36C25818B0336-006.pdf
PDF 7 MB Posted
- Attached to
- LB - Pharmacy Bdg. 126 Rm. 904 Clean Room Site Prep CONST - PERFORMANCE LOCATION IS LONG BEACH CA 90822
- Solicitation number
- 36C25818B0336
About this file
36C25818B0336 S02 - Specs - 600-18-200.B126.Specifications.062818_v4.pdf
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25818C0153-000.docx | DOCX document | |
| 36C25818C0153-001.pdf | ||
| 36C25818B0336-0003003.pdf | ||
| 36C25818B0336-0003002.pdf | ||
| 36C25818B0336-0003000.docx | DOCX document | |
| 36C25818B0336-0003001.pdf | ||
| 36C25818B0336-0002000.docx | DOCX document | |
| 36C25818B0336-0001001.pdf | ||
| 36C25818B0336-0001000.docx | DOCX document | |
| 36C25818B0336-002.pdf | ||
| 36C25818B0336-007.pdf | ||
| 36C25818B0336-004.pdf | ||
| 36C25818B0336-005.pdf | ||
| 36C25818B0336-003.pdf | ||
| 36C25818B0336-008.docx | DOCX document | |
| 36C25818B0336-001.docx | DOCX document | |
| 36C25818B0336-010.docx | DOCX document | |
| 36C25818B0336-009.docx | DOCX document | |
| 36C25818B0336-000.docx | DOCX document |
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LBVAHCS Long Beach, CA #600-18-200 Clean Room Site Prep AE Design - 100%CD June 28, 2018
TABLE OF CONTENTS
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
Section 00 01 10
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 10-17
01 33 23 Shop Drawings, Product Data, and Samples 05-17
01 35 26 Safety Requirements 02-17
01 42 19 Reference Standards 05-16
01 45 00 Quality Control 01-18
01 45 29 Testing Laboratory Services 08-17
01 57 19 Temporary Environmental Controls 01-11
01 58 16 Temporary Interior Signage 07-15
01 74 19 Construction Waste Management 09-13
01 91 00 General Commissioning Requirements 10-15
DIVISION 02 – EXISTING CONDITIONS
02 21 13 Site Surveys 08-16
02 41 00 Demolition 08-17
DIVISION 03 – CONCRETE
03 30 53 (Short-Form) Cast-in-Place Concrete 02-16
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 01 50.19 Preparation for Re-Roofing 02-16
07 84 00 Firestopping 02-16
07 92 00 Joint Sealants 10-17
DIVISION 09 – FINISHES
09 05 16 Subsurface Preparation for Floor Finishes 02-15
09 22 16 Non-Structural Metal Framing 06-18
09 29 00 Gypsum Board 06-18
09 91 00 Painting 01-16
DIVISION 10 – SPECIALTIES
10 14 00 Signage 10-15
10 26 00 Wall and Door Protection 10-15
DIVISION 11 – EQUIPMENT
00 01 10-2
11 05 12 General Motor Requirements for Equipment 11-11
11 53 23 Laboratory Refrigerators 11-11
11 53 53 Biological Safety Cabinets Laminar Airflow Stations 01-11
DIVISION 12 – FURNISHINGS
12 31 00 Manufactured Metal Casework 05-15
12 36 00 Countertops 12-15
DIVISION 13 - SPECIAL CONSTRUCTION
13 05 41 Seismic Restraint Requirements for Non-Structural Components 01-14
DIVISION 21- FIRE SUPPRESSION
21 08 00 Commissioning of Fire Suppression System 11-16
21 13 13 Wet-Pipe Sprinkler Systems 06-15
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 07-16
22 07 11 Plumbing Insulation 09-15
22 08 00 Commissioning of Plumbing Systems 11-16
22 40 00 Plumbing Fixtures 09-15
22 67 19.16 Reverse-Osmosis Water Equipment 09-15
DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING
(HVAC)
23 05 11 Common Work Results for HVAC 08-17
23 05 12 General Motor Requirements for HVAC and Steam Generation Equipment 08-17
23 05 41 Noise and Vibration Control for HVAC Piping and Equipment 02-15
23 05 93 Testing, Adjusting, and Balancing for HVAC 02-15
23 07 11 HVAC and Boiler Plant Insulation 02-15
23 08 00 Commissioning of HVAC Systems 11-16
23 09 23 Direct-Digital Control System for HVAC 09-11
23 21 13 Hydronic Piping 08-17
23 31 00 HVAC Ducts and Casings 03-13
23 34 00 HVAC Fans 02-15
23 36 00 Air Terminal Units 02-15
23 37 00 Air Outlets and Inlets 02-15
23 40 00 HVAC Air Cleaning Devices 02-12
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 01-16
26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17
26 05 26 Grounding and Bonding for Electrical Systems 01-17
26 05 33 Raceway and Boxes for Electrical Systems 01-18
26 08 00 Commissioning of Electrical Systems 11-16
26 24 16 Panelboards 01-18
26 27 26 Wiring Devices 01-18
00 01 10-3
26 29 11 Motor Controllers 01-18
26 29 21 Enclosed Switches and Circuit Breakers 01-17
DIVISION 27 – COMMUNICATIONS
27 05 11 Requirements for Communications Installations 06-15
27 05 26 Grounding and Bonding for Communications Systems 06-15
27 05 33 Raceways and Boxes for Communications Systems 06-15
27 08 00 Commissioning of Communications Systems 11-16
27 10 00 Control, Communication and Signal Wiring 06-15
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 05 00 Common Work Results for Electronic Safety and Security 04-18
28 05 13 Conductors and Cables for Electronic Safety and Security 09-11
28 05 26 Grounding and Bonding for Electronic Safety and Security 09-11
28 05 28.33 Conduits and Backboxes for Electronic Safety and Security 09-11
28 08 00 Commissioning of Electronic Safety and Security Systems 11-16
28 13 00 Physical Access Control System 10-11
LBVAHCS Long Beach, CA #600-CSI-109 Clean Room Site Prep AE Design - 100%CD June 12, 2018
GENERAL REQUIREMENTS
01 00 00 - 1
SECTION 01 00 00
GENERAL REQUIREMENTS
TABLE OF CONTENTS
1.1 SAFETY REQUIREMENTS
1.2GENERAL INTENTION
1.3 STATEMENT OF BID ITEM(S)
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
1.5 CONSTRUCTION SECURITY REQUIREMENTS
1.6 OPERATIONS AND STORAGE AREAS
1.7 ALTERATIONS
1.8 DISPOSAL AND RETENTION
1.10 PHYSICAL DATA
1.11 PROFESSIONAL SURVEYING SERVICES
1.12 LAYOUT OF WORK
1.13 AS-BUILT DRAWINGS
1.14 USE OF ROADWAYS
1.15 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
1.16 TEMPORARY USE OF EXISTING ELEVATORS
1.17 TEMPORARY TOILETS
1.18 AVAILABILITY AND USE OF UTILITY SERVICES
1.19 TESTS
1.20 INSTRUCTIONS
1.21 CONSTRUCTION SIGN
1.22 SAFETY SIGN
1.23 HISTORIC PRESERVATION
01 00 00 - 2
SECTION 01 00 00
GENERAL REQUIREMENTS
1.1 SAFETY REQUIREMENTS
Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing systems and structures, and furnish labor and materials and perform work for 600-18-
200 Clean Room Site Prep AE Design. Project includes modifications to existing HVAC, plumbing, electrical, IT, fire suppression systems and architectural renovation of the space with built-in counters and cabinetry as required by the drawings and specifications. The Overall
Project will be performed within room E904 located on the ninth floor of the Long Beach VA
Medical Center: Building 126; the plenum spaces directly above and adjacent to the room; and the roof above the eleventh floor for a new exhaust fan at the same location of the existing fan.
This site preparation project precedes installation of a prefabricated, modular clean room system to be installed in the space under a separate contract. All modifications to the space have been designed to integrate with this prefabricated system.
All construction is to be performed in one phase during normal working hours. Off-hours premium time is included for noise abatement and utility shutdowns only. Any item(s) to be salvaged by the owner are to be removed by the owner from the site before construction begins. contractor to provide dumpsters for disposal of construction debris and materials. The construction contractor will be required to submit construction waste debris reports to include weight of construction waste, weight of any recycled materials and the cost for removing construction waste. The construction contractor shall comply with VA Medical Center guidance to ensure infection controls during the construction. Infection control procedures are shown on the general sheets and appended to this specification.
Contractor to perform Testing, Adjustment and Balancing for new HVAC systems and existing
HVAC systems impacted by the project per Section 23 07 11 after site preparations are complete and re-balanced and tested after the prefabricated clean room system is installed under a separate contract.
Contractor to perform Commissioning of all new systems and existing systems impacted by the project according to requirements in sections: 01 91 00 – GENERAL COMMISSIONING
01 00 00 - 3
REQUIREMENTS; 21 08 00 – COMMISSIONING OF FIRE SUPPRESSION SYSTEMS; 22 08 00
– COMMISSIONING OF PLUMBING SYSTEMS; COMMISSIONING OF HVAC SYSTEMS; 26 08
00 – COMMISSIONING OF ELECTRICAL SYSTEMS; 27 08 00 – COMMISSIONING OF
COMMUNICATIONS SYSTEMS; and 28 08 00 COMMISSIONING OF ELECTRONIC SAFETY
AND SECURITY SYSTEMS. All systems are to be re-commissioned after the prefabricated clean room is installed.
B. A one time visit to the site by Bidders may be made only at the time arranged by the Contracting
Officer..
C. Offices of Offices of Triple C – The A&E Group at 4401 Atlantic Avenue, Suite 200, Long Beach, CA 90807, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting
Officer or his duly authorized representative.
D. All testing shall be by certified testing laboratories subcontracted by the Contractor. The
Government shall not be required to contract testing for any trade.
E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
F. Comprehensive 3rd party inspections, testing and written reports for all Divisions (paid by the
General Contractor). Contractor shall employ third party inspection consultants to perform all inspections required by this contract. The VA has no inspection capability. Any reference to VA inspections shall be by a third-party inspector qualified to perform the work. Credentials shall be supplied to the VA/AE as required by this contract. All inspections, testing, certifications, and permits are to be paid for by the General Contractor. An air quality permit is required for the generator. The VA will not pay for or perform any required inspections. VA inspections are for
VA use only, when performed, and do not reduce the inspection burden on the Contractor. Third party inspection services must be submitted for acceptance by the VA after award. Submission to include resumes of inspectors, with alternates, projected days on site, qualifications of inspectors showing similar projects, related portfolio, and description of communication protocol with Owner.
Acceptable 3rd Party inspectors include the following:
Parsons Brinckerhoff http://www.wsp-pb.com/en/WSP-USA/What-we-do-USA/Services/All- Services-A-Z/Bridge-Engineering/Construction-
Inspection/
01 00 00 - 4
Booz Allen http://www.boozallen.com
US Army Corps of Engineers http://www.usace.army.mil/ Bureau
Veritas http://www.bureauveritas.com/
Stantec http://www.stantec.com/our-work/services/construction-qa-qc-monitoring-inspection- services.html
HDR, Inc.
http://www.hdrinc.com/
Gilbane http://www.gilbaneco.com
Minimum inspections required:
Mechanical, Electrical, Plumbing, Fire
Protection, Structural Steel, Welding, low voltage systems, controls system integration, commissioning support, Framing
G. Contractor to provide, Autodesk A360® Project Site dedicated for this project, or approved equal (substitutions must be submitted with Contractor Bid), for the duration of the contract.
Contractor will provide VA access to the site. Contractor will keep this site current and will use it for all submittals, RFIs, change documents, Record Drawing, electronic file management, and communication logs for the duration of the contract.
H. Contractor to provide Infection Control Plan as required by Memorandum 111-40, Subj:
VHA Directive 7715 Safety and Health During Construction dated April 6, 2017. Submit to
COR for approval prior to the start of work.
I. Contractor to Infection Control follow requirements listed in the “VA Long Beach Healthcare
System – Preconstruction Risk Assessment for Construction and Renovation” submitted 12-
27-17 (also appended to 01 00 00). Coordinate with COR.
J. Prior to commencing work, general contractor shall provide proof that a OSHA designated
“competent person” (CP) (29 CFR 1926.20(b)(2) will maintain a presence at the work site whenever the general or subcontractors are present. CP will have authority letter.
K. Pricing Proposal transparency requirements: this project requires pricing proposals to include breakdown pricing for the General Contractor and all subcontractors. All price proposals, 01 00 00 - 5 including subcontractor pricing must include a breakdown of pricing per the format included with tis specification. Third-party inspections must be included as a line item in the price proposal.
See example at the end of GENERAL REQUIREMENTS section.
1.3 STATEMENT OF BID ITEM(S)
ITEM I, Clean Room Site Prep AE Design: Work includes general construction, alterations, and necessary removal of existing systems and structures and construction or and certain other items. Project includes modifications to existing HVAC, plumbing, electrical, IT, fire suppression systems and architectural renovation of the space. The Overall Project will be performed within the following existing rooms/ located on the first floor of the Long Beach VA Medical Center:
Building 126.
ITEM II, Electrical Work: Includes all labor, material, equipment and supervision to perform the required electrical construction work on this project including providing a new panel to supply the prefabricated clean room unit, new HVAC terminal unit and valves and power for the new roof top exhaust fan.
ITEM III, Mechanical Work: Work includes all labor, material, equipment and supervision to perform the required Mechanical construction work on this project including provide material and construction equipment to reconfigure the existing supply and exhaust ductwork. This includes providing a new terminal unit, valves, duct work, and roof top exhaust fan and all associated components. Testing and Balancing the HVAC is also required for the new space configuration to ensure the USP 800 pressure differential and air change rate mandates are achieved. For plumbing, provide materials, equipment and certification to reconfigure existing piping and install a new lavatory/eyewash station and to remove other existing plumbing fixtures, cap and seal existing drains and connections. For fire suppression, contractor to reconfigure and certify the existing automatic sprinkler system the clean room to coordinate with the prefabricated clean room system.
All site preparation work on this project must be coordinated with the clean room manufacturer and must interface with the prefabricated unit and be commissioned as a complete system to ensure all VA and clean room manufacturer requirements are met.
01 00 00 - 6
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s notice to the
Contracting Officer so that security arrangements can be provided for the employees.
This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting
Officer.
4. VA reserves the right to close down or shut down the project site and order General
Contractor’s employees off the premises in the event of a national emergency. The
General Contractor may return to the site only with the written approval of the Contracting
Officer.
C. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the
Contracting officers representative (COR) for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.
2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See Section 08 71 00, DOOR HARDWARE and coordinate.
D. Document Control:
1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.
01 00 00 - 7
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law
Enforcement Sensitive” or “Sensitive Unclassified”. Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document Management Software (EDMS).
a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.
b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
E. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
2. A limited number of (2 to 5) permits shall be issued for General Contractor and its employees for parking in designated areas only.
1.6 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the
Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the
Contractor at its expense upon completion of the work. With the written consent of the
Contracting Officer, the buildings and utilities may be abandoned and need not be removed.
01 00 00 - 8
C. The Contractor shall, under regulations prescribed by the Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
(FAR 52.236-10)
D. Working space and space available for storing materials shall be as determined by the COR
E. Workmen are subject to rules of Medical Center applicable to their conduct. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.
F. Execute work so as to interfere as little as possible with normal functioning of Medical as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
G. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR. All such actions shall be coordinated with the COR or Utility Company involved:
1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Contractor.
H. Phasing:
01 00 00 - 9
The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:
To insure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof.
Arrange such dates to insure accomplishment of this work in successive phases mutually agreeable to Medical Center Director, COR and Contractor.
Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered.
Contractor shall permit access to Department of Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment.
These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc. to facilitate patient and staff access.
Coordinate alteration work in areas occupied by Department of Veterans Affairs so that Medical
Center operations will continue during the construction period.
I. Immediate areas of alterations will be temporarily vacated while alterations are performed.
J. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans
Affairs or municipal) whichever will be required to respond to an alarm from Contractor's employee or watchman.
K. Utilities Services: Maintain existing utility services for Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems
01 00 00 - 10
(including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR.
Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical
Center Director’s prior knowledge and written approval. Refer to specification Sections 26
05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 27 05 11
REQUIREMENTS FOR COMMUNICATIONS INSTALLATIONS and 28 05 00, COMMON
WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY for additional requirements.
2. Contractor shall submit a request to interrupt any such services to COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center.
Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by COR .
5. In case of a contract construction emergency, service will be interrupted on approval of
COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
L. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
M. To minimize interference of construction activities with flow of Medical Center traffic, comply with the following:
01 00 00 - 11
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
N. Coordinate the work for this contract with other construction operations as directed by the COR.
This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF
ROADWAYS.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed to the Contracting Officer. This report shall list by rooms and spaces:
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of Building 126
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur, and which have been agreed upon COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of Resident Engineer COR to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-2) and
"CHANGES" (FAR 52.243-4 and VAAR 852.236-88).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workmen in executing work of this contract.
01 00 00 - 12
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.
2. Items not reserved shall become property of the Contractor and be removed by
Contractor from Medical Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
1.9 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work.
Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR.
Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged. Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.)
01 00 00 - 13 disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES" (FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE
CONDITIONS" (FAR 52.236-2).
1.10 PHYSICAL DATA
A. Data and information furnished or referred to below is for the Contractor's information. The
Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
1.13 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To insure compliance, as-built drawings shall be made available for the COR review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version
(scanned PDF) COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
E. Contractor is to provide a LIDAR survey of the renovated area, the plenum spaces and roof above the affected area as part of the close out process. This LIDAR survey will serve as documentation that the work was completed and shall work in conjunction with the as-built drawings. The unregistered (raw) point cloud data and registered, linked, point cloud model shall be turned over the Government at project close out.
1.14 USE OF ROADWAYS
A. For hauling, use only established public roads and roads on Medical Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of
01 00 00 - 14 contract work. Temporary roads shall be constructed and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
1.15 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:
1. Permission to use each unit or system must be given by COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the COR will withdraw permission for use of the equipment.
2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted.
Installation of temporary electrical equipment or devices shall be in accordance with
NFPA 70, National Electrical Code, (2014 Edition), Article 590, Temporary Installations.
Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.
3. Units shall be properly lubricated, balanced, and aligned. Vibrations must be eliminated.
4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.
5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.
6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use;
and cleaned, maintained and inspected prior to acceptance by the Government.
B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the Government.
C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.
D. Any damage to the equipment or excessive wear due to prolonged use will be repaired replaced by the contractor at the contractor’s expense.
01 00 00 - 15
1.16 TEMPORARY USE OF EXISTING ELEVATORS
A. Use of existing elevators for handling building materials and Contractor's personnel will be permitted subject to following provisions:
1. Contractor makes all arrangements with the COR for use of elevators. COR will ascertain that elevators are in proper condition. Contractor may use elevators in Building No. 41 for for special nonrecurring time intervals when permission is granted. Personnel for operating elevators will not be provided by the Department of Veterans Affairs.
2. Contractor covers and provides maximum protection of following elevator components:
a. Entrance jambs, heads soffits and threshold plates.
b. Entrance columns, canopy, return panels and inside surfaces of car enclosure walls.
c. Finish flooring.
3. Government will accept hoisting ropes of elevator and rope of each speed governor if they are worn under normal operation. However, if these ropes are damaged by action of foreign matter such as sand, lime, grit, stones, etc., during temporary use, they shall be removed and replaced by new hoisting ropes at the contractor’s expense.
4. If brake lining of elevators are excessively worn or damaged during temporary use, they shall be removed and replaced by new brake lining at the contractors expense.
5. All parts of main controller, starter, relay panel, selector, etc., worn or damaged during temporary use shall be removed and replaced with new parts at the contractor’s expense, if recommended by elevator inspector after elevator is released by Contractor.
6. Place elevator in condition equal, less normal wear, to that existing at time it was placed in service of Contractor as approved by Contracting Officer.
1.18 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably required amounts of utilities available to the
Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to the
Government. The Contractor shall carefully conserve any utilities furnished without charge.
B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the
Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia and repair restore the infrastructure as required.
C. Contractor shall install meters at Contractor's expense and furnish the Medical Center a monthly record of the Contractor's usage of electricity as hereinafter specified.
LBVAHCS Long Beach, CA #600-18-200
01 00 00 - 16
D. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted. Maintain minimum temperatures as specified for various materials:
1. Obtain heat by connecting to Medical Center heating distribution system.
E. Electricity (for Construction and Testing): Furnish all temporary electric services.
1. Obtain electricity by connecting to the Medical Center electrical distribution system. The
Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat. Electricity for all other uses is available at no cost to the Contractor.
F. Water (for Construction and Testing): Furnish temporary water service.
1. Obtain water by connecting to the Medical Center water distribution system. Provide reduced pressure backflow preventer at each connection as per code. Water is available at no cost to the Contractor.
2. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes will be cause for revocation (COR discretion) of use of water from Medical Center's system.
1.19 TESTS
A. As per specification section 01 91 00 the contractor shall provide a written testing and commissioning plan complete with component level, equipment level, sub-system level and system level breakdowns. The plan will provide a schedule and a written sequence of what will be tested, how and what the expected outcome will be. This document will be submitted for approval prior to commencing work. The contractor shall document the results of the approved plan and submit for approval with the as built documentation.
B. Pre-test mechanical and electrical equipment and systems and make corrections required for proper operation of such systems before requesting final tests. Final test will not be conducted unless pre-tested.
C. Conduct final tests required in various sections of specifications in presence of an authorized representative of the Contracting Officer. Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.
D. Mechanical and electrical systems shall be balanced, controlled and coordinated. A system is defined as the entire system which must be coordinated to work together during normal operation to produce results for which the system is designed. For example, air conditioning supply air is only one part of entire system which provides comfort conditions for a building. Other related components are return air, exhaust air, steam, chilled water, refrigerant, hot water, controls and electricity, etc. Another example of a system which involves several components of different
01 00 00 - 17 disciplines is a boiler installation. Efficient and acceptable boiler operation depends upon the coordination and proper operation of fuel, combustion air, controls, steam, feedwater, condensate and other related components.
E. All related components as defined above shall be functioning when any system component is tested. Tests shall be completed within a reasonably period of time during which operating and environmental conditions remain reasonably constant and are typical of the design conditions.
F. Individual test result of any component, where required, will only be accepted when submitted with the test results of related components and of the entire system.
1.20 INSTRUCTIONS
A. Contractor shall furnish Maintenance and Operating manuals (hard copies and electronic) and verbal instructions when required by the various sections of the specifications and as hereinafter specified.
B. Manuals: Maintenance and operating manuals and one compact disc (four hard copies and one electronic copy each) for each separate piece of equipment shall be delivered to the COR coincidental with the delivery of the equipment to the job site. Manuals shall be complete, detailed guides for the maintenance and operation of equipment. They shall include complete information necessary for starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub-assembly components. Manuals shall include an index covering all component parts clearly cross-referenced to diagrams and illustrations. Illustrations shall include "exploded" views showing and identifying each separate item. Emphasis shall be placed on the use of special tools and instruments. The function of each piece of equipment, component, accessory and control shall be clearly and thoroughly explained.
All necessary precautions for the operation of the equipment and the reason for each precaution shall be clearly set forth. Manuals must reference the exact model, style and size of the piece of equipment and system being furnished. Manuals referencing equipment similar to but of a different model, style, and size than that furnished will not be accepted.
C. Instructions: Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed training to assigned Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site. These requirements are more specifically detailed in the various technical sections. Instructions for different items of equipment that are component parts of a complete system, shall be given in an integrated, progressive manner. All instructors for every piece of component equipment in a system shall be available until instructions for all items included in the system have been completed. This is to assure proper instruction in the operation of inter-related systems. All instruction periods shall be at such times as scheduled by the COR and shall be considered concluded only when the COR is satisfied in regard to complete and thorough coverage. The
01 00 00 - 18 contractor shall submit a course outline with associated material to the COR for review and approval prior to scheduling training to ensure the subject matter covers the expectations of the
VA and the contractual requirements. The Department of Veterans Affairs reserves the right to request the removal of, and substitution for, any instructor who, in the opinion of the COR , does not demonstrate sufficient qualifications in accordance with requirements for instructors above.
1.21 CONSTRUCTION SIGN
A. Provide a Construction Sign where directed by the COR. All wood members shall be of framing lumber. Cover sign frame with 0.7 mm (24 gage) galvanized sheet steel nailed securely around edges and on all bearings. Provide three 100 by 100 mm (4 inch by 4 inch) posts (or equivalent round posts) set 1200 mm (four feet) into ground. Set bottom of sign level at 900 mm (three feet) above ground and secure to posts with through bolts. Make posts full height of sign. Brace posts with 50 x 100 mm (two by four inch) material as directed.
B. Paint all surfaces of sign and posts two coats of white gloss paint. Border and letters shall be of black gloss paint, except project title which shall be blue gloss paint.
C. Maintain sign and remove it when directed by the COR.
1.22 SAFETY SIGN
A. Provide a Safety Sign where directed by the COR. Face of sign shall be 19 mm (3/4 inch) thick exterior grade plywood. Provide two 100 mm by 100 mm (four by four inch) posts extending full height of sign and 900 mm (three feet) into ground. Set bottom of sign level at 1200 mm (four feet) above ground.
B. Paint all surfaces of Safety Sign and posts with one prime coat and two coats of white gloss paint.
Letters and design shall be painted with gloss paint of colors noted.
C. Maintain sign and remove it when directed by the COR.
D. Standard Detail Drawing Number SD10000-02(Found on VA TIL) of safety sign shows required legend and other characteristics of sign.
E. Post the number of accident free days on a daily basis.
1.23 HISTORIC PRESERVATION
Where the Contractor or any of the Contractor's employees, prior to, or during the construction work, are advised of or discover any possible archeological, historical and/or cultural resources, the Contractor shall immediately notify the COR verbally, and then with a written follow up.
- - - E N D - - -
JRM
2015(v3)
V
A Long B each H ealthcare System
P
R
EC
O N
STR
U
C
TIO
N R
ISK
A
SSESSM
EN
T FO
R
C O
N
STR
U C
TIO
N
A N
D R
EN
O
V A
TIO
N
Step O ne:
U sing the follow table, identify the Type of C onstruction P roject A ctivity (Types A -D
Type A
Inspection and N on
-invasive activities, including, but not lim ited to:
R em oval of ceiling tiles for visual inspections w here no dust or asbestos is expected (Lim ited to 1 tile per 50 square feet)
Painting, but not sanding
W all covering, electrical trim w ork, m inor plum bing, and activities w hich do not generate dust or require cutting of w alls or access to ceilings other than for visual inspection
Type B
Sm all scale, short duration activities w hich create m inim al dust, including but not lim ited to:
Installation of electrical, plum bing, H VAC, telephone and com puter cabling
Access to chase spaces w here asbestos is not present
Cutting of w alls or ceiling w here dust m igration can be controlled
Type C
W ork that generates a m oderate to high…