This document is a Request for Quotes (RFQ) for a construction contract issued by the Department of Veterans Affairs Network Contracting Office (NCO) located in Temple, Texas. The solicitation is for replacing condensate return units and pumps at the Garland VA Medical Center, with a project scope estimated between $100,000 and $250,000. The contract is set aside exclusively for Service-Disabled Veteran Owned Small Businesses (SDVOSB) under NAICS code 238220, with a size standard of $19 million.
The project requires furnishing labor, materials, equipment, and construction services to replace five condensate return units and pumps located in various mechanical rooms within the facility. Key requirements include providing units that can withstand high-temperature heating water ranges from 209-250 degrees, with factory-mounted control panels, high/low alarms, pressure gauges, and associated electrical and plumbing connections. The site visit is scheduled for August 18, 2025, at 1000 CST, with quote submissions due by September 12, 2025, at 1000 CDT. Quotes must be emailed to the contracting officer, Rhonda Richardson, and must include various certifications and representations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| site visit.pdf | ||
| 36C25725R0084 0001.docx | DOCX document | |
| RFIs 36C25725R0084.xlsx | XLSX spreadsheet | |
| PCRA Project 549-25-178.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C25725R0084
1. SOLICITATION NUMBER
2. TYPE OF SOLICITATION
3. DATE ISSUED
PAGE OF PAGES
4. CONTRACT NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
6. PROJECT NUMBER
7. ISSUED BY
CODE
8. ADDRESS OFFER TO
a. NAME
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014)
STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION
SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).
YES
NO
a.
Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b.
An offer guarantee is, is not required.
c.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d.
Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
36C25725R0084 X 08-12-2025
TBD
TBD
549-25-178 Department of Veterans Affairs Network Contracting Office (NCO) 17 1901 Veterans Memorial Dr. Building #171 Temple TX 76504 Department of Veterans Affairs Network Contracting Office (NCO) 17 1901 Veterans Memorial Dr. Building 171 Temple TX 76504 Rhonda Richardson rhonda.richardson5@va.gov This is a Request for Quotes:
Project Location: Garland VA Medical Center, 2300 Marie Curie Blvd, Garland, TX 75042
Description: Contractor shall furnish all necessary labor, materials, equipment, supervision, and construction services necessary for the replacement of CONDENSATE RETURN UNITS & PUMPS All work shall be performed in accordance with the Statement of Work.
Magnitude of Construction: Between $100,000 and $250,000 per FAR 36.204.
Applicable North American Industry Classification System (NAICS) code 238220, Plumbing, Heating, and Air-Conditioning Contractors with a size standard of $19M.
This requirement is a "Competitive" Offer, Set-Aside 100% Service Disabled Veteran Owned Small Business (SDVOSB) In accordance with VAAR Clause 852.219-75, and Public Law 109-461 (38 US 8127).
Per FAR 28.101-1, all offerors must submit a Bid Guarantee as part of their Quote package.
See FAR Clause 52.236-27, Alt I for site visit information. Site visit contact point of contact is Mr. Doug Person.
Mr. Person will meet all contractors in the lobby of the main entrance.
CUT OFF SUBMISSION OF RFI/QUESTIONS SHALL BE: Aug 25, 2025, @ 10:00AM CDT.
ALL RFI/QUESTIONS SHALL BE IN WORD FORMAT and emailed to Rhonda Richardson at rhonda.richardson5@va.gov
SUBMISSION OF QUOTES: All quotes shall be emailed to Rhonda Richardson at rhonda.richardson5@va.gov.
X X 52.211-10 X 10:00
CDT
09-12-2025 X
14. NAME AND ADDRESS OF OFFEROR
15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE
FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (
26. ADMINISTERED BY
27. PAYMENT WILL BE MADE BY
PHONE:
FAX:
28. NEGOTIATED AGREEMENT
29. AWARD
Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code) (Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror) (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
Department of Veterans Affairs Central Texas Veterans HCS 1901 Veterans Memorial Dr. Building 171 Temple TX 76504 This is accomplished through the Tungsten Network located at:
http://www.fsc.va.gov/einvoice.asp This is mandatory and the sole method for submitting invoices.
(877) 353-9791
(512) 460-5540
Table of Contents
| PART I - THE SCHEDULE | 1 |
| SECTION A - SOLICITATION/CONTRACT FORM | 1 |
| A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair) | 1 |
| A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK | 2 |
| A.3 PRICE/COST SCHEDULE | 5 |
| ITEM INFORMATION | 5 |
| STATEMENT OF WORK | 6 |
| INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS | 10 |
| INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS | 16 |
| 2.1 52.216-1 TYPE OF CONTRACT (APR 1984) | 16 |
| 2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) | 16 |
| 2.3 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014) | 16 |
| 2.4 52.228-1 BID GUARANTEE (SEP 1996) | 17 |
| 2.5 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE) (FEB 2021) | 18 |
| 2.6 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995) | 18 |
| 2.7 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009) | 19 |
| 2.8 VAAR 852.223-70 INSTRUCTIONS TO OFFERORS—SUSTAINABLE ACQUISITION PLAN (SEP 2019) | 19 |
| 2.9 VAAR 852.239-75 INFORMATION AND COMMUNICATION TECHNOLOGY ACCESSIBILITY NOTICE (FEB 2023) | 19 |
| 2.10 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) | 20 |
| REPRESENTATIONS AND CERTIFICATIONS | 21 |
| 3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2025) (DEVIATION FEB 2025) | 21 |
| 3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021) | 25 |
| 3.3 52.204-29 FEDERAL ACQUISITION SUPPLY CHAIN SECURITY ACT ORDERS—REPRESENTATION AND DISCLOSURES (DEC 2023) | 27 |
| GENERAL CONDITIONS | 30 |
| 4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014) | 30 |
| 4.2 52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB COVERED ENTITIES (DEC 2023) | 30 |
| 4.3 52.204-30 FEDERAL ACQUISITION SUPPLY CHAIN SECURITY ACT ORDERS—PROHIBITION (DEC 2023) | 31 |
| 4.4 52.219-28 POSTAWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JAN 2025) | 36 |
| 4.5 52.222-35 EQUAL OPPORTUNITY FOR VETERANS (JUN 2020) | 39 |
| 4.6 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUN 2020) | 39 |
| 4.7 52.223-2 REPORTING OF BIOBASED PRODUCTS UNDER SERVICE AND CONSTRUCTION CONTRACTS (MAY 2024) | 40 |
| 4.8 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022) | 40 |
| 4.9 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 45 |
| 4.10 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (JAN 2023) (DEVIATION) | 45 |
| 4.11 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (JAN 2023) (DEVIATION) | 48 |
| 4.12 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018) | 50 |
| 4.13 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019) | 51 |
| 4.14 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019) | 52 |
| 4.15 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019) ALTERNATE I (APR 2019) | 52 |
| 4.16 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020) | 53 |
| 4.17 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020) | 55 |
| 4.18 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019) | 55 |
| 4.19 VAAR 852.201-70 CONTRACTING OFFICER'S REPRESENTATIVE (DEC 2022) | 56 |
| 4.20 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018) | 57 |
| 4.21 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008) | 57 |
| 4.22 VAAR 852.232-71 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (INCLUDING NAS– CPM) (NOV 2018) | 57 |
| 4.23 VAAR 852.246-71 REJECTED GOODS (OCT 2018) | 60 |
| WAGE DETERMINATION | 63 |
A.3 PRICE/COST SCHEDULE
ITEM INFORMATION
| ITEM NUMBER |
| DESCRIPTION OF SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 1.00 |
| JB |
| __________________ |
| __________________ |
Project 549-25-178, Replace Condensate Return Units and Pumps at Garland. The contractor shall provide all supervision, labor, equipment, and materials needed to complete work IAW SOW, drawings, and specifications.
PRINCIPAL NAICS CODE: 238220 - Plumbing, Heating, and Air-Conditioning Contractors PRODUCT/SERVICE CODE: Y1DZ - Construction of Other Hospital Buildings
| 1.00 |
| EA |
| __________________ |
| __________________ |
Payment and Performance Bonds PRINCIPAL NAICS CODE: 238220 - Plumbing, Heating, and Air-Conditioning Contractors PRODUCT/SERVICE CODE: Y1DZ - Construction of Other Hospital Buildings
| GRAND TOTAL |
| __________________ |
Page 1 of Page 1 of
INSTRUCTIONS FOR CALCULATION OF SELF-PERFORMED WORK IAW “Limitations on Subcontracting” (VAAR 852.219-75)
OFFEROR’S SELF PERFORMED ESTIMATED CALCULATIONS
At the time of proposal Offeror’s are required to complete.
a) Offeror’s total proposed price: $ __________
b) Cost of Materials $ __________
c) Total excluding materials (a-b) $ __________
d) Amount projected to be paid to non-SAM listed SDVOSBs: $ __________ (not including materials)
e) Offeror’s percentage of estimated Non SAM work (d/c X 100 = %) __________%
f) Offeror’s percentage of estimated self-performed work (100 – e = %) __________%
A/E-Services. In the case of a contract for services (except construction), it will not pay more than 50% of the amount paid by the government to firms that are not SAM-listed VOSBs.
General construction. In the case of a contract for general construction, it will not pay more than 85% of the amount paid by the government to firms that are not SAM-listed SDVOSBs.
Special trade contractors. In the case of a contract for special trade contractors, it will not pay more than 75% of the amount paid by the government to firms that are not SAM-listed SDVOSBs.
STATEMENT OF WORK
REPLACE CONDENSATE RETURN UNITS & PUMPS AT GARLAND VA
549-25-178
The contractor is responsible for providing supervision, labor, parts, and materials for the replacement of the condensate return units at the VAMC Garland VA, located at 2300 Marie Curie Blvd, Garland, TX 75042. The replacements are to be carried out at the specified locations within the facility.
| 1. | CONTRACTOR RESPONSIBILITIES: The Contractor shall exercise extreme care to avoid damaging Government property such as buildings, equipment, trees, shrubs, or turf. Any damage to Government property by the Contractor shall be repaired by the Contractor to its original condition at no additional cost to the Government. The Contractor shall ensure that all materials are new, free from defects, imperfections, and asbestos free (NO ASBESTOS CONTAINING MATERIALS SHALL BE USED ON THIS PROJECT). |
| 2. | SCHEDULE OF WORK: The Contractor shall notify the Contracting Officer’s Representative (COR), prior to start of work. The Contractor shall schedule work through the COR. The Contractor shall coordinate work with COR NLT 3 days before starting work. Work shall be complete with-in 180 days of work start. Other contractors may be working in the same area performing other work. The contractor shall execute work in a manner so as not to impede other contract work. |
| 3. | HOURS OF WORK: The normal hours of work are 0700-1600 Monday through Friday. Work shall be performed during normal working hours. Work to be performed in other than normal hours shall be approved by the Contracting Officer’s Representative. |
| 4. | WORKMANSHIP: All work under this contract shall conform to the standards of these specifications. The Contractor at no additional cost to the Government shall correct work not meeting these specifications. Work shall be accomplished by mechanics skilled in the trade. |
| 5. | DAILY PROGRESS REPORTS: The Contractor shall provide daily progress report of work accomplished the previous day to COR. |
| 6. | WORKING CONDITIONS: The buildings and the surrounding site areas will be occupied, and Government operations will continue a normal, temporary, or restricted basis for the duration of the contract. The Contractor shall take all precautions to ensure that his operations are conducted in a manner so as not to interfere with the normal operation of surrounding facilities. The Contractor shall execute work in a safe manner and shall not subject personnel to unsafe conditions. The Contractor shall provide safety barricades, devices, and equipment to protect personnel and property, and repair damage caused by construction operations. Take all precautions to protect the building and its occupants during the construction period. |
| 7. | BADGES: All Contractors are required to sign in at Building (Boiler Plant). Visitor’s badges will be obtained and always worn. |
| 8. | SITE VISIT: The Contractor shall visit the site to determine the full extent of the work. Failure to inspect the site will not constitute grounds for a claim after contract award. A site visit will be scheduled through the Construction Control Officer. |
| 9. | DISPOSAL: Disposal of materials removed under this contract at an approved disposal site in accordance with all local, state, and federal laws, regulations, and guidelines are the Contractor’s sole responsibility. The contractor shall adhere to all OSHA requirements concerning removal, transporting, and disposal of the material. |
| 10. | CLEAN-UP: The Contractor shall keep the area neat and tidy and free of debris at the end of each workday. |
| 11. | TEMPORARY FACILITIES: Temporary electrical power and water may be provided by the Government at no cost to the Contractor from existing lines and sources located at the building site. The characteristics and source locations may be verified by a visit to the site. The Contractor shall provide ample temporary storage shed space for materials requiring shelter from the weather, and security and safety protection. Storage facilities shall be located in the areas of the facility designated by the Contracting Officer’s Representative. |
| 12. | SAFETY AND FIRE: All fire and safety rules and regulations are applicable; The International Plumbing Code (IPC), National Fire Protection Association NFPA. American Society of Plumbing Engineers (ASPE). The Contractor shall comply with Construction Safety Guidebook (VHA Center for Engineering & Occupational Safety & Health). Construction Safety Checklist. Contractor to follow all VA and OSHA requirement and facility policies. LO/TO procedures to be followed. A site-specific safety plan & OSHA 3071 Job Hazard Analysis/AHA Activity Hazard Analysis must be submitted by the contractor and approved before a preconstruction meeting can be scheduled. VHA-PCRA-2023-1.0 Pre-Construction Risk Assessment (PCRA). |
| 13. | PERMITS: The Contractor shall be responsible for obtaining any licenses and permits and complying with any laws, codes, and regulations applicable to the execution of this work as required Federally and by the State of Texas. |
| 14. | WARRANTEE: The contractor shall warrantee work to be free of defects and workmanship for a period of 1 year from date of acceptance. |
| 15. | STATEMENT OF WORK: The Contractor shall provide all supervision, labor, materials to perform installation for all materials and components. |
Work shall include, but is not limited to the following:
Please see specifications on condensate units: Contractor is to provide Supervision, Labor, Parts & Material on replacements of the Condensate Return Units located at the VAMC Garland VA facility. To include a total of (5) five- Condensate Return Units and Pumps sized to existing units or better. Units shall be able to withstand High Temp heating water seal ranges from 209° minimum up to 250°. Units shall come with Factory Mounted Control Panels with High Level Alarms, Discharge Pressure Gauges, Dial Thermometers, Centrifugal Pumps, Float Switches & Water Level Gauges. Electrical panels with high & low alarms. Connections from existing unit flange to flange connections no less than 3,000 psi unions connections and scheduled 80 or better related pipe. Electrical connections are required per installation from the contractor. Related plumbing shall be required. Insulation required per contractor for all related exposed areas related to installation. With associated material & related parts.
Return units are located within the building at the following locations:
BD-106 Boiler Plant 1B-169 East Tower Mechanical Room BD-131C Chiller Room BD-101 Sub-Basement BC-100 Mechanical Room
| 16. | QUALITY ASSURANCE: The Contracting Officer reserves the right to conduct any inspections or perform any tests deemed necessary at any time during the execution of the contract to determine conformance with the requirements of these specifications. |
| 17. | SUBMITTALS: Site specific and site-visit is highly encouraged for review of existing equipment, details for specialty trade equipment, project requirements, to determine accurate resource and material allocations, understanding site conditions and upcoming challenges and adapt a suitable plan, comprehend in detail of scope of work to better create the price, and overall project performance for successful completed project. |
Notes: Follow VA TIL/MS Electrical Div-26-05-11, Plumbing DIV 22-35-00, Steam Div 33-63-00. Water Utilities DIV 33-10-00, and All DIV related categories listed at https://www.cfm.va.gov/til/.
18. NARA RM LANGUAGE CLAUSE:
Contractor shall comply with all applicable records management laws and regulations, as well as National Archives and Records Administration (NARA) records policies, including but not limited to the Federal Records Act (44 U.S.C. chs. 21, 29, 31, 33), NARA regulations at 36 CFR Chapter XII Subchapter B, and those policies associated with the safeguarding of records covered by the Privacy Act of 1974 (5 U.S.C. 552a). These policies include the preservation of all records, regardless of form or characteristics, mode of transmission, or state of completion.
In accordance with 36 CFR 1222.32, all data created for Government use and delivered to, or falling under the legal control of, the Government are Federal records subject to the provisions of 44 U.S.C. chapters 21, 29, 31, and 33, the Freedom of Information Act (FOIA) (5 U.S.C. 552), as amended, and the Privacy Act of 1974 (5 U.S.C. 552a), as amended and must be managed and scheduled for disposition only as permitted by statute or regulation.
In accordance with 36 CFR 1222.32, Contractor shall maintain all records created for Government use or created in the course of performing the contract and/or delivered to, or under the legal control of the Government and must be managed in accordance with Federal law. Electronic records and associated metadata must be accompanied by sufficient technical documentation to permit understanding and use of the records and data. VA North Texas Health Care System and its contractors are responsible for preventing the alienation or unauthorized destruction of records, including all forms of mutilation. Records may not be removed from the legal custody of VA North Texas Health Care System or destroyed except for in accordance with the provisions of the agency records schedules and with the written concurrence of the Head of the Contracting Activity. Willful and unlawful destruction, damage or alienation of Federal records is subject to the fines and penalties imposed by 18 U.S.C. 2701.
In the event of any unlawful or accidental removal, defacing, alteration, or destruction of records, Contractor must report to VA North Texas Health Care System. The agency must report promptly to NARA in accordance with 36 CFR 1230.
The Contractor shall immediately notify the appropriate Contracting Officer upon discovery of any inadvertent or unauthorized disclosures of information, data, documentary materials, records or equipment. Disclosure of non-public information is limited to authorized personnel with a need-to-know as described in the [contract vehicle]. The Contractor shall ensure that the appropriate personnel, administrative, technical, and physical safeguards are established to ensure the security and confidentiality of this information, data, documentary material, records and/or equipment is properly protected. The Contractor shall not remove material from Government facilities or systems, or facilities or systems operated or maintained on the Government’s behalf, without the express written permission of the Head of the Contracting Activity. When information, data, documentary material, records and/or equipment is no longer required, it shall be returned to VA North Texas Health Care System control or the Contractor must hold it until otherwise directed. Items returned to the Government shall be hand carried, mailed, emailed, or securely electronically transmitted to the Contracting Officer or address prescribed in the [contract vehicle]. Destruction of records is EXPRESSLY PROHIBITED unless in accordance with Paragraph (4).
The Contractor is required to obtain the Contracting Officer's approval prior to engaging in any contractual relationship (sub-contractor) in support of this contract requiring the disclosure of information, documentary material and/or records generated under, or relating to, contracts. The Contractor (and any sub-contractor) is required to abide by Government and VA North Texas Health Care System guidance for protecting sensitive, proprietary information, classified, and controlled unclassified information.
The Contractor shall only use Government IT equipment for purposes specifically tied to or authorized by the contract and in accordance with VA North Texas Health Care System policy.
The Contractor shall not create or maintain any records containing any non-public VA North Texas Health Care System information that are not specifically tied to or authorized by the contract.
The Contractor shall not retain, use, sell, or disseminate copies of any deliverable that contains information covered by the Privacy Act of 1974 or that which is generally protected from public disclosure by an exemption to the Freedom of Information Act.
The VA North Texas Health Care System owns the rights to all data and records produced as part of this contract. All deliverables under the contract are the property of the U.S. Government for which VA North Texas Health Care System shall have unlimited rights to use, dispose of, or disclose such data contained therein as it determines to be in the public interest. Any Contractor rights in the data or deliverables must be identified as required by FAR 52.227-11 through FAR 52.227-20.Training. All Contractor employees assigned to this contract who create, work with, or otherwise handle records are required to take VHA-provided records management training, Talent Management System (TMS) Item #10176, Privacy and Information Security, Rules of Behavior. The Contractor is responsible for confirming training has been completed according to agency policies, including initial training and any annual or refresher training.
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS
PREPARATION OF QUOTES
To ensure that quotes submitted are responsive, vendors must follow the instructions provided here. These instructions outline the required format and detail the approach for preparing and presenting the quote package. They are designed to guarantee the submission of all necessary information. Vendors must comply with all solicitation requirements, including terms and conditions, as well as representations and certifications. The contracting officer has determined that there is a high likelihood of adequate price competition for this acquisition. Interested vendors are solely responsible for all costs associated with this solicitation, including but not limited to the preparation of quotes
1. Quotes shall be (1) submitted on the forms furnished by the Government or on copies of those forms; and (2) manually signed. The person signing a quote shall initial each erasure or change appearing on any proposal form.
2. Vendors shall submit proposed prices for ALL quote items as listed in the quote schedule. Failure to submit proposed prices for ALL quote items will result in the quote being rejected as nonresponsive without further consideration.
3. Alternate quotes will NOT be considered unless this solicitation authorizes their submission.
4. QUOTE SUBMISSION:
The following documents shall be submitted to the Contracting Officer at the due date and time listed on SF 1442. Electronic quotes transmitted through email are the only authorized form of submission under this solicitation. One (1) emailed electronic PDF document of the quote shall be submitted and received by the contracting office by time listed on page 1. The emailed electronic PDF document of the quote shall be organized as follows:
a) Standard Form 1442: Page 2 of the SF1442 shall be completed and signed by the signatory authority. All blocks under section “OFFER” on page 2 of SF1442 (Item 14 thru 20C) shall be completed.
b) Standard Form 30: Amendment of Solicitation: Vendors shall be solely responsible for monitoring Government’s website at https://sam.gov for amendments to this solicitation, if any, and acknowledge them in accordance with the requirements stipulated in this solicitation and amendments. Page 1 (Item 15A-15C) shall be completed.
c) Price Schedule: Schedule of Prices/Description shall be completed by the quoter.
d) Calculations on Self-Performed Work: Complete the Self-Performed Work Calculations and return with the quote.
e) Representations and Certifications Clause: 52.204-8 Annual Representations and Certifications: since 52.204-7 is incorporated by reference in this solicitation, paragraph (d) under clause 52.204-8 applies to this contract. Quoter shall check the box in front of paragraph (2)(i) under clause 52.204-8 and indicate any changes under paragraph (d) of clause 52.204-8. If no change has been made to the quoter’s annual representations and certifications accessed through https://sam.gov, please indicate “NONE”. Print out this clause in its entirety and submit it with the quote or you can submit your SAM.gov Reps and Certs on-line printout.
f) SAM.gov Registration: Please be advised that to be eligible for award, Vendors are required to register their businesses at https://sam.gov and complete the Reps and Certs Section. The quoter shall have an active registration in SAM at the time of quote submission otherwise the Contracting Officer shall deem the quoter’s quote non-responsive to the solicitation requirements (See FAR 52.204-7).
g) 52.204-24 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment: Print out this clause in its entirety and complete (d)(1) and (d)(2).
h) 52.219-28 Post-Award Small Business Program Representation: (Required if Applicable) If the Contractor does not have representations and certifications in SAM.gov or does not have a representation in SAM for the NAICS code applicable to this contract, the Contractor is required to print out this clause in its entirety and complete Section (h), the authorized signer must sign and date.
i) VAAR Clause 852.219-75 VA Notice of Limitations on Subcontracting: Print out this clause in its entirety and submit the completed certification portion with the quote
j) SBA VetCert Registration (evidence of SDVOSB Status): Evidence of certification from the U.S. Small Business Administration (SBA) Veteran Small Business Certification (VetCert) Program showing your firm as an eligible, visible, and certified Service-Disabled Veteran Owned Small Business (SDVOSB). To be eligible for award, Vendors are required to register their businesses at https://veterans.certify.sba.gov.
k) Vets-4212 Forms: The offeror shall affirm that they have filed the Vets-4212, Federal Contractor Veterans’ Employment Report (VETS-4212) forms for the prior fiscal year if the offeror was subject to the reporting requirements of 38 U.S.C. 4212(d) for that fiscal year. Contractors are required to submit the required annual Form VETS-4212, in all cases where the contractor or subcontractor has received an award of $150,000 or more in any fiscal year. Contracting Officers are prohibited from awarding a contract to a contractor that has not submitted a required VETS-4212 Report with respect to the preceding fiscal year if the contractor was subject to the reporting requirement of 38 U.S.C. 4212(d). Submit this report as soon as possible, if not already submitted, to avoid delays in the contract award process. For more information on this requirement and/or for completing the web-based reporting form, visit the following website https://www.dol.gov/agencies/vets/programs/vets4212. See FAR provision 52.222-38, Compliance with Veterans' Employment Reporting Requirements under Representations and Certifications and FAR clause 52.222-37, Employment Reports on Veterans.
l) Financial Responsibility: In accordance with FAR 9.104-1(a) and VAAM M809.104-1, the contracting office must ensure that prospective contractors possess adequate financial resources to perform the contract, or the ability to obtain them IAW FAR 9.104-3(a). To facilitate this determination, you shall submit any one of the four items listed below to demonstrate financial responsibility:
1. A letter of reference or other verification from your financial institution.
2. Copies of recent company audits and annual financial reports.
3. Copies of the past two years of annual tax returns.
4. A summary of your company’s past performance and delivery history i.e.: CPARS
Note: Failure to submit all aforementioned documents (a-l) shall result in a nonresponsive quote and the quote shall not be considered for evaluation.
Offerors are strongly encouraged to carefully review this solicitation and ensure all requested documents are included in their package. The government reserves the right to seek clarification or allow correction of minor informalities or irregularities in packages and may provide offerors an opportunity to cure such deficiencies or waive them if doing so is in the Government’s best interest.
5. Quotes shall be submitted electronically to the email address below by or on the due date set forth in this solicitation, Page 1, Form SF1442, Block 13:
Contracting Officer: Rhonda Richardson | Email: Rhonda.Richardson5@va.gov.
The Email Subject Line shall include the Solicitation Number and Project Title:
36C25725R0084, 549-25-178 Replace Condensate Return Units & Pumps at Garland VA It is solely the responsibility of the vendors to ensure the Government receives the quotes before or on the exact due date and time set forth in this solicitation. Emails are limited to five (5) MB.
REQUESTS FOR INFORMATION (RFIs)
To obtain clarifications and/or additional information concerning the solicitation requirements, specifications and/or drawings, or any other issue pertaining to the advertisement for quotes, submit an RFI via email to the attention of the Contracting Officer at rhonda.richardson5@va.gov The email subject line shall include the Solicitation number and project title. 36C25725R0084, 549-25-178 Replace Condensate Return Units & Pumps at Garland VA
a. RFIs related to the project technical documents must be specific identifying section, paragraph and page no. of the specifications or cite the drawing number and must be in question format.
b. RFIs related to the solicitation or other related documents shall refer to the specific provision, clause, etc. All requests for information must be submitted via email to the Contracting Officer for action no later than the date shown in Block 10 of the Standard Form 1442, Solicitation, Offer and Award. No phone or faxed inquiry will be accepted. No questions will be answered after this date unless determined to be in the best interest of the Government as deemed by the Contracting Officer.
Government’s responses to inquiries will be issued in the form of an amendment to the original solicitation and posted to the same website where this solicitation is posted: https://sam.gov. All interested vendors including those submitting inquiries are required to monitor the above website for any posted amendments and acknowledge them in accordance with the instructions provided in the amendments as well as in this solicitation.
QUOTE EVALUATION
1. All quotes submitted on time and in accordance with FAR 13.106 will be evaluated for the conformance to all requirements of this solicitation. Any quotes that fails to conform to the requirements of this solicitation will be determined non-responsive and therefore will not be considered for evaluation.
2. For all remaining quotes, prices will be evaluated as follows:
For determining the low quote conforming to the solicitation, the Government will evaluate the proposed total schedule quote items and make an award on the proposed total schedule quote items to the lowest quoter whose quote conforms to this solicitation.
BASIS FOR CONTRACT AWARD
1. Award will be made to the lowest responsible quoter whose quote conforms to this solicitation and is deemed the most advantageous to the Government, considering only price and price-related factors specified in this solicitation. In accordance with FAR 13.106-1(a)(2)(i), the award will be made on price alone.
2. Determination of Responsibility:
a) Pursuant to FAR 9.103 prescribing that purchases shall be made from, and contracts shall be awarded to, responsible prospective contractors only, the Government will perform the determination of responsibility on the apparently lowest quoter whose quote is deemed conforming to the solicitation as stated under paragraph a). The Government’s determination of responsibility will be performed in accordance with FAR 9.1 and will include but not limited to the review of all federal excluded or debarred lists from different U.S. departments, and from the SAM.gov Responsibility/Qualification (R/Q) records, FedDataCheck Contractor Responsibility Assessment (CRA) Report; Contractor Performance Assessment Reporting System (CPARS), and Electronic Subcontract Reporting System (eSRS).
b) Since this solicitation is set aside 100% for Service-Disabled Veteran-Owned Small Business (SDVOSB), the Government will refer the matter to the Small Business Administration which will decide whether to issue a Certificate of Competency if the Government deems a potential SDVOSB awardee non-responsible.
OTHER IMPORTANT QUOTEDER INFORMATION:
WAGE DETERMINATION
The wage determination is included in the solicitation and is applicable to any resultant contract. If necessary, subsequent revisions will be posted to the solicitation via amendment prior to quote opening. Revision may also be applicable prior to any contract award. Wage determinations are available at https://sam.gov/.
EXCLUSIONS
Exclusion record identifies parties excluded from receiving Federal contracts, certain subcontracts, and certain types of Federal financial and non-financial assistance and benefits. Exclusions are also referred to as “suspensions” and “debarments.” The contractor is required to check exclusions located at https://sam.gov/ for each person or business providing services under this contract. During the performance of this contract the Contractor is prohibited from using any individual or business with active exclusions.
CONTRACTOR PERFORMANCE ASSESSMENT REPORTING SYSTEM (CPARS)
1. As prescribed in Federal Acquisition Regulation (FAR) Part 42.15, the Department of Veterans Affairs (VA) evaluates contractor past performance on all construction contracts that exceed $750,000 and shares those evaluations with other Federal Government contract specialists and procurement officials. The FAR requires that the contractor be provided an opportunity to comment on past performance evaluations prior to each report closing. To fulfill this requirement VA uses an online database, CPARS.
1. Each contractor whose construction contract award is estimated to exceed $750,000 is required to register with the CPARS database at the following web address: https://www.cpars.gov/ Help in registering can be obtained by contacting Customer Support Desk at 207-438-1690. Registration should occur no later than thirty days after contract award and must be kept current should there be any change to the contractor's registered representative.
1. For contracts with a period of one year or less, the contracting officer will perform a single evaluation when the contract is complete. For contracts exceeding one year, the contracting officer will evaluate the contractor's performance annually. Interim reports will be filed each year until the last year of the contract, when the final report will be completed. The report shall be assigned in CPARS to the contractor's designated representative for comment. The contractor representative will have thirty days to submit any comments and re-assign the report to the VA contracting officer.
1. Failure to have a current registration in the CPARS database, or to re-assign the report to the VA contracting officer within those thirty days, will result in the Government's evaluation being placed on file in the database with a statement that the “contractor failed to respond.”
1. Limitation on Subcontracting:
IAW VAAR 852.219-75 each offeror will review the clause and complete the certificate included in the clause. This certificate will be complete prior to solicitation closing and submitted with the proposal, bid, or quote documents. Failure to comply with this requirement will result in removal from consideration for the award.
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
2.1 52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.
(End of Provision)
2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
(End of Provision)
2.3 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)
(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers.
(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
(End of Provision)
2.4 52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—
(1) To unsuccessful bidders as soon as practicable after the opening of bids; and
(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3M, whichever is less.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of Provision)
2.5 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE) (FEB 2021)
(a) Offerors shall obtain from each person acting as an individual surety on a bid guarantee—
(1) A pledge of assets that meets the eligibility, valuation, and security requirements described in the Federal Acquisition Regulation (FAR) 28.203–1; and
(2) Standard Form 28, Affidavit of Individual Surety.
(b) The Offeror shall include with its offer the information required at paragraph (a) of this provision within the timeframe specified in the provision at FAR 52.228–1, Bid Guarantee, or as otherwise established by the Contracting Officer.
(c) The Contracting Officer may release the security interest on the individual surety’s assets in support of a bid guarantee based upon evidence that the offer supported by the individual surety will not result in contract award.
(End of Provision)
2.6 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for— Monday, August 18, 2025 at 1000 CST
(c) Participants will meet at— Garland VA, 2300 Marie Curie Blvd, Garland, TX 75042 (End of Provision)
2.7 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009) Prime contractors are encouraged to assist service-disabled veteran-owned and veteran-owned small business potential subcontractors in obtaining bonding, when required. Mentor firms are encouraged to assist protégé firms under VA's Mentor-Protégé Program in obtaining acceptable bid, payment, and performance bonds, when required, as a prime contractor under a solicitation or contract and in obtaining any required bonds under subcontracts.
(End of Clause)
2.8 VAAR 852.223-70 INSTRUCTIONS TO OFFERORS—SUSTAINABLE ACQUISITION PLAN (SEP 2019) Offerors shall include a Sustainable Acquisition Plan in their technical proposals. The plan must describe the approach and quality assurance mechanisms for applying FAR subpart 23.1, Sustainable Acquisition Policy and other Federal laws, regulations and Executive Orders governing sustainable acquisition. The plan shall clearly identify those products and services included in the proposal.
(End of Provision)
2.9 VAAR 852.239-75 INFORMATION AND COMMUNICATION TECHNOLOGY ACCESSIBILITY NOTICE (FEB 2023)
(a) Any offeror responding to this solicitation must comply with established VA Information and Communication Technology (ICT) (formerly Electronic and Information (EIT)) accessibility standards. Information about Section 508 is available at http://www.section508.va.gov/.
(b) The Section 508 accessibility standards applicable to this solicitation are stated in the clause at 852.239–75, Information and Communication Technology Accessibility. In order to facilitate the Government’s determination whether proposed ICT supplies meet applicable Section 508 accessibility standards, offerors must submit appropriate VA Section 508 Checklists, in accordance with the checklist completion instructions. The purpose of the checklists is to assist VA acquisition and program officials in determining whether proposed ICT supplies, or information, documentation and services conform to applicable Section 508 accessibility standards. The checklists allow offerors or developers to self-evaluate their supplies and document—in detail—whether they conform to a specific Section 508 accessibility standard, and any underway remediation efforts addressing conformance issues.
(c) Respondents to this solicitation must identify any exception to Section 508 requirements. If an offeror claims its supplies or services meet applicable Section 508 accessibility standards, and it is later determined by the Government, i.e., after award of a contract or order, that supplies or services delivered do not conform to the described accessibility standards, remediation of the supplies or services to the level of conformance specified in the contract will be the responsibility of the Contractor at its expense.
(End of Provision)
2.10 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available.