RFIsto RFQ36C25724Q0421.docx

DOCX document 14 KB Posted

Attached to
Z2DA--36C25724Q0421-Repair perimeter fence (VA-24-00054907)
Solicitation number
36C25724Q0421
Issued by

About this file

This document is a Request for Information (RFI) for solicitation 36C25724Q0421 to repair the perimeter fence at the Amarillo VA Medical Center. The RFI poses several questions to potential contractors, including whether the Statement of Work (SOW) requires just one column, if the VA will allow replacing only the damaged portion of the mow strip instead of the full 41 feet, if contractors can park and set up in the grass between the fence and road, if temporary fencing is required, and if the VA will provide specifications for a pier beneath the stone column. The related federal contract opportunity is for the actual repair of the perimeter fence, with an agency of the Department of Veterans Affairs, Veterans Health Administration, Veterans Integrated Service Network 17.

View the file

Other files

File Type Posted
36C25724Q0421 0002.docx DOCX document
AnswersToRFIsto RFQ36C25724Q0421.docx DOCX document
36C25724Q0421 0001.docx DOCX document
perimeter fence pre bid sign in sheet.pdf PDF
ColumnSupport-PerimeterFenceRepair 02.jpg JPG image
POST 3-perimeterfence repair.jpg JPG image
MowStrip1-Perimeter Fence Repairs.jpg JPG image
ColumnSupport-PerimeterFenceRepair.jpg JPG image
MowStrip2-Perimeter Fence Repair 02.jpg JPG image
Post2 PerimeterFenceRepairs.jpg JPG image
Post1-Perimeter Fence Repair.jpg JPG image
36C25724Q0421.docx DOCX document
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFQ # 36C25724Q0421 – CONST. REPAIR PERIMETER FENCING – Amarillo vamc

RFI’S

1. Is the SOW requiring just one column?

2. The statement of work requires 41' of mow strip to be demoed and replaced. However, only a portion of the mow strip has been damaged. There will be significant savings to the VA if you will allow only the portion that is damaged to be cut out and replaced. Will the VA allow this and if so, how many linear feet should contractors bid for replacement?

3. Are we allowed to park and set up our work area in the grass between the fence and the road?

4. Is temporary construction fencing required during the project?

5. For long-term stability, the stone column should have a pier set beneath it. Will the VA provide a pier detail or specifications for the column?