36C25724Q0720 0001.docx
DOCX document 22 KB Posted
- Solicitation number
- 36C25724Q0720
About this file
This document is an amendment (Amendment 0001) to Solicitation 36C25724Q0720 for the repair of the roof on Building 202 at the Olin E. Teague VA Medical Center in Temple, TX. The key details are:
The amendment is issued to post RFI responses, offer a second site visit, and extend the response due date to August 8, 2024 at 10:00 AM CST. The solicitation requires the contractor to be responsible for providing labor, materials, and equipment to repair roof leaks, rusted areas, and replace gutters on the center section of Building 202. The project involves approximately 15,000 square feet of roof repair, and the contractor must warrant the repairs for 1 year. Attachments include roof drawings, specifications, and additional details about the requirements. Prospective contractors are instructed to submit proposals in accordance with the revised solicitation details.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 36C257 Department Of Veterans Affairs Network Contracting Office 17 5441 Babcock Road Ste. 302 San Antonio
TX
78240 36C257 Department Of Veterans Affairs Network Contracting Office 17 5441 Babcock Road Ste. 302 San Antonio
TX
78240 To all Offerors/Bidders
36C25724Q0720 06-12-2024
X X X
8 August 2024, 10:00 AM CST X Amendment 0001 is issued to post RFI responses and post attachments to RFI Questions.
Amendment 0001 is also issued to offer a second site visit on 25 July 2024 at 9:00am at Building 53 Room 115.
at Olin E. Teague VA Medical Center, 1901 Veterans Memorial Dr. Temple, TX 76504
Amendment 0001 is also issued to extend the response due date until 8 August 2024, 10:00 AM CST.
Tailor Brown RFI’s Repair Building 202 Temple, TX
1. Item # 1 under “Gravel Roof Areas:” "In order to properly perform the IR scan and make appropriate repairs, we need to cut a core sample. Will core sample results be shared with the bidding pool, or will we be required to make a return trip to cut our own cores?" Prints are provided in lieu of core sample.
2. Item #4 under “Gravel Roof Areas:” In order to replace “failing previous repairs,” will a mapping of those previously repaired areas be provided or will some other method of identifying those areas be provided? NO. Per SOW the roof repair is for 15,000 square feet of roof. It is the contractor’s responsibility to locate and repair any leaks up to 15,000 sq. ft. of leaks. All leak repairs are to be completed by industry standards. Provide square foot of repaired area per week.
3. Item #7 under "Metal Roof Areas" says to "seal stone coping joints..." but I did not observe any stone coping on the metal roof structure, nor was Lee Richards able to identify where they were. Please clarify where these conditions exist, or if this should be scratched from the Scope of Work. Remove “seal stone coping joints” from SOW.
4. Lightning Protection System: In order to properly seal all the coping with a 3-course coating, the lightning protection system should be removed. If it is going to be reinstalled, a certified lightning protection company must install and re-certify the system. Please provide directions as to whether the system should be removed and reinstalled or scrapped. Yes, remove reinstall and certify.
5. Lightning Protection System: If the decision is made to remove, reinstall and re-certify the lightning protection system, should an estimate for this work be included in our Proposal as a Scope of Work change or will that work be covered under a separate solicitation? This is part of this contract.
6. Infection Control Risk Assessment (ICRA) Requirements: The SOW states: “All work shall be done according to the Infection Control Risk Assessment (ICRA) specified for the respective areas where work is performed.” Will the ICRA Requirements be posted in or near the work areas or will some other method of notification be used? ICRA will be posted as required.
7. Warranty Requirements: Please clarify expectation of outcomes and responsibility of contractor with regards to warranty. Point-of-entry for leaks on BURs (built-up roofs) are some of the most difficult roof leaks to identify. The IR scan and prescribed leaks will almost certainly help address a number of the current leaks, but it should be expected that not all leaks will be addressed in the initial round of work, and call-backs should be anticipated. Does the required 1-year warranty only apply to the actual work completed, or is it expected that the contractor will for 1 year assume responsibility for all prior leaks, and be required to do additional work, even if beyond the scope of the original contract, up through the 1-year mark? The warranty will apply to the 15,000 sq. ft. of leaks that are repaired per contract.
8. Past Performance Requirements: My Firm is a certified SDVOSB. As such, it is my plan to be the Prime Contractor for this project with responsibility for high-level contracts and project management operations. My Subcontractor is an experienced Roofing Company with verifiable past performance on government, state and local commercial projects of similar type, scope, size and complexity of the roofing repair requirements of the solicitation. Is it permissible to use only the Subcontractor’s past performance for our proposal? Past performance is from the General Contractor.
9. Quote Requirements: The Quote requires 2 emails of no more than 5MB each, 1 email for Price and 1 email for technical/past performance. Is the expectation to include Reps and Certs as an attachment to the email with the Technical/Past Performance information? Send all information per Contracting requirements.
10. Can you provide a copy of the roof plan and cut throughs from the architectural drawings? See attached.
11. The entire gravel roof was hit by 3-4 inch hail, do you all want use to warranty our repairs only or the entire roof? If we only need to warranty our repairs, how would billing for non warrantied roof repairs look like? Warranty is to cover repaired areas.
12. Do we need to detach and reset lighting rods or can we coat over them? Detach and reset lighting rods, no coating over lighting system.
13. When we are caulking the joints, do we need to caulk run all the way to the top of the joint underneath the coping metal or can we go as far as possible up the joint without bending the metal? No bending of metal.
14. Would you all accept an alternate if we could provide a 10 or 20 year solution that came with a manufacturer's warranty on the gravel roof system and stayed within the projects budget? Must meet the contract requirement.
15. Can you provide the contact information for the company that specified the scope for this RFP so we can discuss alternative options that can be installed within budget? No. Must meet the contract requirement.
16. What materials are to be used on the “expansion joints”. Stated in Statement of Work.
17. Provide asbuilts for the Building 202 or drawings. See attached.
18. Provide specifications. See SOW.
19. Provide is this a repair or replace project? Bidding process needs to be fair and for all to bid apples to apples. See SOW.
20. Can we have a satellite image or Eagleview report for the site? Contractor responsibility.
21. Is a bid bond required with our proposal? Per contract.
22. What are the badging/paperwork/legal requirements of our site workers? Contractor owned badge, and VA badges are required and will be provided by the VA.
23. To confirm, we need to have one OSHA 30 worker and all other workers onsite need to be OSHA 10? Per SOW.
24. How do you require us to store materials on site? A laydown yard will be provided. It is the Contractor’s responsibility to store and secure all materials.
25. Bldg 202 has a lightening arrest (bonding) system that will have to be manipulated in order to replace the roof. The solicitation does not reference the bonding system.
0. Does the VA require any specific work to the bonding system? If so, please describe.
0. Does the bonding system need to be re-certified after the roof repair is completed?
Contractor’s responsibility to remove and reinstall. With certification.
See attached document: Attachment 1_S06 RFIs Building Roof 202 Temple_TX _002.
See attached document: Attachment 2_S11 building 202 roof.
See attached document: Attachment 3_S12 building 202 roof.
See attached document: Attachment 4 1-3 Building 202 roof.
See attached document: Attachment 5_5-2 Building 202 roof.
See attached document: Attachment 6_5-3 Building 202 roof.
See attached document: Attachment 7_2-11 Building 202 roof.
See attached document: Attachment 8_5-4 Building 202 roof.
See attached document: Attachment 9_6-3 Building 202 roof.
See attached document: Attachment 10_7-1 Building 202 roof.
See attached document: Attachment 11_7-2 Building 202 roof.
See attached document: Attachment 12_7-3 Building 202 roof.
See attached document: Attachment 13_8-4 Building 202 roof.
See attached document: Attachment 14_8-5 Building 202 roof.
See attached document: Attachment 15_8-6 Building 202 roof.
See attached document: Attachment 16_8-7 Building 202 roof.
See attached document: Attachment 17_10-10 Building 202 roof.
File details come from the government source that posted it. Updated .