About this file

36C25819Q0465 0003 S02_ATTACHMENT 04_RFI Log_36C25819C0465.pdf

View the file

Other files

File Type Posted
36C25819Q0465-0003000.docx DOCX document
36C25819Q0465-0003002.pdf PDF
36C25819Q0465-0003000.docx DOCX document
36C25819Q0465-0003001.pdf PDF
36C25819Q0465-0003002.pdf PDF
36C25819Q0465-0002000.docx DOCX document
36C25819Q0465-0002000.docx DOCX document
36C25819Q0465-0002002.pdf PDF
36C25819Q0465-0002001.pdf PDF
36C25819Q0465-0002001.pdf PDF
36C25819Q0465-0002002.pdf PDF
36C25819Q0465-0001000.docx DOCX document
36C25819Q0465-0001000.docx DOCX document
36C25819Q0465-004.pdf PDF
36C25819Q0465-003.pdf PDF
36C25819Q0465-002.pdf PDF
36C25819Q0465-001.docx DOCX document
36C25819Q0465-004.pdf PDF
36C25819Q0465-002.pdf PDF
36C25819Q0465-001.docx DOCX document
36C25819Q0465-003.pdf PDF
36C25819Q0465-000.docx DOCX document
36C25819Q0465-000.docx DOCX document
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT 04

Request for Information (RFI) Log

Part 1 of 1

2 pages

19 September 2019

San Diego, California VA Health Care System (664)

664‐19‐426

B171B SPS Sterilization Room Remediation

CONSTRUCTION

RequestforInformation(RFI)Log
B171BSPSSterilizationRoomRemediation

Construction 18 September 2019

San Diego, California VA Health Care System (664)

RFI

Number

Date Question Answer

001. 16 Sep 2019

Per detailed SOW issued with this solicitation, all walls and ceiling shall be demolished and rebuilt to match existing epoxy paint finishes as the main focus of this remediation project, please confirm.

Yes. Intent is to match existing epoxy paint finish.

002. 16 Sep 2019

It wasn’t made clear during the job walk if the interstitial space directly above the affected project is asbestos free. If so, please state formally

The interstitial space above the project space is asbestos free.

003. 16 Sep 2019

The 20 – calendar day duration may not be enough to carry out all the project requirements. Please check if this can be extended to 30‐45 days.

The period of performance will remain 20 days.