- Main Building Chilled /Heating water pump VFD replacement Federal contract opportunity
- Solicitation number
- 36C25725Q0735
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C25725Q0735 0002.pdf | ||
| 36C25725Q0735.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE 7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO. 1. CONTRACT ID CODE
FACILITY CODE CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30 PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243
(Type or print) (Type or print)
(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code)
(If other than Item 6)
(Specify type of modification and authority)
(such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
1 3
0001 07-28-2025
36C257
Department of Veterans Affairs Central Texas Veterans HCS 1901 Veterans Memorial Dr. Building #171 Temple TX 76504
To all Offerors/Bidders
36C25725Q0735
07-18-2025
X
X X
X 1
The purpose of this amendment is to provide answers to questions that were received by the due time and date for questions.
///SEE CONTINUATION PAGES///
Shawn R. Reinhart Contracting Officer
36C25725Q0735 CONTINUATION PAGES
QUESTION 1: Will there be a Site Visit?
ANSWER: Yes, a site visit will be conducted on July 30, 2025 and starting at exactly 10:00 AM and lasting approximately 1-hour.
QUESTION 2: Who is the Incumbent?
ANSWER: None.
QUESTION 3: Past contract award #?
ANSWER: None.
QUESTION 4: Has the budget been approved for this contract?
ANSWER: The Government is not allowed to solicit with funds being available.
QUESTION 5: Is there a scheduled site visit day, date and time? Apologize if I overlooked it.
ANSWER: See answer to question 1 above.
QUESTION 6: Do you have the pricing template in an Excel, pdf or another form to submit back in a clean format?
ANSWER: No. It is upon the offeror to create their own pricing template as long as it follows the information in Addendum FAR 52.212-1, under “Volume III: Price”.
QUESTION 7: Can the VA provide a picture of each of the 10 current VFDs and the surrounding area?
ANSWER: Photography will be allowed during the site visit.
QUESTION 8: What is specifically required for the controls scope with the new drives?
ANSWER: It was requested that the new VFDs be ABB ACH580 VFDs. Nothing more is required.
QUESTION 9: What is the extent of assistance to be provided by the VA controls shop in programming the BAS?
ANSWER: The Controls shop can assist with addressing and settings to commission the new VFDs.
QUESTION 10: What is required of the contractor and how is the existing VFD tied into the controls. I'm assuming we'll have to disconnect and reconnect some hard-wired points, start/stop, speed signal, alarm or fault, etc.
ANSWER: The controls are currently a single twisted wire/Pair that may be daisy chained from device to device. This wire shall be disconnected from the current VFD and connected to the new ABB VFD, then properly programmed to communicate with the Siemens BAS.
QUESTION 11: Is there existing communication wire on the old drives? If not, is any communication wiring needed or does the drive just need to be capable of it for tying in at a later time?
ANSWER: See answer to question 10 above.
QUESTION 12: Will each new VFD require extension of electrical wiring?
ANSWER: It depends on the size of the new VFD. This information can be seen firsthand during the walkthrough / Site visit conducted on July 30 starting at 10 AM.
QUESTION 13: Can the VA provide an estimate of the extension required for each VFD?
ANSWER: See answer to question 12 above.
QUESTION 14: In executing this project, can one superintendent fulfill the supervision, safety, and QAQC roles?
ANSWER: Yes.
QUESTION 15: Are contractors required to issue a contract specific QA / QC Plan?
ANSWER: Yes.
QUESTION 16: Are contractors required to issue a contract specific Safety Plan?
ANSWER: Yes.
QUESTION 17: Is this project tax exempt?
ANSWER: Any project performed on a federal installation is exempt from state tax.