
1. High and low fuel pressure switches (gas/oil).
2. Low fuel oil atomizing media (steam/compressed air) pressure switches.
3. Low differential pressure switch, atomizing media/fuel oil (if provided by burner manufacturer).
4. Oil burner position switch (if provided by burner manufacturer).
5. Fuel safety shut off valves proof of closure (over-travel/valve seal switch).
6. Leak test fuel safety shut off valves (main and pilot burners) (leakage into burner).
7. Leak test gas fuel vent valves.
8. Forced draft motor interlock.
9. Forced draft damper wide-open interlock for purge.
10. Outlet damper open interlock for purge (if outlet damper provided).
11. Purge airflow interlock.
12. Purge timing.
13. Ignition timing.
14. Low fire position interlock, if present.
15. Combustion airflow interlock.
16. Main flame out – time to close fuel valves.
17. Ignition flame out – burner shutdown.
18. Scanner not sensing ignition spark (ultraviolet scanner).
19. Scanner not sensing hot refractory (infrared scanner).
iv. Required burner performance (natural gas and fuel oil):
1. Turndown (ratio of maximum and minimum firing rates): 10/1 8/1 5/1 4/1 (Refer to original burner specification).
2. Achieve, but do not exceed, boiler maximum steam flow output rating. Measure fuel input at minimum and maximum firing rates.
3. Maximum carbon monoxide: 200 parts per million (ppm)
4. Maximum NOx (Nitrous Oxide): _____ (Refer to original burner specification).
5. Flue gas oxygen: 2.5 – 4.2% (Up to 5.2% at loads below 40% of maximum steam output; no upper limit at minimum firing rate; oxygen can be one percentage point higher on oil firing).
6. Flue gas oxygen (low excess air burners): 1.0 – 2.0% (Up to 2.5% at loads below 40% of maximum steam output; no upper limit at minimum firing rate; oxygen can be one percentage point higher on oil firing).
7. No visible smoke, except on heavy oil fuel maximum opacity is 20%. Comply with local emissions regulations.
8. Flames shall be stable with no pulsations, shall be retained near burner, no blow-off or flashbacks, no constant flame impingement on refractory or water-walls.
e. Boiler Inspections summary of requirements:
i. Annual internal and external inspections are required for each boiler. Internal inspections of the feed water de-aerator pressure vessel are required every six years or more frequently if welding repairs have been performed.
ii. Contractor shall coordinate with COR to schedule an inspection. The Contractor shall ensure coordination and scheduling of any inspection is conducted at least two weeks prior to the intended date of an inspection. Inspections must be scheduled for periods when the VA determines that the boilers that will be inspected internally will not be needed for steam supply and when the COR or his/her designate is available on site to monitor the inspections. To maintain steam service, typically only one boiler at a time will be scheduled for internal inspections per inspection visit. Thus, multiple visits will be necessary every year to inspect all the boilers internally.
iii. Feed water de-aerator pressure vessel inspections must be scheduled during periods of low steam demand.
iv. Coordinate the inspection schedule with the COR so that VAMC can have personnel available to monitor the inspections.
v. Boilers scheduled for internal inspection will be prepared by the contractor prior to the scheduled arrival of the Qualified Professional Inspector. This includes cooling the boilers to near ambient temperature and having all man ways, hand holes and furnace access doors open; the boilers cleaned of loose materials waterside and fireside; electrical “lock-out, tag-out” in place; connecting piping isolated; proper illumination provided; compliance with “confined space” access requirements including having safety personnel present in the boiler plant. Similar advance preparations will be made to the feed water de-aerator when it is scheduled for internal inspection.
vi. VAMC will comply with any other requirements of the contractor that are considered reasonable by VAMC and have been presented in writing at least two weeks prior to the scheduled inspection.
vii. The boiler and feed water de-aerator inspections shall comply with the guidelines in the current issue of the NATIONAL BOARD INSPECTION CODE, Part RB, In-service Inspection of Pressure-Retaining Items, and ASME Boiler and Pressure Vessel Code, Section VI or VII as applicable. In addition to those guidelines, the inspections shall comply with all requirements listed in statement of work.
viii. The inspector must completely enter the internal spaces of the boiler or feed water de-aerator and visually inspect all internal surfaces that can be accessed. Methods for testing safety devices shall comply with VHA Boiler Plant Safety Device Testing Manual, 2nd Edition.
f. Summary of the minimum inspection requirements for boilers:
i. Review the boiler history including: operating conditions, date of last inspection, current inspection certificate, ASME stamping on boiler, National Board registration number, history of repairs and modifications. Review boiler logs, water test reports, and reports on tests performed on the burner controls and interlocks.
ii. Assess the external parts of the boilers and boiler accessories and piping and valves for safety, accessibility, proper maintenance and operation, cleanliness, and compliance with codes.
iii. Inspect for evidence of leakage of combustion gases or fluids, externally and internally, including all gaskets.
iv. Inspect foundations for signs of stress such as cracking or movement.
v. Inspect boilers externally and internally for defects including bulges, blisters, cracks, wasted or eroded material, warping, general corrosion, grooving and pitting, damaged insulation.
vi. Inspect all accessible internal surfaces for waterside and fireside deposits, including scaling, sediment, debris, carbon deposits.
vii. Examine all stays and stayed plates.
viii. Inspect gas side baffles.
ix. Inspect internal drum surfaces and steam separating internals.
x. Inspect tubes, tube ends and tube alignment. Check for sagging tubes.
xi. Set combustions for boilers number one, two, and three, on natural gas and number two oil.
xii. Test all safety devices and perform annually required accumulation tests on boilers one, two and three.
xiii. Verify that all nozzles of internal piping such as feed water admission and bottom blow off collection are clear with no obstructions.
xiv. Inspect seating surfaces of man ways and hand holes.
xv. Check that boiler structure is plumb and level with no excessive deformations.
xvi. Check for missing items such as bolts and nuts.
xvii. Examine all valve and pipe connections to the pressure vessel.
xviii. Inspect refractory including burner throat, expansion joint, bull ring, furnace seals, furnace walls and floor.
xix. Verify proper alignment of burner assembly.
xx. Inspect furnace for evidence of flame impingement.
xxi. Test operation of water level gage glass.
xxii. Perform mechanical and electrical inspection of disassembled low water cutouts (disassembly by VA). After reinstallation, test operation to the extent possible. Test low water cutouts on hot boilers by lowering water level gradually.
xxiii. Verify that steam pressure gage is properly calibrated.
xxiv. Test operation of high steam pressure cutouts on hot boilers by raising steam pressure.
xxv. Inspect safety valve installations and verify that the valves have proper capacity and set pressure and valves, drains and vents are properly installed. Verify that valve locking seals are not broken. On boilers that are hot, perform an operation test under pressure to confirm operation at proper set pressures. Operate boiler with burner at high fire to verify adequate steam flow capacity of the safety valves (“accumulation test”).
xxvi. Inspect piping connected to the boilers for evidence of leakage, provision for expansion, provision of adequate support, proper alignment, and evidence of detrimental conditions.
xxvii. Inspect piping to the water column, low water cutoffs and alarms, gage glass. Verify that interior of piping is clear of obstructions.
xxviii. Inspect valves on boiler feed water, blow down, drain and steam systems.
xxix. Perform service and Calibration of boiler instrumentation and controls.
xxx. Provide recommendations for non-destructive testing when the inspections indicate that this is necessary to assure continued safety and reliability under current operating conditions.
g. Summary of the minimum inspection requirements for Feed water Deaerators:
i. Review the feed water de-aerator history including: operating conditions, date of last inspection, current inspection certificate, ASME stamping, National Board registration number, materials of construction, extent of post weld heat treatment, history of repairs and modifications.
ii. Assess the external parts of the feed water de-aerator and accessories and piping for safety, accessibility, cleanliness, proper operation, and compliance with codes.
iii. Test hazardous gas monitoring system.
iv. Inspect for evidence of leakage.
v. Note feed water de-aerator pressure gage and thermometer readings and verify gage and thermometer accuracy.
vi. Inspect safety valve installation and verify that the valves have proper set pressure and capacity and are properly installed. Perform an operation test under pressure to confirm operation at proper set pressures. Verify that the de-aerator can safety withstand the test pressure prior to testing the valve(s) in-situ.
vii. Verify that non-condensable gas vent line is open and proper orifice is provided to permit venting of gases.
viii. Inspect support structures for proper integrity and allowance for thermal expansion.
ix. Internal Inspections
1. Visually inspect all visible pressure vessel surfaces for corrosion, material thinning, deposits, and weld cracking.
2. Inspect spray nozzles and trays.
2. SCHEDULING ARRANGEMENTS: Except by special alternative arrangement, scheduled work will be performed only during VAMC’s normal working hours (8:00 a.m. to 4:30 p.m. Monday through Friday excluding federal holidays). Contractor shall schedule all work within 1 week of contract award, approved by VA HCS COR. Vendor shall provide at least two weeks’ notice to the Contracting Officer’s Representative (COR) prior to performing the work. Work cannot be scheduled during heavy steam load periods. Only one boiler at a time can be out of service for the inspection, testing, and calibration procedures. Work must be conducted when the COR or his/her designate is available on site to monitor the work.
Check in/out procedures: Prior to commencement of and immediately after each service visit, the contractor and/or contractor’s authorized repair technician must check in and out with the VAMC Boiler Plant staff. Due to heightened security requirements, the contractor and/or contractor’s authorized service representative will be required to wear an ID Badge which will be signed for upon arrival and turned in when leaving.
3. FEDERAL HOLIDAYS: Federal holidays are any calendar days designated by statute or executive order as federal holidays. Federal holidays consist of New Year’s Day, Martin Luther King Jr.’s Birthday, Presidents Day, Memorial Day, Independence Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day, and Christmas.
4. DOCUMENTATION: Contractor shall provide this VA HCS with individual service reports, which describes the inspection services performed on the equipment.
a. Provide complete written report of the inspection fully describing all tests performed, all findings, and recommendations. The report shall have two sections the first section will be in a table form that with four columns:
i. The first column labeled “FUNCTION” did the device pass or fail.
ii. The second column labeled “Device” list the device number and description in accordance with the VHA Boiler Plant Safety Devices Testing Manual, 5th Edition.
iii. The third labeled “Deficiencies-Recommendations”
iv. The fourth column labeled “corrective actions” list any corrective actions taken during the inspection.
The next section shall be in paragraph/bulleted form and list each device individual in accordance to the VHA Boiler Plant Safety Devices Testing Manual, 5th Edition. Plus the section must reference the correct Master Specification and Standard Detail for that device. See sample below:
5.1. Condensate Storage Tank High Water Alarm
Purpose: High water level may be an indication of condensate transfer pump failure that could lead to low water condition in the feedwater deaerator and in the boilers. There may be a failure of make-up water controls.
Recommended set point: 4 inches below overflow level and 2/3 of tank height.
Potential hazards due to failure of high water alarm: Feedwater deaerator running dry and, consequently, boiler feed pumps running dry will cause overheating and damage to pumps and potential for plant shut down. Failure of make-up water controls (in open position) could lead to significant cost from waste of water and condensate from the tank overflow if this occurs over a long time period.
Recommended type of device: Conductivity probe type switch. Float typeswitches have high failure rate in this application where they are exposed to flash steam that causes seals to harden and prevent float movement.
VA Master Specification section: 23 50 11 (old 15625).
www.va.gov/facmgt/standard/ VA Standard Detail: SD232111-05.pdf www.va.gov/facmgt/standard/ Failure rate of float types: 48% (BEI study of VA boiler plants).
Make and Model: Mercoid Float Did it function properly: No Category & Action Time Limit: Upon Failure or Within 5 Years Comments: Float type switches are not allowed for high water alarms. The VA recommended switch type is a conductivity probe type switch. Install the VA recommended switch and set to alarm at 2/3 of the tank height. There are valves that can isolate this alarm. These valves must be made lockable only in the operating position.
b. Furnish report within one week of each facility inspection in “Microsoft Word” format by email to the COTR and to the VA Headquarters office designated. Provide hard copies of data sheets and flue gas analyzer “strip” printouts to the COTR within one week of visit.
c. All safety-related deficiencies shall be immediately reported to the COTR, Boiler Plant Supervisor and/or Chief Engineer during the inspection visit.
5. PROTECTION FROM DAMAGE: Contractor shall provide all labor, materials, and equipment necessary for protection of VA HCS personnel, furnishings, equipment and buildings from damage, and shall replace or repair any damage due to work performed under this contract equal to its original construction and finish.
6. RESPONSE REQUESTS: Contractor shall only respond to requests for service from VA HCS CO or COR. If service is requested from any other source the Contractor is to advise the caller of this requirement and refuse to respond. Any billing resulting from unauthorized service will not be paid by the government.
7. CHECK IN/OUT PROCEDURES: Prior to commencement of, and immediately after each service visit, the Contractor or his authorized repair technician must check in and out with the VA HCS COR (during normal working hours). Contractor will be required to obtain contractor badges provided by the VA HCS.
8. LIABILITY INSURANCE: Contractor must provide this VA HCS with written confirmation that Contractor has adequate insurance protection against negligent work and other forms of liability. The nature and level of protection must be acceptable to this VA HCS.
9. INFORMATION SECURITY: The C&A requirements do not apply, and a Security Accreditation Package is not required.
B.2 PRICE/COST SCHEDULE
ITEM INFORMATION
| ITEM NUMBER |
| DESCRIPTION OF SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 2.00 |
| JB |
| __________________ |
| __________________ |
Semi-Annual Safety device testing and combustion analysis/tuning (to include all labor and materials required to prepare unit for inspection) of Clever Brooks Boiler, Model: 4WI-200-600-200, SN: T-1246-1-1 (Base year only one semi-annual inspection due to late contract start date) Contract Period: Base POP Begin: 10-01-2019 POP End: 09-30-2020
| 2.00 |
| JB |
| __________________ |
| __________________ |
Semi-Annual Safety device testing and combustion analysis/tuning (to include all labor and materials required to prepare unit for inspection) of Clever Brooks Boiler, Model: 4WI-200-600-200, SN: T-1246-1-2 (Base year only one semi-annual inspection due to late contract start date)
| 2.00 |
| JB |
| __________________ |
| __________________ |
Semi-Annual Safety device testing and combustion analysis/tuning (to include all labor and materials required to prepare unit for inspection) of Clever Brooks Boiler, Model: 4WI-200-600-200, SN: T-1246-1-3 (Base year only one semi-annual inspection due to late contract start date)
| 1.00 |
| JB |
| __________________ |
| __________________ |
Annual inspection (internal and external, to include all labor and materials required to prepare unit for inspection) of Clever Brooks Boiler, Model: 4WI-200-600-200, SN: T-1246-1-1
| 1.00 |
| JB |
| __________________ |
| __________________ |
Annual inspection (internal and external, to include all labor and materials required to prepare unit for inspection) of Clever Brooks Boiler, Model: 4WI-200-600-200, SN: T-1246-1-2
| 1.00 |
| JB |
| __________________ |
| __________________ |
Annual inspection (internal and external, to include all labor and materials required to prepare unit for inspection) of Clever Brooks Boiler, Model: 4WI-200-600-200, SN: T-1246-1-3
| 4.00 |
| JB |
| __________________ |
| __________________ |
Semi-Annual inspection (internal and external, to include all labor and materials required to prepare unit for inspection) of Feedwater Deaerator Tanks
| 1.00 |
| JB |
| __________________ |
| __________________ |
6 Year Deaerator Tank Inspection
| 2.00 |
| JB |
| __________________ |
| __________________ |
Semi-Annual Safety device testing and combustion analysis/tuning (to include all labor and materials required to prepare unit for inspection) of Clever Brooks Boiler, Model: 4WI-200-600-200, SN: T-1246-1-1 Contract Period: Option 1 POP Begin: 10-01-2020 POP End: 09-30-2021
| 2.00 |
| JB |
| __________________ |
| __________________ |
Semi-Annual Safety device testing and combustion analysis/tuning (to include all labor and materials required to prepare unit for inspection) of Clever Brooks Boiler, Model: 4WI-200-600-200, SN: T-1246-1-2
| 2.00 |
| JB |
| __________________ |
| __________________ |
Semi-Annual Safety device testing and combustion analysis/tuning (to include all labor and materials required to prepare unit for inspection) of Clever Brooks Boiler, Model: 4WI-200-600-200, SN: T-1246-1-3
| 1.00 |
| JB |
| __________________ |
| __________________ |
Annual inspection (internal and external, to include all labor and materials required to prepare unit for inspection) of Clever Brooks Boiler, Model: 4WI-200-600-200, SN: T-1246-1-1
| 1.00 |
| JB |
| __________________ |
| __________________ |
Annual inspection (internal and external, to include all labor and materials required to prepare unit for inspection) of Clever Brooks Boiler, Model: 4WI-200-600-200, SN: T-1246-1-2
| 1.00 |
| JB |
| __________________ |
| __________________ |
Annual inspection (internal and external, to include all labor and materials required to prepare unit for inspection) of Clever Brooks Boiler, Model: 4WI-200-600-200, SN: T-1246-1-3
| 4.00 |
| JB |
| __________________ |
| __________________ |
Annual inspection (internal and external, to include all labor and materials required to prepare unit for inspection) of Feedwater Deaerator Tanks
| 2.00 |
| JB |
| __________________ |
| __________________ |
Semi-Annual Safety device testing and combustion analysis/tuning (to include all labor and materials required to prepare unit for inspection) of Clever Brooks Boiler, Model: 4WI-200-600-200, SN: T-1246-1-1 Contract Period: Option 2 POP Begin: 10-01-2021 POP End: 09-30-2022
| 2.00 |
| JB |
| __________________ |
| __________________ |
Semi-Annual Safety device testing and combustion analysis/tuning (to include all labor and materials required to prepare unit for inspection) of Clever Brooks Boiler, Model: 4WI-200-600-200, SN: T-1246-1-2
| 2.00 |
| JB |
| __________________ |
| __________________ |
Semi-Annual Safety device testing and combustion analysis/tuning (to include all labor and materials required to prepare unit for inspection) of Clever Brooks Boiler, Model: 4WI-200-600-200, SN: T-1246-1-3
| 1.00 |
| JB |
| __________________ |
| __________________ |
Annual inspection (internal and external, to include all labor and materials required to prepare unit for inspection) of Clever Brooks Boiler, Model: 4WI-200-600-200, SN: T-1246-1-1
| 1.00 |
| JB |
| __________________ |
| __________________ |
Annual inspection (internal and external, to include all labor and materials required to prepare unit for inspection) of Clever Brooks Boiler, Model: 4WI-200-600-200, SN: T-1246-1-2
| 1.00 |
| JB |
| __________________ |
| __________________ |
Annual inspection (internal and external, to include all labor and materials required to prepare unit for inspection) of Clever Brooks Boiler, Model: 4WI-200-600-200, SN: T-1246-1-3
| 4.00 |
| JB |
| __________________ |
| __________________ |
Annual inspection (internal and external, to include all labor and materials required to prepare unit for inspection) of Feedwater Deaerator Tanks
| 2.00 |
| JB |
| __________________ |
| __________________ |
Semi-Annual Safety device testing and combustion analysis/tuning (to include all labor and materials required to prepare unit for inspection) of Clever Brooks Boiler, Model: 4WI-200-600-200, SN: T-1246-1-1 Contract Period: Option 3 POP Begin: 10-01-2022 POP End: 09-30-2023
| 2.00 |
| JB |
| __________________ |
| __________________ |
Semi-Annual Safety device testing and combustion analysis/tuning (to include all labor and materials required to prepare unit for inspection) of Clever Brooks Boiler, Model: 4WI-200-600-200, SN: T-1246-1-2
| 2.00 |
| JB |
| __________________ |
| __________________ |
Semi-Annual Safety device testing and combustion analysis/tuning (to include all labor and materials required to prepare unit for inspection) of Clever Brooks Boiler, Model: 4WI-200-600-200, SN: T-1246-1-3
| 1.00 |
| JB |
| __________________ |
| __________________ |
Annual inspection (internal and external, to include all labor and materials required to prepare unit for inspection) of Clever Brooks Boiler, Model: 4WI-200-600-200, SN: T-1246-1-1
| 1.00 |
| JB |
| __________________ |
| __________________ |
Annual inspection (internal and external, to include all labor and materials required to prepare unit for inspection) of Clever Brooks Boiler, Model: 4WI-200-600-200, SN: T-1246-1-2
| 1.00 |
| JB |
| __________________ |
| __________________ |
Annual inspection (internal and external, to include all labor and materials required to prepare unit for inspection) of Clever Brooks Boiler, Model: 4WI-200-600-200, SN: T-1246-1-3
| 4.00 |
| JB |
| __________________ |
| __________________ |
Annual inspection (internal and external, to include all labor and materials required to prepare unit for inspection) of Feedwater Deaerator Tanks
| 2.00 |
| JB |
| __________________ |
| __________________ |
Semi-Annual Safety device testing and combustion analysis/tuning (to include all labor and materials required to prepare unit for inspection) of Clever Brooks Boiler, Model: 4WI-200-600-200, SN: T-1246-1-1 Contract Period: Option 4 POP Begin: 10-01-2023 POP End: 09-30-2024
| 2.00 |
| JB |
| __________________ |
| __________________ |
Semi-Annual Safety device testing and combustion analysis/tuning (to include all labor and materials required to prepare unit for inspection) of Clever Brooks Boiler, Model: 4WI-200-600-200, SN: T-1246-1-2
| 2.00 |
| JB |
| __________________ |
| __________________ |
Semi-Annual Safety device testing and combustion analysis/tuning (to include all labor and materials required to prepare unit for inspection) of Clever Brooks Boiler, Model: 4WI-200-600-200, SN: T-1246-1-3
| 1.00 |
| JB |
| __________________ |
| __________________ |
Annual inspection (internal and external, to include all labor and materials required to prepare unit for inspection) of Clever Brooks Boiler, Model: 4WI-200-600-200, SN: T-1246-1-1
| 1.00 |
| JB |
| __________________ |
| __________________ |
Annual inspection (internal and external, to include all labor and materials required to prepare unit for inspection) of Clever Brooks Boiler, Model: 4WI-200-600-200, SN: T-1246-1-2
| 1.00 |
| JB |
| __________________ |
| __________________ |
Annual inspection (internal and external, to include all labor and materials required to prepare unit for inspection) of Clever Brooks Boiler, Model: 4WI-200-600-200, SN: T-1246-1-3
| 4.00 |
| JB |
| __________________ |
| __________________ |
Annual inspection (internal and external, to include all labor and materials required to prepare unit for inspection) of Feedwater Deaerator Tanks
| GRAND TOTAL |
| __________________ |
36C25919Q0587
Page 1 of Page 1 of
SECTION C - CONTRACT CLAUSES
C.1 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL ITEMS (OCT 2018)
(a) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The Government must exercise its post-acceptance rights—
(1) Within a reasonable time after the defect was discovered or should have been discovered; and
(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.
(b) Assignment. The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims Act (31 U.S.C. 3727). However, when a third party makes payment (e.g., use of the Governmentwide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.
(c) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.
(d) Disputes. This contract is subject to 41 U.S.C. chapter 71, Contract Disputes. Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause at FAR 52.233-1, Disputes, which is incorporated herein by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.
(e) Definitions. The clause at FAR 52.202-1, Definitions, is incorporated herein by reference.
(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting Officer of the cessation of such occurrence.
(g) Invoice.
(1) The Contractor shall submit an original invoice and three copies (or electronic invoice, if authorized) to the address designated in the contract to receive invoices. An invoice must include—
(i) Name and address of the Contractor;
(ii) Invoice date and number;
(iii) Contract number, line item number and, if applicable, the order number;
(iv) Description, quantity, unit of measure, unit price and extended price of the items delivered;
(v) Shipping number and date of shipment, including the bill of lading number and weight of shipment if shipped on Government bill of lading;
(vi) Terms of any discount for prompt payment offered;
(vii) Name and address of official to whom payment is to be sent;
(viii) Name, title, and phone number of person to notify in event of defective invoice; and
(ix) Taxpayer Identification Number (TIN). The Contractor shall include its TIN on the invoice only if required elsewhere in this contract.
(x) Electronic funds transfer (EFT) banking information.
(A) The Contractor shall include EFT banking information on the invoice only if required elsewhere in this contract.
(B) If EFT banking information is not required to be on the invoice, in order for the invoice to be a proper invoice, the Contractor shall have submitted correct EFT banking information in accordance with the applicable solicitation provision, contract clause (e.g., 52.232-33, Payment by Electronic Funds Transfer—System for Award Management, or 52.232-34, Payment by Electronic Funds Transfer—Other Than System for Award Management), or applicable agency procedures.
(C) EFT banking information is not required if the Government waived the requirement to pay by EFT.
(2) Invoices will be handled in accordance with the Prompt Payment Act (31 U.S.C. 3903) and Office of Management and Budget (OMB) prompt payment regulations at 5 CFR part 1315.
(h) Patent indemnity. The Contractor shall indemnify the Government and its officers, employees and agents against liability, including costs, for actual or alleged direct or contributory infringement of, or inducement to infringe, any United States or foreign patent, trademark or copyright, arising out of the performance of this contract, provided the Contractor is reasonably notified of such claims and proceedings.
(i) Payment.—
(1) Items accepted. Payment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in this contract.
(2) Prompt payment. The Government will make payment in accordance with the Prompt Payment Act (31 U.S.C. 3903) and prompt payment regulations at 5 CFR part 1315.
(3) Electronic Funds Transfer (EFT). If the Government makes payment by EFT, see 52.212-5(b) for the appropriate EFT clause.
(4) Discount. In connection with any discount offered for early payment, time shall be computed from the date of the invoice. For the purpose of computing the discount earned, payment shall be considered to have been made on the date which appears on the payment check or the specified payment date if an electronic funds transfer payment is made.
(5) Overpayments. If the Contractor becomes aware of a duplicate contract financing or invoice payment or that the Government has otherwise overpaid on a contract financing or invoice payment, the Contractor shall—
(i) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment including the—
(A) Circumstances of the overpayment (e.g., duplicate payment, erroneous payment, liquidation errors, date(s) of overpayment);
(B) Affected contract number and delivery order number, if applicable;
(C) Affected line item or subline item, if applicable; and
(D) Contractor point of contact.
(ii) Provide a copy of the remittance and supporting documentation to the Contracting Officer.
(6) Interest.
(i) All amounts that become payable by the Contractor to the Government under this contract shall bear simple interest from the date due until paid unless paid within 30 days of becoming due. The interest rate shall be the interest rate established by the Secretary of the Treasury as provided in 41 U.S.C. 7109, which is applicable to the period in which the amount becomes due, as provided in (i)(6)(v) of this clause, and then at the rate applicable for each six-month period as fixed by the Secretary until the amount is paid.
(ii) The Government may issue a demand for payment to the Contractor upon finding a debt is due under the contract.
(iii) Final decisions. The Contracting Officer will issue a final decision as required by 33.211 if—
(A) The Contracting Officer and the Contractor are unable to reach agreement on the existence or amount of a debt within 30 days;
(B) The Contractor fails to liquidate a debt previously demanded by the Contracting Officer within the timeline specified in the demand for payment unless the amounts were not repaid because the Contractor has requested an installment payment agreement; or
(C) The Contractor requests a deferment of collection on a debt previously demanded by the Contracting Officer (see 32.607-2).
(iv) If a demand for payment was previously issued for the debt, the demand for payment included in the final decision shall identify the same due date as the original demand for payment.
(v) Amounts shall be due at the earliest of the following dates:
(A) The date fixed under this contract.
(B) The date of the first written demand for payment, including any demand for payment resulting from a default termination.
(vi) The interest charge shall be computed for the actual number of calendar days involved beginning on the due date and ending on—
(A) The date on which the designated office receives payment from the Contractor;
(B) The date of issuance of a Government check to the Contractor from which an amount otherwise payable has been withheld as a credit against the contract debt; or
(C) The date on which an amount…
This is the start of the file's text. The full file is on GovTribe.