Attachment 1- RFI Responses.pdf
PDF 41 KB Posted
- Attached to
- Y1DA--Fix Restroom Partition Federal contract opportunity
- Solicitation number
- 36C25725Q0527
About this file
This document is a Request for Information (RFI) response for Solicitation 36C25725Q0527, a VA project to fix restroom partitions at the San Antonio VA facility. The RFI addresses seven key questions from potential contractors, covering project details such as hazardous material handling, infection control requirements (ICRA), subcontractor needs, work hours, project delivery method, fire watch requirements, and fire suppression system status. The responses clarify that no asbestos abatement or lead/mold removal is needed, work can be performed during normal hours, no proprietary subcontractors are required, the project is not a design-build effort, no 24-hour fire watch is necessary, and the existing fire suppression system will remain in place.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C25725Q0527 0002.docx | DOCX document | |
| 36C25725Q0527 0001.docx | DOCX document | |
| Site Visit Sign In.pdf | ||
| Attachment 2 Partition drawing J101.pdf | ||
| Attachment 1 Scope of Work 04-29-2025.pdf | ||
| Attachment 4 Self Performance Calculations.docx | DOCX document | |
| Attachment 3 Bexar County Wage Determination.pdf | ||
| 36C25725Q0527_1.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C25725Q0527 - San Antonio VA - Fix Restroom Partitions – RFI’s
1. Are we to dispose/abate of any asbestos, lead, mold or other hazardous material as part of this project? If so, provide appropriate hazardous material site survey report.
Answer: No asbestos abatement, lead or mold removal is needed for this project.
2. What will the ICRA level be for this project?
Answer: Plastic Sticky mat required at entrance/exit. Contain all trash/debris and remove daily. Vacuum sheetrock dust as needed. Plastic zip door at entrance/exit to Restroom.
3. Are there any required/proprietary subcontractors the general contractor is to hire associated with this project?
Answer: No proprietary contractors needed
4. Will all work associated with this project able to be performed during regular working hours?
Answer: All work can be performed during normal work hours.
5. It is our understanding that the Solicitation is a negotiated Bid (RFP) design-bid-build project with the Government's AE being responsible for the design portion (providing a full and complete set of Specifications and Plans) and the successful offeror being responsible for bidding and building the project based on the Specifications and Plans provided by the Government's AE. Put another way, the successful offeror will not be required to perform any design-build services as part of the contract - correct?
Answer: No design bid build is required.
6. Are we required to provide a 24 hour/day on-site fire watch during demolition?
Answer: No
7. Please confirm
1) Fire Suppression to be left in place as-is.
Answer: Yes
2) Parts of the fire suppression are to be replaced. If so, please specify what is to be replaced.
Answer: This project does not involve fire suppression work.
3) The entire fire suppression system is to be removed and replaced throughout the entire construction space.
Answer: Not Applicable
File details come from the government source that posted it. Updated .