This is Amendment 0002 to a Department of Veterans Affairs (DVA) Request for Proposals (RFP) for testing, inspecting, preventative maintenance, corrective repair, emergency repair, and service calls for the VA's Boiler/Chiller & Cogeneration plant located in Buildings 70, 87, and 2J at the Dallas VA Medical Center.
The amendment provides responses to 109 questions submitted by offerors and updates the Performance Work Statement (PWS) and Schedule B.2 accordingly. Key clarifications include: corrective and emergency repair parts will be purchased by the contractor using funds from CLIN 0002 with COR approval; the 1,500 repair labor hour bank is firm fixed price and resets annually; the $250,000 NTE applies to parts and materials only and is separate from the repair labor hours; repair labor is billed at $200 per hour not to exceed 1,500 hours per year; contractor personnel must include properly certified technicians for OEM equipment; monthly inspections for steam chillers total 12 monthly plus 1 annual (not 11); boiler tube cleaning is one boiler per year on a four-year rotation; Solar turbine repairs and parts are exclusively sourced through Solar Turbines with no current service agreement transferring; BAC cooling tower work must be performed by a verified BAC-authorized service contractor; the contractor must provide a full-time onsite project coordinator Monday through Friday, 8:00 AM to 5:00 PM; and all certifications must be in place at time of contract award. The contract period is base year plus four one-year options, with performance beginning November 15, 2026. The amendment includes the updated revised Schedule B.2 price/cost schedule with CLINs for the base year and four option years, detailed task sheets for equipment-specific maintenance requirements, and a site visit attendance roster.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25727R0005 0001.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE 7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO. 1. CONTRACT ID CODE
FACILITY CODE CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30 PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243
(Type or print) (Type or print)
(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code)
(If other than Item 6)
(Specify type of modification and authority)
(such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
1 81
0002 09-28-2026
36C257
Department of Veterans Affairs Central Texas Veterans HCS 1901 Veterans Memorial Dr. Building #171 Temple, TX 76504
To all Offerors/Bidders 36C25727R0005
08-10-2026 X
X X
See CONTINUATION Page
X 1
The purpose of this amendment is to:
a. Provide answers to questions that were asked by the due time and date in the soliciation.
b. Update Schedule B.2 based on answers to questions.
c. Update the Performance Work Statement (PWS) based on answers to questions (Changes highlighted in yellow).
d. Provide a copy of the Site Visit Roster.
///SEE CONTINUATION PAGES///
Shawn R. Reinhart Contracting Officer
36C25727R0005-0002 CONTINUATION PAGES
QUESTIONS WITH ANSWERS
QUESTION 1: Section 6.3.3 states that any parts required for repair/corrective maintenance "will be purchased by the VA," while Section 6.6 and the "Unforeseen Repairs, Parts & Materials" CLINs (NTE $250,000 each) state that corrective and emergency repair parts "will be purchased by the contractor upon approval of the COR." Please confirm which party purchases corrective/emergency repair parts, and how those parts are to be priced and reimbursed under the CLIN structure.
ANSWER 1: Will be purchased by the contractor upon approval of the COR.
QUESTION 2: The 1,500 repair-labor-hour bank is described as being tracked under "CLIN 0002," but CLIN 0002 is the "Unforeseen Repairs, Parts & Materials" line (NTE $250,000). Please clarify:
a. whether the 1,500 hours are priced within the monthly CLIN 0001 firm-fixed price or drawn against the $250,000 NTE line;
b. whether the 1,500 hours are per year or for the entire period of performance;
c. whether unused repair hours roll over or expire each period;
d. the labor rate basis the Government expects for hours drawn from the bank.
ANSWER 2: a. See revised Schedule B.2.
b. Per year
c. Reset each year,
d. See revised Schedule B.2.
QUESTION 3: In the event the contractor exhausts the repair-labor-hour bank within a performance period, will the Contracting Officer approve additional hours, and what is the process and approval authority for requesting them? (Note: the solicitation states 1,500 hours; if the Government intends a different figure, please confirm the correct number of banked repair hours.
ANSWER 3: A Mod will be requested by the COR
QUESTION 4: Section 6.3.6 references "preventative maintenance defined in Section 1.5." There is no Section 1.5 in the PWS. Please identify the intended reference so offerors can correctly distinguish PM labor from repair-bank labor.
ANSWER 4: See revised Schedule B.2
QUESTION 5: For pricing the FFP monthly CLIN, please confirm whether historical corrective/emergency repair-hour usage and parts expenditure from the incumbent contract can be provided, so offerors can price the repair bank and NTE line on a common basis.
ANSWER 5: No, it is the incumbents’ records and agreements. All labor and maintenance funds were expended.
QUESTION 6: The "Unforeseen Repairs, Parts & Materials" NTE amount ($250,000) is stated per contract period. Please confirm this ceiling is per period/year and clarify whether the Contracting Officer will approve additional funds — and by what process — if repair/parts costs exceed the NTE within a performance period. (Note: the solicitation states $250,000 NTE; if the Government intends a different figure, please confirm.)
ANSWER 6: Per Year / The COR approves and coordinates the increase with the CO by contract modification.
QUESTION 7: Several PWS scope elements appear to require OEM-authorized or manufacturer-representative performance — Solar Mercury 50 turbine service, Frick gas compressor service, BAC cooling-tower work ("must be performed by BAC Manufacturer’s Representative," p.30), and switchgear rack-in/rack-out ("must be performed by qualified subcontractor personnel," p.35). Given the 50% limitation on subcontracting for services, please confirm whether the Government intends for these
OEM/manufacturer-representative tasks to count against the prime’s 50% self-performance requirement, or whether any are treated as excluded direct costs under 13 CFR 125.6.
ANSWER 7: Offerors are responsible for ensuring compliance with VAAR 852.219-75. It is not the Government's responsibility to advise offerors on how they can meet the compliance requirements.
QUESTION 8: Please confirm whether the Government is aware of any VIP-listed SDVOSB firms holding Solar Turbines factory authorization for the Mercury 50, or VHA-1810 boiler safety-device testing qualification, that would qualify as "similarly situated" for limitations-on-subcontracting purposes.
ANSWER 8: The VIP database formerly managed by the VA no longer exists. Currently the VA uses the Small Business Administration, Small Business Search (https://search.certifications.sba.gov/) to verify socio-economic status.
QUESTION 9: Please confirm the warranty status and expiration date of the Solar Mercury 50 gas turbine and enclosure and confirm whether service of this unit must be performed exclusively by Solar Turbines-authorized technicians (consistent with PWS section 6.6, which routes Solar repairs and parts through the contractor to Solar). This information is necessary to determine the required service provider and to price the turbine scope.
ANSWER 9: There is no warranty / exclusively by Solar. Contractors would have to have an agreement with Solar
QUESTION 10: Please confirm whether the Rentech HRSG and Solar Mercury 50 tasks must be performed by current factory-authorized representatives, or whether qualified independent technicians with documented equivalent experience are acceptable.
ANSWER 10: Solar Mercury 50 is to be performed by factory- authorized representative, and the Rentech HRSG can be by a qualified representative.
QUESTION 11: The task sheets indicate that on the York YST steam chillers the contractor brushes the tubes, while on the York YK electric chillers "VA staff to brush tubes" (p.46). Please confirm the division of tube-brushing responsibility between the contractor and VA staff across all chillers so labor can be priced correctly.
ANSWER 11: Contractor to complete chiller tube brushing on both evaporator and condenser.
QUESTION 12: Eddy-current testing is shown next due November 2026 (Chillers #1 and #2) — within the first weeks of the base period (POP begins 11/15/2026). Please confirm the Government’s expected schedule for the first eddy-current testing cycle and whether it falls within the base year firm-fixed price.
ANSWER 12: Yes, and the cost is within the base year of the contract, due per PWS additional tasks shown in Attachments to PWS.
QUESTION 13: The PWS states the VA will provide the scissor lift needed for the Solar system and that the contractor must maintain certifications per Solar/manufacturer requirements for the VA-supplied Solar lifting and rigging equipment. Please confirm (a) that the VA both furnishes and maintains/inspects the lift itself, and (b) exactly which operator/lifting-and-rigging certifications the Government expects contractor personnel to hold for use of the VA-supplied equipment.
ANSWER 13: Certifications are for the Solar lifting and rigging equipment only that the VA owns.
QUESTION 14: The boiler equipment schedule lists the three Cleaver Brooks DL-52 boilers, the Rentech HRSG, and the deaerator (DA tank), but does not list a condensate tank/receiver. Please confirm whether a condensate tank is part of the equipment covered under this contract and, if so, provide its make, model, and serial and its required PM tasks.
ANSWER 14: The condensate (surge tank) is not listed, but if work is needed that would fall under the unforeseen repairs/correction repairs.
QUESTION 15: For the quarterly boiler preventive maintenance, please confirm whether the contractor is required to perform testing in accordance with the VHA Boiler and Associated Plant Safety Device https://search.certifications.sba.gov/
Testing Manual during the quarterly PM, or only the specific task/check points listed on the quarterly PM task sheet. (The safety-device-manual testing appears to be an annual requirement; please clarify the quarterly scope.)
ANSWER 15: As per PWS located under Attachments to PWS, The quarterly and annual PM service would be completed as quarterly and annual requirements.
QUESTION 16: The additional boiler tasks require mechanical tube cleaning ("rattling") performed on one boiler each year on a rotation such that each of the four boilers is completed once every four years.
Please confirm how this four-year rotation is to be scheduled and priced across the contract period of performance (base year plus four option years) and identify which specific boiler(s) are due for rattle-punch cleaning in the base year. (Note: if the Government intends a period of performance other than the five-year base-plus-four-options structure in the B.2 schedule, please confirm the correct contract length.)
ANSWER 16: Scheduling of the boilers tube rattling can be planned once the contractor has been selected. The is a base plus 4 contract only, so one of the boilers would have two tube rattling conducted within the base plus four period...
QUESTION 17: Please confirm whether an annual internal (and external) boiler certification/inspection performed by an authorized/certificated boiler inspector — including any non-jurisdictional (National Board / insurance) authorized inspector inspection — is within the contractor’s scope of work, or whether such certificated-inspector inspections are furnished or arranged by the VA. The PWS specifies safety-device testing (VHA 1810), combustion/operational testing, and mechanical tube cleaning, but does not reference NDT or an authorized-inspector internal/external boiler inspection.
ANSWER 17: Internal/ external inspection and safety device texting i.e. safety relief valves are not included in this contract.
QUESTION 18: The cover page notes this RFP "aligns with 36C25727Q0003," while the solicitation number is 36C25727R0005. Please confirm 36C25727R0005 is the operative solicitation number for proposal submission and that no separate response to 36C25727Q0003 is required.
ANSWER 18: 36C25727Q0003 was the sources sought. Because the requirement required more information, the solicitation number was changed to 36C25727R0005 to accommodate the changes.
QUESTION 19: Please confirm the logistics for the 16 September 2026 (0900 CDT) site visit — registration/RSVP method and deadline, required identification/badging, whether attendance is mandatory for award eligibility, and whether teaming partners/subcontractors may attend with the prime.
ANSWER 19: Site visits have been conducted and are completed.
QUESTION 20: Please confirm whether resumes and OEM/manufacturer certification documents submitted as "Technical Exhibits" are excluded from the 25-page Technical Approach limit (as indicated in the Volume I page-count table), and whether a compliance/cross-reference matrix would likewise be treated as an excluded exhibit.
ANSWER 20: The table on page 75 clearly states “Does not include Technical Exhibits (such as Resumes) which means the technical exhibits are not counted in the 25 pages of the Technical Proposal.
This includes OEM/manufacturer certification documentation. A compliance / cross-reference checklist will be treated as a technical exhibit.
QUESTION 21: The equipment schedules provide equipment names and, in some cases, serial numbers, but complete manufacturer, model, and serial data is missing for the majority of listed equipment (summarized in the attached Equipment Data table). Complete nameplate data is necessary to identify OEM parts, apply the correct OEM preventive-maintenance procedures, determine tube counts for eddy-current testing, and price the repair-parts and NTE lines accurately. Please provide a complete equipment inventory listing the manufacturer, full model number, and serial number for all listed equipment — including the seven York chillers, the two air-cooled chillers, all eight BAC cooling towers, all chilled-water/condenser-water pumps and water separators, all VFDs/drives, the Rentech HRSG boiler, the deaerator (DA tank), and the full cogeneration electrical and controls train (Mercury 50 turbine, Frick compressor, KATO generator, protective relays, switchgear, ATS, MCC, and glycol pump set).
Alternatively, please confirm whether the Government intends offerors to capture nameplate data by physical inspection at the 16 September 2026 site visit.
ANSWER 21: Contractors that were at the site visit were able to take pictures of all names’ plates. The equipment’s name is the manufacturer, and the serial number would get you all information from the manufacturer. OEM parts shall be provided within a quote if repairs are needed.
QUESTION 22: The serial number for Chiller #3 is listed as "#SLBM2915527B," while the sibling YK electric chillers follow the pattern "#SLBM92915527A/C/D." Please confirm whether the Chiller #3 serial contains a typographical error and provide the correct serial number.
ANSWER 22: Typographical error, #3 – SLBM92915527B / #4 - SLBM92915527A / #5 -
SLBM92915527C / #6 - SLBM92915527D
QUESTION 23: The two 300-ton air-cooled screw chillers are listed with serial numbers but no manufacturer/model in the equipment schedule; a later task sheet (p.29) identifies them as "York YCAV."
Please confirm the complete manufacturer and model number for these two units.
ANSWER 23: Air Cooled Screw chiller MODEL#YCAV0307PA46VABBXT
SERIAL#1 – 2HXM013135,#2 – 2HXM013136
QUESTION 24: PWS §11 requires "Murray Steam Turbine technicians," indicating the York YST steam-driven chillers (#1 and #2) are driven by steam turbines whose make and model are not stated in the equipment schedule. Please provide the manufacturer, model, and serial number of the steam turbines on the YST chillers and confirm whether the drive make is Murray.
ANSWER 24: Yes, the drive is Murray. YORK MODEL# YSTHFGDJ1-K2G51000090-11-1.361-
29168A-FS
SERIAL #1 - SGTM-000900, #2 – SCSM-443320
QUESTION 25: The table below summarizes the manufacturer, model, and serial data provided in Exhibit A of the solicitation. Cells shaded and marked - MISSING - indicate data not provided in the solicitation. Entries shown in amber are partial or ambiguous (e.g., a model family without a full model number, a drive/manual reference in place of the unit model, or data appearing only in a task sheet rather than the equipment schedule).
ANSWER 25: Completed to best of our ability
QUESTION 26: The Equipment Schedule identifies a series/refrigerant designation for each chiller (e.g., York YST R-134A, York YKR R-22, York YK R-134A), but it does not provide the complete manufacturer model number. Please provide the full OEM model number for each of the seven (7) chillers (Chillers #1 through #7) exactly as shown on the equipment data/nameplate. RJY understands the designations currently listed to identify the chiller type/series rather than the complete model number.
ANSWER 26: YST -YSTHFGDJ1-K2G51000090-11-1.362-29168A-FS, YKr22 - YK Q2 P2 H1 CBA, YKR134A- YKQCQLK2-DBHS
QUESTION 27: The Equipment Schedule lists the following serial numbers:
The serial number provided for Chiller #3 appears to be missing a digit when compared with the numbering pattern shown for Chillers #4, #5, and #6. Please confirm whether the serial number listed for Chiller #3 contains a typographical error or omission.
• Chiller #3: SLBM2915527B
• Chiller #4: SLBM92915527A
• Chiller #5: SLBM92915527C
• Chiller #6: SLBM92915527D
Please confirm the correct serial numbers, as shown on the equipment data/nameplates, for Chillers #3, #4, #5, and #6.
ANSWER 27: SLBM92915527B
QUESTION 28: To assist offerors in preparing accurate technical and pricing proposals, would the Government be willing to provide photographs of the equipment data/nameplates for Chillers #3 through
Equipment Manufacturer Model No. Serial No. VFD #1 Boiler (water tube) Cleaver Brooks DL-52E LH #WG-3768 Danfoss# VLT6032GT4CN1STR0DLF00A00C0 #2 Boiler (water tube) Cleaver Brooks DL-52E RH #WG-3766 Danfoss# VLT6032GT4CN1STR0DLF00A00C0 #3 Boiler (water tube) Cleaver Brooks DL-52E RH #WG-3767 Danfoss# VLT6032GT4CN1STR0DLF00A00C0 #4 Boiler (HRSG, water tube) Rentech O-TYPE WATER TUBE 2011-42-BLR Weg # EUCFW110031T40FAZ Air-Cooled Chiller #1 (300-ton screw) York (per p.29 task sheet only) YCAV (per p.29 — absent from 2HXM013135 Air-Cooled Chiller #2 (300-ton screw) York (per p.29 task sheet only) YCAV (per p.29 — absent from 2HXM013136 Automatic Transfer Switch (ATS) ASCO 970326 H7ACTBB30800NSXL Bell & Gossett Glycol Pump Set (2) Bell & Gossett Series 80-SC N/A NIDEC HV-300 Chill Water Pump #10 (serves Chiller #7) TACO N/A N/A Chill Water Pumps #1 BELL & GOSSETT HSC-3-940 C064721-01-F80 Chill Water Pumps #2 BELL & GOSSETT HSC-3-940 C035972-01-A70 Chill Water Pumps #3– 6 BELL & GOSSETT F20-05 N/A Chiller #1 (1000 ton) York YST (family only — no full model) #SGTM-000900 Chiller #2 (1000 ton) York YST (family only — no full model) #SCSM-443320 Chiller #3 (1000 ton) York YKR (family only) YK-Q2 P2 H1 CBA #SLBM92915527B Chiller #4 (1000 ton) York YKR (family only) YK-Q2 P2 H1 CBA #SLBM92915527A Chiller #5 (1000 ton) York YKR (family only) YK-Q2 P2 H1 CBA #SLBM92915527C Chiller #6 (1000 ton) York YKR (family only) YK-Q2 P2 H1 CBA #SLBM92915527D Chiller #7 (1500 ton) York YK (family only) YDHK-84VDD #SFKM-043450 Cond. Water Separator 1200 GPM #2 AMIAD 200110-000047 S0330840-10230898 Cond. Water Separator 1200 GPM #3 AMIAD 200110-000047 S0330840-10230899 Cond. Water Separator 1200 GPM #4 AMIAD 200110-000047 S0330840-10230897 Cond. Water Separator 600 GPM #5 AMIAD 200109-000062 S0330840-10230900 Condenser Water Pumps #1 GOULDS N/A N/A Condenser Water Pumps #2 GOULDS N/A N/A Condenser Water Pumps #3 HYDROFLO 14HL-2 TX33327-6 ABB # ACH580-3BCR-124A+F267 Condenser Water Pumps #4 HYDROFLO 14HL-2 TX33327-3 ABB # ACH580-3BCR-124A+F267 Condenser Water Pumps #5 HYDROFLO 14HL-2 TX33327-4 ABB # ACH580-3BCR-124A+F267 Condenser Water Pumps #6 HYDROFLO 14HL-2 TX33327-5 ABB # ACH580-3BCR-124A+F267 Condenser Water Pumps #7 HYDROFLO 14HL-2 TX33327-3 ABB # ACH580-3BCR-124A+F267 Condenser Water Pumps #8 HYDROFLO 14HL-2 TX33327-6 ABB # ACH580-3BCR-124A+F267 Cooling Towers #1 BAC 31301/AV (partial) TWR 1 U065958701 ABB # ACS880-01-124A-5+N7581+X1563 Cooling Towers #2 BAC 31301/AV (partial) TWR 2U065958702 ABB # ACS880-01-124A-5+N7581+X1563 Cooling Towers #3 BAC BAC 3000E MODEL# S3E-1222-14S U212059903-01-01 ABB# ACS880-01-124A-5+N5350+N8029 Cooling Towers #4 BAC BAC 3000E MODEL# S3E-1222-14S U212059903-02-01 ABB# ACS880-01-124A-5+N5350+N8029 Cooling Towers #5 BAC BAC 3000E MODEL# S3E-1222-14S U212059903-01-01 ABB# ACS880-01-124A-5+N5350+N8029 Cooling Towers #6 BAC BAC 3000E MODEL# S3E-1222-14S U212059902-01-01 ABB# ACS880-01-124A-5+N5350+N8029 Cooling Towers #7 BAC BAC 3000E MODEL# S3E-1222-14S U212059903-04-01 ABB# ACS880-01-124A-5+N5350+N8029 Cooling Towers #8 BAC BAC 3000E MODEL# S3E-1222-14S U212059903-03-01 ABB# ACS880-01-124A-5+N5350+N8029 DA Tank (Deaerator, 125,000 lbs) BFS INDUSTRIES 125MDVT #11033-12-18A/B (partial) Frick Gas Compressor Frick XJF-95S 10241K211279877 Hayden Lube Oil Heat Exchanger Hayden TT-424 S18562 High Voltage Switch EATON VC-W MDA0006000-002 HRSG Duct Burner DeJONG / R&V Engineering TTL/MG 7,5 3177 Load / Input Transmitter Controls Allen-Bradley N/A N/A Mercury 50 Gas Turbine Engine Solar Mercury 50 (line only — no full PG12848 A/B PowerFlex 700 / Eaton HVX 9000 Motor Control Center Freedom (2100 series) Freedom 2100 N/A Paralleling Switchgear SEL SEL3530 N/A Power AC Generator KATO N/A N/A Protective Relays (set) Schweitzer (SEL) / GE / Basler SEL5872 N/A Second Chill Water Pumps #11 & 12 TACO TA2530 N/A ABB # ACH580-3BCR-124A+F267 Second Chill Water Pumps #7 – 9 BELL & GOSSETT A-C 8100 N/A ABB # ACH580- Synchronizing Switchgear EATON MVS G166081-P
#6, or preferably for all seven (7) chillers? The photographs should clearly display the model number, serial number, and any other relevant nameplate information ANSWER 28: Please look at questions 21, 23, 24, 26, and 27. Contractors were able to take pictures at site visit.
QUESTION 29: The PWS references adjusting water chemical feed and feed rate and also includes cooling-tower blowdown adjustments. Please confirm whether the contractor is required to provide:
• Water-treatment chemicals for the cooling towers, boilers, chilled-water, and condenser-water systems
• Routine water testing and chemical analysis
• Chemical delivery and replenishment
• Chemical feed equipment service/calibration
• Legionella testing or Water Management Program support
• Any other ongoing water-treatment services
If these services are required, please identify the applicable section of the PWS and the expected frequency.
ANSWER 29: No
QUESTION 30: Would it be possible to accommodate an additional site visit before the September 30 proposal deadline? We were unable to attend the September 16 site visit. This would allow our technical teams to inspect the equipment conditions and develop accurate pricing for the complete requirement.
ANSWER 30: No
QUESTION 31: The equipment schedule provides serial numbers but does not identify the corresponding model numbers. Please provide the model number for each unit where it is omitted. If a model-number list is unavailable, please provide clear photographs of the manufacturer’s equipment nameplates or data plates showing the make, model, and serial number.
ANSWER 31: Information was made available for every offeror on all equipment during site walk thru.
QUESTION 32: Tube brushing – York YK motor-driven chillers: We normally just pull the non-piping end (turnaround head) to brush. Need to clarify: does "pull all heads" in the scope mean we also drop both piping-side end heads?
ANSWER 32: Both ends are to be removed.
QUESTION 33: Eddy current testing: Is this called out in the scope? If so, which chillers need eddy currents?
ANSWER 33: All dates are listed as additional tasks on the Section II Equipment Schedule Exhibit A: Dallas b). Chillers
QUESTION 34: Schedule: Can we get the schedule for the one-year contract they're requesting?
ANSWER 34: Who requested this information? What is the contract number?
QUESTION 35: Air-cooled chillers: What are the model numbers?
ANSWER 35: See Question 23
QUESTION 36: Cooling tower sweeper pumps: Are these on our PM scope? They're on site but not listed in the scope.
ANSWER 36: No
QUESTION 37: The solicitation identifies NAICS 238220, Plumbing, Heating, and Air-Conditioning Contractors. However, Section C.9, VAAR 852.219-75(a)(1), checks Services and leaves Special trade construction contractors unchecked. The checked Services provision limits payments to firms that are not similarly situated certified SDVOSB/VOSB concerns to 50%, while the special trade construction provision states a 75% limit, excluding the cost of materials.
The PWS requires specialized work on equipment that supports the Dallas VA Medical Center’s critical plant operations, including:
• Eight BAC cooling towers, for which the PWS requires work by a BAC manufacturer’s representative;
• Seven York centrifugal chillers: two steam-driven 1,000-ton units, four electric-driven 1,000-ton units, and one electric-driven 1,500-ton unit;
• Three Cleaver-Brooks water-tube boilers and one Rentech heat recovery steam generator boiler;
• One Solar Mercury 50 gas turbine and its associated Frick gas compressor; and
• Associated variable frequency drives, chilled-water and condenser-water pumps, controls, and electrical systems.
The PWS and evaluation criteria also require appropriately certified or qualified personnel for equipment including the chillers, Solar turbine, HRSG and controls, boiler controls, and electrical systems.
Please confirm whether the Government intends NAICS 238220 to classify this entire acquisition as a special trade construction contract for purposes of the limitation on subcontracting, or whether the Government intends the checked Services category in VAAR 852.219-75(a)(1)(i) to govern the entire contract, including the OEM-qualified maintenance, testing, and repair work listed above. If Services governs, please explain how the Government reconciles that selection with the assigned NAICS code. If the Government intends the special trade construction limit to apply, please issue an amendment checking the applicable provision in Section C.9 and identifying the work and pricing to which that limit applies.
Please also confirm how offerors should calculate compliance when using required OEM or manufacturer-authorized providers that are not similarly situated certified SDVOSB/VOSB concerns, including whether any work may be evaluated separately and which costs, if any, may be excluded from the calculation. This clarification is needed for consistent staffing, subcontracting, certification, and pricing proposals.
ANSWER 37: Special Trade Construction Contractors will not be checked in VAAR 852.219-75. This requirement does not involve construction or special trade construction. Market research shows the most appropriate NAICS code and the PSC (listed in the CLINs) chosen are proper. The PSC for this requirement is Z1NB (Maintenance of Heating and Plumbing Plants).
The following trades are formally recognized as special trade construction activities:
• CORE BUILDING & MECHANICAL TRADES
o Painting & Paper Hanging (including bridge painting and traffic lane painting) [osha.gov] o Electrical Work (bridges, power plants, power lines, building electrical systems)
[osha.gov] o Carpentry & Trim Work [osha.gov] o Plumbing, Heating, & Air‑Conditioning (HVAC) [osha.gov] o Roofing, Siding & Sheet Metal Work [osha.gov]
• STRUCTURAL, MASONRY & FINISHING TRADES
• Masonry, Stonework, Tile Setting & Plastering o Masonry o Plastering & Drywall o Acoustical & Insulation work o Terrazzo, Tile, Marble & Mosaic Work
• Concrete Work (forming, pouring, finishing)
• UTILITY, SITEWORK & DRILLING TRADES
o Water Well Drilling o Excavation Work o Wrecking & Demolition Work
• SPECIALIZED INSTALLATION & EQUIPMENT TRADES
These “Miscellaneous Special Trades” (SIC 1799) include numerous specialty contractors:
o Structural steel erection o Glass & glazing work o Fence construction o Fireproofing / Dampproofing / Waterproofing o Scaffolding construction o Ornamental metal installation o Bath tub refinishing o Boring/drilling for construction o Core drilling o Sandblasting / Steam cleaning building exteriors o Lightning conductor installation o Mobile home site setup o Countertop installation o Weather stripping o Welding contractors working on construction sites o Cable splicing (non‑electrical) o Spectator seating installation o Artificial turf installation o Gas leak detection o Gasoline pump installation o Posthole digging o Fireplace/escape and building equipment erection, not elsewhere classified
SIC 1799, which is not included in the April 2025 PSC Manual, includes contractors primarily engaged in construction work not elsewhere classified. SIC 1799 is a catch‑all construction service code used when a contractor performs a specialized trade that does not squarely fall under standard roofing, HVAC, electrical, plumbing, or general construction PSCs. It encompasses a wide range of niche installation, demolition, coating, drilling, prepping, and specialty construction services.
QUESTION 38: Please also confirm how offerors should calculate compliance when using required OEM or manufacturer-authorized providers that are not similarly situated certified SDVOSB/VOSB concerns, including whether any work may be evaluated separately and which costs, if any, may be excluded from the calculation. This clarification is needed for consistent staffing, subcontracting, certification, and pricing proposals.
ANSWER 38: Offerors are responsible for ensuring compliance with VAAR 852.219-75. It is not the Government's responsibility to advise offerors on how they can meet the compliance requirements.
QUESTION 39: Please clarify whether the cooling direct drive Endura systems will be included in this solicitation and if you deem them special trade and will want certified personnel to maintain them? How will that effect the SDVOSB Special Trade percentage?
ANSWER 39: Yes, the cooling direct drive Endura is included. It is not the Government's responsibility to advise offerors on how they can meet the compliance requirements
QUESTION 40: During the walk through, we were told that chillers 3-6 and cooling towers 1-2 are to be replaced in the next 10-18 months. How will that effect this contract bid? Are these chillers and cooling towers considered Special Trade equipment and require certified personnel to maintain them? How will that effect the SDVOSB Special Trade percentage?
ANSWER 40: Towers 1-2 were not stated to be replaced during the walkthrough. Chiller 3-6 are to be changed out / R513A refrigerant (new). Offerors are responsible for ensuring compliance with VAAR 852.219-75. It is not the Government's responsibility to advise offerors on how they can meet the compliance requirements.
QUESTION 41: Why does the solicitation require a redacted copy of the same technical approach, limited to 25 pages. Remove company and subcontractor names, logos, personnel names, and other identifying details when you ask for specific VA performance experience that will identify the respondent?
ANSWER 41: The solicitation requires a separate redacted copy of the same technical approach to ensure fairness and procurement integrity. This measure ensures that technical evaluators assess each submission solely on its merits, without the possibility of organizational or personal bias.
QUESTION 42: PWS Section 6.3.6 states that 1,500 repair labor hours will be drawn from CLIN 0002, while the price schedule describes CLIN 0002 as a $250,000 NTE line item for unforeseen repairs, parts, and materials. Please confirm whether the 1,500 hours are included in the NTE amount, included in CLIN 0001, or priced separately. Please also confirm how offerors should complete the pricing for CLIN 0002 and the corresponding option-year CLINs.
ANSWER 42: The labor hours are a part of the fixed price. See revised Schedule B.2.
QUESTION 43: PWS Section 6.3.3 states that repair parts will be purchased by the VA, while Section
6.6 states that they will be purchased by the contractor after COR approval. Please confirm which party is responsible for purchasing repair parts and how contractor-purchased parts will be reimbursed.
ANSWER 43: Contractor using funds from CLIN 0002 with COR approval.
QUESTION 44: PWS Section 6.7 requires a full-time onsite project coordinator. Please confirm whether the coordinator must be physically onsite Monday through Friday from 8:00 AM to 5:00 PM throughout the contract period or only while scheduled work is being performed. May the coordinator also perform qualified technical work under the contract?
ANSWER 44: Physically on-site Monday through Friday from 8:00 AM to 5:00 PM throughout the contract period. Yes, providing this does not interfere with other daily obligations.
QUESTION 45: Exhibit A does not provide quantities for the 600 GPM condenser-water separator, the 600-volt panelboards, and several other electrical and cogeneration equipment entries. Please provide the quantities for all equipment requiring testing or preventive maintenance where the quantity field is blank.
ANSWER 45: Condenser-water separator = 4 / 600-volt panelboards = 1
QUESTION 46: Section III states that steam-chiller operational inspections are required 11 times per year, while the description states “eleven (12)” monthly inspections. Please confirm whether the requirement is 11 monthly inspections plus the annual preventive maintenance or 12 monthly inspections plus a separate annual preventive maintenance.
ANSWER 46: 12
QUESTION 47: PWS Section 6.4.1 requires a technician onsite within two hours, while Technical Sub- Factor 1(a)(3) requires a certified technician onsite within 12 hours. Please confirm whether the two-hour responder must hold the applicable equipment-specific certification or whether a certified technician may arrive within 12 hours.
ANSWER 47: A certified technician may arrive within 12 hours
QUESTION 48: Boiler tube cleaning frequency. Please clarify the required frequency for mechanical tube cleaning/rattle punching of the four boilers. Page 16 states one boiler per year so each boiler is completed every four years, while Page 33 states ‘Annual Cleaning of all boilers’ and ‘Once each per boiler.’ Which requirement governs?
ANSWER 48: One boiler per year so each boiler is completed every four years.
QUESTION 49: Steam chiller monthly PM frequency. Please clarify whether the two YORK YST steam chillers require eleven (11) monthly PM inspections per year or twelve (12). The PWS states both ‘11 times per year’ and ‘eleven (12) monthly inspections.’
ANSWER 49: 12 monthly’s and 1 annual. 1 monthly can coincide with the annual 12 Preventative Maintenance inspections and reports.
QUESTION 50: Corrective repair parts responsibility. Please clarify responsibility for purchasing corrective repair and emergency repair parts. Section 6.3.3 states parts required for corrective maintenance will be purchased by the VA, while Section 6.6 states corrective/emergency parts will be supplied by the Contractor after COR approval. Please identify which provision governs and how these costs are to be billed under CLIN 0002.
ANSWER 50: See revised Schedule B.2
QUESTION 51: $250,000 NTE - labor, parts, or both. Please confirm whether the $250,000 annual NTE under CLIN 0002 is intended to cover the combined cost of the 1,500 repair labor hours, parts/materials, equipment, rigging and emergency response, or whether the 1,500 labor hours are separately funded from the $250,000 parts/materials NTE.
ANSWER 51: 1,500 labor hours are separately funded from the $250,000 parts/materials NTE.
QUESTION 52: For the 1,500-hour repair labor bank, should offerors include an hourly repair labor rate within CLIN 0002, or is the Government requesting one lump-sum annual amount for the entire 1,500-hour allowance?
ANSWER 52: Repair labor rate will be provided.
QUESTION 53: Unused repair hours / NTE funds. Are CLIN 0002 repair labor hours and the $250,000 NTE paid only when authorized and used, or is CLIN 0002 intended to be awarded as a fully funded annual lump-sum amount?
ANSWER 53: Unused repair hours will be defunded at the end of each contact period.
QUESTION 54: Solar Turbines responsibility. Please clarify which Mercury 50 services must be performed directly by Solar Turbines versus work that may be performed by an appropriately Solar-certified third-party technician. Please also identify any Solar service agreement currently in place that will transfer to or remain available to the awarded contractor.
ANSWER 54: All services sole source with solar. No current agreement will transfer.
QUESTION 55: Solar parts exclusion. The PWS states Solar repairs and parts are excluded and will go through the Contractor to Solar for purchase. Please clarify whether Solar repair labor and parts are reimbursable under CLIN 0002 or are expected to be included in the Firm-Fixed-Price PM CLIN.
ANSWER 55: This is part of the contract agreement between the contractor and solar.
QUESTION 56: Required OEM certifications at proposal versus post-award. Please confirm whether all OEM certifications and qualified technicians identified in the PWS must be in place at the time of proposal submission, at time of award, or prior to the individual technician performing work.
ANSWER 56: At the time of awarding the contract.
QUESTION 57: Factor 1 requires qualified technicians to possess a minimum of four years of experience with the listed systems. Please clarify whether one technician must possess four years of experience with every listed system, or whether the contractor may demonstrate this requirement through a team of qualified technicians and subcontractors collectively.
ANSWER 57: Technicians are to possess a minimum of four years of experience with the listed systems.
QUESTION 58: VHA 1810 five-site requirement. Please confirm whether the requirement for experience at a minimum of five VA sites/campuses with at least three years of reporting history may be satisfied by a proposed qualified subcontractor or key technician, or whether this experience must belong directly to the prime contractor.
ANSWER 58: Prime or the subcontractor
QUESTION 59: Full-time Project Coordinator hours. Please define ‘full-time onsite’ for the Project Coordinator. Is the coordinator required onsite Monday through Friday, 8:00 AM–5:00 PM, excluding federal holidays, or is additional onsite coverage required during nights, weekends, emergencies, and scheduled shutdown work?
ANSWER 59: Onsite Monday through Friday, 8:00 AM–5:00 PM as per PWS.
QUESTION 60: Emergency response qualification. For the two-hour emergency onsite response, must the responding technician hold the specific OEM certification for the affected equipment, or may a qualified RMS technician respond initially to assess/stabilize the condition while the applicable certified specialist arrives within the stated 12-hour requirement?
ANSWER 60: Certified OEM technician
QUESTION 61: Existing equipment condition / deferred maintenance. Please provide a list of all currently known deficiencies, open corrective maintenance items, active alarms, leaking equipment, deferred maintenance and outstanding recommended repairs for the equipment included in the PWS.
ANSWER 61: This information if fluid and changes daily, the current plant status will be provided to the awardee during 1st meeting.
QUESTION 62: Historical service records. Are we to assume we are inheriting a “clean” plant or is there a backlog of repair.
ANSWER 62: This is not a “clean” plant as the plant is 30+ years old plant and repairs are needed.
QUESTION 63: Historical repair-hour usage. Please provide historical annual usage of corrective/emergency repair labor hours for the previous three contract years, including the number of hours used from the 1,500-hour allowance.
ANSWER 63: We use every hour and dollar from the previous three contracts years.
QUESTION 64: Historical CLIN 0002 spending. Please provide annual expenditures under the unforeseen repairs/parts/materials CLIN for the previous three contract years.
ANSWER 64: We use every hour and dollar from the previous three contracts years.
QUESTION 65: Scheduled shutdown windows. Please identify the anticipated annual outage/shutdown windows available for the chillers, boilers, Mercury 50 turbine, HRSG, switchgear and related equipment.
ANSWER 65: Shutdown windows are scheduled with the COR for PMs and repairs.
QUESTION 66: After-hours shutdown work. If annual PM, tube cleaning, electrical rack-out/rack-in, turbine service or other required work must be performed outside normal business hours due to plant operations, should all associated premium labor be included in the FFP CLIN?
ANSWER 66: Shutdown windows are scheduled with the COR for PMs and repairs. Normal PMs are to be schedule during normal work hours.
QUESTION 67: Crane, rigging and scaffolding responsibility. Please confirm which cranes, rigging, lifts and scaffolding will be Government-furnished versus Contractor-furnished. The PWS identifies a VA-furnished scissor lift for the Solar system but elsewhere requires the Contractor to provide cranes, rigging and scaffolding.
ANSWER 67: Contractor furnished and within the firm fixed price.
QUESTION 68: BAC manufacturer representative. The PWS states annual cooling tower PM must be performed by a BAC Manufacturer’s Representative. Please confirm whether a BAC-authorized service contractor satisfies this requirement or whether BAC factory personnel are specifically required.
ANSWER 68: Yes, by a verified BAC-authorized service contractor.
QUESTION 69: Eddy-current testing quantities in Base Year. Please confirm exactly which chillers require eddy-current testing during the Base Year beginning November 15, 2026, including whether the November 2026 due date shown for Chiller #1 must be completed immediately following contract award.
ANSWER 69: As per the PWS.
QUESTION 70: Tube brushing scope and disposal. Please confirm whether annual chiller tube brushing includes all labor, chemicals, flushing, disposal, tube-opening gaskets, end-bell gaskets, consumables and water treatment coordination.
ANSWER 70: Annual chiller tube brushing includes all labor, no water treatment
QUESTION 71: Water treatment responsibility. Please identify whether condenser-water, chilled-water, boiler-water and glycol chemical treatment is performed under another VA contract or is included in this requirement.
ANSWER 71: Chemical treatment is performed under another VA contract
QUESTION 72: Consumable definition. Please provide clarification or a list of expected PM consumables and wear items that must be included in the FFP pricing, particularly filters, oils, refrigerant dehydrators, seals, O-rings, batteries, glycol, calibration gases and fire-suppression consumables.
ANSWER 72: As per OEM for each unit or equipment.
QUESTION 73: Refrigerant responsibility. Please clarify whether refrigerant required for routine charge adjustment during PM is included in the FFP PM price and whether refrigerant required because of a corrective repair or major leak is chargeable under CLIN 0002.
ANSWER 73: See revised Schedule B.2.
QUESTION 74: Existing refrigerant inventory. Please provide current refrigerant type and approximate charge for each covered chiller and identify whether the VA maintains any onsite R-22 or R-134a refrigerant inventory for contractor use.
ANSWER 74: R22, R-135A is the current refrigerant. Per chiller is at manufacturer recommendation. If any refrigerant is onsite it can be used for our equipment.
QUESTION 75: VFD and electrical OEM PM. Where the equipment schedule states ‘OEM PM on VFD,’ please identify whether the OEM must physically perform the PM or whether an appropriately factory-trained/certified technician may perform the work.
ANSWER 75: Appropriately factory-trained/certified technician may perform the work.
QUESTION 76: High/medium-voltage testing scope. Please clarify whether the required high/medium/low-voltage scope includes NETA testing, primary injection, secondary injection, breaker maintenance, relay calibration/testing, infrared scanning, insulation resistance testing, oil testing, or only the inspections expressly shown in the task sheets.
ANSWER 76: Only the inspections expressly shown in the task sheets.
QUESTION 77: Existing service agreements / warranties. Please identify any active OEM warranties, service agreements or extended warranties for the new cooling towers, ABB drives, pumps, controls or other equipment included in the PWS, and whether those agreements remain in force after award.
ANSWER 77: No warranties on any equipment.
QUESTION 78: For informational planning purposes, does the Government have an anticipated annual funding range or historical annual expenditure for the fixed-price Testing, Inspecting, Preventative Maintenance and Emergency Call Service CLIN?
ANSWER 78: Yes, but this is not a construction contract, and the Government will not provide a rough order of magnitude.
QUESTION 79: Please provide a copy of the Site Visit Attendance Sheet.
ANSWER 79: See attached Site Visit Attendance Sheet.
QUESTION 80: Please confirm this is not a sales tax-exempt project. If sales tax-exempt, will the government provide the prime contractor with a tax-exempt certificate for use by subcontractors and vendors?
ANSWER 80: Contractors must obtain and use the Texas Sales and Use Tax Exemption Certification (Form 01‑339), issued by the Texas Comptroller of Public Accounts.
QUESTION 81: Will the VA consider extending the proposal due date to at least seven calendar days after posting the amendment containing the RFI responses to allow offerors sufficient time to obtain and incorporate revised OEM and specialty subcontractor pricing?
ANSWER 81: Proposal due date was extended in Amendment 0001.
QUESTION 82: PWS 9 requires background checks for personnel entering patient care or secure areas.
Please identify which project work areas are considered patientcare or secure areas and confirm whether access to those areas requires fingerprinting.
ANSWER 82: All work will have the COR or USO operator with them to escort them. Contractor personnel shall sign in and out of the energy center.
QUESTION 83: Please identify all pre-access requirements applicable to contractor personnel, including orientation, fingerprinting, health screening, and vaccination or masking requirements.
ANSWER 83: All work will have the COR or USO operator with them to escort them. Contractor personnel shall sign in and out of the energy center.
QUESTION 84: Other than emergency response, please identify any scheduled maintenance, testing, or outages that must be performed outside the stated normal operating hours.
ANSWER 84: None.
QUESTION 85: B.2 identifies CLIN 0002 as a $250,000 NTE allowance, while PWS 6.3.6 establishes a 1,500-hour repair labor bank. Please clarify how offerors are to price CLIN 0002.
ANSWER 85: 1,500-hour repair labor bank is firm fixed price .
QUESTION 86: Additionally, please confirm whether the 1,500 repair labor hours apply separately to each contract year.
ANSWER 86: 1,500-hour repair labor bank is a firm fixed price and included for each year.
QUESTION 87: B.2 includes emergency-call service in CLIN 0001, while PWS 6.3.6 assigns emergency-repair labor to the 1,500-hour repair bank. Please clarify whether emergency travel and diagnostic labor are included in CLIN 0001 or charged to CLIN 0002.
ANSWER 87: Diagnostic labor will come for the 1500-labor hour. See revised Schedule B.2
QUESTION 88: PWS 6.3.3 states that repair parts will be purchased by the VA, while 6.6 states that they will be purchased by the contractor. Please confirm which party is responsible for purchasing corrective and emergency repair parts.
ANSWER 88: Both. See revised Schedule B.2
QUESTION 89: The Chiller Equipment Schedule on pages 13–14 requires tube brushing, while the Annual YK Task List on page 46 states that VA staff will brush the tubes. Please confirm whether the contractor or VA is responsible for YK electric-chiller tube brushing.
ANSWER 89: The Contractor once per year, and VA for additional brushings
QUESTION 90: PWS 6.4.1 requires a technician onsite within two hours, while Evaluation Factor 1(a)(3) references 12 hours. Please confirm the required onsite response time.
ANSWER 90: See Question 47.
QUESTION 91: Project Coordinator: Please define the required onsite coverage schedule, including whether physical presence is required continuously during normal operating hours or during periods of onsite contract activity.
• Outside of above physical presence requirements, can the positions be managed remotely?
• May the required Project Coordinator be employed by a subcontractor, or must…
This is the start of the file's text. The full file is on GovTribe.