This document is a solicitation for leveling approximately 400 square feet of concrete sidewalk and ramp at three buildings on the campus of the Amarillo Veterans Affairs Medical Center in Amarillo, Texas. The work includes lifting and repairing existing concrete to stabilize levels and drainage, as well as sealing joints and cracks. Offerors must provide pricing to perform the work by November 1, 2023 using domestic materials, along with past performance evaluations, safety records, and certifications. Submissions are due by September 19, 2023. The award will be a firm-fixed-price contract to a certified Service-Disabled Veteran-Owned Small Business. The successful offeror must meet limitations on subcontracting requirements and provide performance and payment bonds.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25723Q1255 0001.docx | DOCX document | |
| 504-23-007 drawings WORK AREA- CONCRETE LEVEL-Model 02.pdf | ||
| SPEC for level concrete 5-26-2023.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. SOLICITATION NUMBER
2. TYPE OF SOLICITATION
3. DATE ISSUED
PAGE OF PAGES
4. CONTRACT NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
6. PROJECT NUMBER
7. ISSUED BY
CODE
8. ADDRESS OFFER TO
a. NAME
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014)
STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION
SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).
YES
NO
a.
Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b.
An offer guarantee is, is not required.
c.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d.
Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
36C25723Q1255 X 08-15-2023 504-23-007 36C257 Department Of Veterans Affairs Network Contracting Office 17 1901 Veterans Memorial Drive Temple
TX
76504 Department of Veterans Affairs
NCO 17
Contract Specialist Bobby Reveles 1901 Veterans Memorial Drive Temple
TX
76504 Bobby Reveles (254)899-6042 Project Number : 504-23-007 Project Title : Level Sidewalks of Buildings 33, 9, & Dock of Building 28 Project Location : Thomas E. Creek VA Medical Center, 6010 Amarillo Blvd. Amarillo Texas 79106.
Award is subject to the availability of funds.
Award of a contract as a result of this solicitation is contingent upon the availability of appropriated funds from which payment of this contract may be made.
There shall be no legal liability on the part of the Government for contract purposes until funds are made available to The Contracting Officer will confirm availability of funds prior to award of a contract.
This is a 100% set aside for Service Disabled Veteran Owned Small Business.
Magnitude of Construction: IAW FAR 36.204 is less than $25,000
Performance/Payment Bonds are needed for any construction contract exceeding $35,000
X 52.211-10 X
5:00 PM
MDT
09-22-2023 X
14. NAME AND ADDRESS OF OFFEROR
15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE
FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (
26. ADMINISTERED BY
27. PAYMENT WILL BE MADE BY
PHONE:
FAX:
28. NEGOTIATED AGREEMENT
29. AWARD
Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code) (Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror) (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
36C671 Department Of Veterans Affairs Network Contracting Office 17 1901 Veterans Memorial Drive Temple
TX
76504 This is accomplished through the Tungsten Network located at:
http://www.fsc.va.gov/einvoice.asp This is mandatory and the sole method for submitting invoices.
(877) 353-9791
(512) 460-5540
Table of Contents
| PART I - THE SCHEDULE | 1 |
| SECTION A - SOLICITATION/CONTRACT FORM | 1 |
| A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair) | 1 |
| A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK | 2 |
| A.3 PRICE/COST SCHEDULE | 5 |
| ITEM INFORMATION | 5 |
| INSTRUCTIONS FOR CALCULATION OF SELF-PERFORMED WORK IAW “Limitations on | 5 |
| OSHA -EMR Requirement | 6 |
| INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS | 13 |
| 2.1 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) | 16 |
| 2.2 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014) | 16 |
| 2.3 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995) | 17 |
| 2.4 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) | 17 |
| REPRESENTATIONS AND CERTIFICATIONS | 19 |
| 3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2023) | 19 |
| 3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021) | 23 |
| GENERAL CONDITIONS | 26 |
| 4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014) | 26 |
| 4.2 52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB AND OTHER COVERED ENTITIES (NOV 2021) | 26 |
| 4.3 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) | 27 |
| 4.4 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (MAR 2023) | 27 |
| 4.5 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022) | 30 |
| 4.6 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 35 |
| 4.7 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (JAN 2023) (DEVIATION) | 37 |
| 4.8 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018) | 39 |
| 4.9 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019) | 41 |
| 4.10 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019) | 42 |
| 4.11 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019) | 42 |
| 4.12 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020) | 42 |
| 4.13 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020) | 44 |
| 4.14 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019) | 44 |
| General Decision Number: TX20230265 04/14/2023 | 45 |
A.3 PRICE/COST SCHEDULE
ITEM INFORMATION
| ITEM NUMBER |
| DESCRIPTION OF SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 1.00 |
| JB |
| __________________ |
| __________________ |
Provide all labor, materials, supplies, tools, equipment, supervision, and construction services necessary for the construction of this project. All work shall be done as per specifications, drawings and to manufactures instructions. The Contractor shall ensure that all materials are new, free from defects, imperfections and asbestos free (NO ASBESTOS CONTAINING MATERIALS SHALL BE USED ON THIS PROJECT).
Work shall Contract Period: Base POP Begin: 10-02-2023 POP End: 11-01-2023
| 1.00 |
| JB |
| __________________ |
| __________________ |
PERFORMANCE AND PAYMENT BOND TOTAL PROJECT DURATION: 30 Calendar days to complete work from issuance of the Notice to Proceed Contract Period: Base POP Begin: 10-02-2023 POP End: 11-01-2023
| GRAND TOTAL |
| __________________ |
INSTRUCTIONS FOR CALCULATION OF SELF-PERFORMED WORK IAW “Limitations on Subcontracting” (VAAR 852.219-75)
OFFEROR’S SELF PERFORMED ESTIMATED CALCULATIONS
At the time of proposal Offeror’s are required to complete.
a) Offeror’s total proposed price: $ __________
b) Cost of Materials $ __________
c) Total excluding materials (a-b) $ __________
d) Amount projected to be paid to non-SAM listed SDVOSBs: $ __________ (not including materials)
e) Offeror’s percentage of estimated Non SAM work (d/c X 100 = %) __________%
f) Offeror’s percentage of estimated self-performed work (100 – e = %) __________%
A/E-Services. In the case of a contract for services (except construction), it will not pay more than 50% of the amount paid by the government to it to firms that are not vetcert-listed VOSBs.
General construction. In the case of a contract for general construction, it will not pay more than 85% of the amount paid by the government to it to firms that are not VetCert -listed SDVOSBs.
Special trade contractors. In the case of a contract for special trade contractors, it will not pay more than 75% of the amount paid by the government to it to firms that are not VetCert -listed SDVOSBs.
OSHA -EMR Requirement
OSHA or EPA Violation(s):
(1) Offerors shall provide Summary of Work-Related Injuries and Illnesses, affirming that the
(2) Offeror has no more than three serious, or one repeat, or one willful OSHA or EPA violation(s) in the past 3 years Experience Modification Rate (EMR):
(1) Offerors shall provide documentation to show that the offeror has an Experience Modification Rate (EMR) of equal to or less than 1.0.
STATEMENT OF WORK
LEVEL SIDEWALKS BUILDING 33,9, & DOCK OF 28
Project Number 504-23-007
1.PROJECT OVERVIEW
PURPOSE: The Department of Veteran Affairs (VA) is looking to hire a contractor to level approximately 400 square feet of concrete sidewalk and ramp in front of the building 33, building 9 and at the loading dock of building 28 at the Thomas E. Creek VA Medical Center, 6010 Amarillo Blvd. West, Amarillo, Texas 79106. This project will lift and repair the designated concrete in areas to stabilize the level to the adjacent concrete appropriately with joint sealants to provide walking and wheelchair accessibility as well as the drainage of water away from the buildings. The project will be done in accordance with the prepared drawings and specifications.
2.SCOPE:
2.1 GENERAL:
Provide all labor, materials, supplies, tools, equipment, supervision, and construction services necessary for the construction of this project. All work shall be done as per specifications, drawings and to manufactures instructions. The Contractor shall ensure that all materials are new, free from defects, imperfections and asbestos free (NO ASBESTOS CONTAINING MATERIALS SHALL BE USED ON THIS PROJECT).
Work shall include:
A pre-bidding site visit is recommended. Site visit will be coordinated by the Contracting Officer (CO) and the Contracting Officer Representative (COR). A pre-construction meeting is required and regular coordination meetings during construction work may be scheduled.
All numbers and measurements are for reference only. Contractor shall verify all amounts and measurements. Any discrepancy in the amounts provided and or any condition affecting work shall be brought to the attention of the VA COR before proceeding with the work.
All work as shown in the drawings and specs are the responsibility of the general contractor. Any subdivision of this work to subcontractors remains the sole responsibility of the general contractor.
Applicable permits, installation, Quality Control and testing, are the responsibility of the general contractors.
Normal hours of operation for VA sites are 8:00AM to 4:30 PM CST Monday through Friday except for Federal Holidays. Work to be performed in other than normal hours shall be approved by the COR.
The Contractor shall notify the COR, prior to start of work. The Contractor shall schedule work through the COR. The Contractor shall coordinate work with COR no later than 3 days before starting work. Work shall be completed with-in 30 calendar days of start date.
All work under this contract shall conform to the standards of these specifications. The Contractor at no additional cost to the Government shall correct work not meeting these specifications. Work shall be accomplished by mechanics skilled in the trade. The Contractor shall provide on a daily basis and no later than 9:00 AM, a progress report of work accomplished the previous day and projected work to be completed that day to COR.
2.2 STATEMENT OF WORK
The work will include all labor, material, equipment, and supervision to perform the required work on this project. This work requires the Contractor to repair the existing concrete steps by using foams to level sinking concretes to the appropriate position for pedestrians at front of building 33, which is next to the parking lot N. All areas and lengths are approximate. The intended area is approximately 150 square feet. The Contractor must seal all cracks whose minimum width is 1/16 inch regardless of the length or depth, and joints between the slabs with polyurethane sealant, or equivalent materials. The estimated length of seal joints is about 66 linear feet to be sealed. Moreover, the same work is required for a 100-square-foot area at the dock of building 28 with the seal joints of 60 linear feet. The Contractor shall ensure that there is smooth transition between intendedly repaired concretes with the adjacent ones to provide access for walkers and direct water flow, and the running slope of the walkway is 2% maximum according to the VA Barrier Free Design Standard.
In addition, the Contractor must use polyurethane foams, or equivalent materials to lift the ramp and sidewalk areas to drain water away from the building 9 while the reparation shall give appropriate and comfortable accessibility for pedestrians and wheelchairs with estimated area of 150 square feet in addition to seal 140-linear-foot sealant joints. The running slope of the ramp shall be 1% minimum and 5% maximum while the sidewalk’s maximum slope is 2%. The Contractor must ensure the smooth connection between repaired concretes and other ones with appropriate leveling and polyurethane sealants, or equivalent materials at joints, and cracks.
The work shall not interfere with normal hospital operation. The deliverable shall be leveled concretes to drain water off outward of the buildings, installing sealants at joints and filling sealant at least 1-inch depth for the cracks, and providing smooth transition between the slabs for comfortable accessibility for pedestrians and wheelchairs for purpose of repairing approximately combined 400-square-foot concrete areas and 266-linear-foot joints. Furthermore, the Contractor shall use sealants whose colors match with the color of the existing sealant joints. For the cracks, the Contractor shall apply the sealants that match the color of the adjacent concretes.
2.3 DESCRIPTION OF WORK
A. Existing Conditions
a. Before disabling any system(s), the contractor shall coordinate with COR at least 3working days in advance. Disablement shall be approved by VA-COR prior to starting work. Contractor shall be responsible for relocating and temporary installing all utilities and controls, including, but not limited to, telephone, data, electrical, med/gas, etc. It is the contractor’s responsibility to immediately repair any tampered with system at no additional cost to the government.
b. The buildings and the surrounding site areas will be occupied, and Government operations will continue a normal, temporary, or restricted basis for the duration of the contract. The Contractor shall take all precautions to ensure that his operations are conducted in a manner so as not to interfere with the normal operation of surrounding facilities. The Contractor shall execute work in a safe manner and shall not subject personnel to unsafe conditions. The Contractor shall provide safety barricades, devices, and equipment to protect personnel and property and repair damage caused by construction operations. Take all precautions to protect the building, equipment, and occupants during the construction period.
c. Contractor will coordinate all work with existing work to remain and existing conditions.
d. Contractor shall be responsible for complying with all the construction documents and applicable Department of Veterans Affairs Master Specifications as part of this project.
e. Contractor shall comply with all applicable city, county, state, and federal regulations /codes and applicable OSHA standards. Construction shall also comply with Interim Life Safety Measured delineated in the specifications. Including but not limited to the following:
1.NEC
2.NFPA
3.ADA
3.Life Safety Code 4.OSHA Standards 5.EPA regulations
6.ASME
7.ASPE
8.ASTM
9.National and Local Building Codes 10.Others as appliable
f. Contractor will be allowed to park on the VA campus in designated areas.
g. Demolition and renovation shall take place with minimal disruption to adjacent areas.
h. Demolition debris shall be recycled to the best ability of the contractor. Reports of weight and deposition of all waste are to accompany the monthly progress payments.
i. Disposal of materials removed under this contract at an approved disposal site in accordance with all local, state, and federal laws, regulations, and guidelines are the Contractor’s sole responsibility. No disposal in VA property is permitted. The contractor shall adhere to all OSHA and DOT requirements concerning removal, transporting, and disposal of the material.
j. The contractor shall immediately repair any damage to the adjacent facilities/equipment and will return the area to the government within a condition like that before the construction started. This work is the contractor’s responsibility to replace at no additional cost to the government.
k. The contractor shall protect adjacent equipment from construction damage and particulate.
l. All work shall be in accordance with VA specifications. All costs shall be included in the base bid. All work shall be coordinated with the VA prior to any demolition work being performed.
B. Additional Requirements
a. Housekeeping - Accumulation of trash, paper, wood shavings, sawdust, excelsior, boxes and other packing materials will be cleaned up as often as necessary and at the end of each workday.
b. Fire Watch - Provide fire watch for impairments more than 4 hours in a 24-hour period. Request interruptions in accordance with Article, OPERATIONS AND STORAGE AREAS, and coordinate with COR and facility safety officer. All existing or temporary fire protection systems (fire alarms, sprinklers) located in construction areas shall be tested as coordinated with the medical center. Parameters for the testing and results of any tests performed shall be recorded by the medical center and copies provided to the COR.
c. Smoking is strictly prohibited in all facilities, and on campus.
d. Security – Contractors will always wear security badge in plain sight above the waist. Contractors found without a badge will be immediately removed from VA property by VA Police.
e. Parking – Contractor vehicles found parked in non-designated areas will be issued a United States District Court Violation Notice and immediately removed and banned from VA property.
f. OSHA 10 & 30 -Hour Training Course – All construction workers are required to have the OSHA 10-hour Construction Safety training certification. The construction safety manager and/or superintendent shall have the 30-hour Construction Safety course certification. Proof of certification shall be on site at all times.
g. All construction and installation work shall comply with VA specifications for material and workmanship, NEC, NFPA and all applicable city, county, state, and federal regulations and codes and OSHA standards. Refer construction drawings and specs for requirements.
h. All incidental work associated with the installation and construction works in the exterior and interior of the building shall be included in the base bid.
i. Conduct work as to interfere as least as possible with facility operations. All shutdown shall be approved by VA. All coordination for utilities shutdown shall be coordinated at least 72 hours prior to event with COR. For major utility system shutdowns, coordination shall be done at least 2 weeks in advance.
j. The Contracting Officer reserves the right to conduct any inspections or perform any tests deemed necessary at any time during the execution of the contract to determine conformance with the requirements of theses specifications.
k. SUBMITTALS: Contractor shall provide with their quote manufacturer’s descriptive literature for items mentioned in STATEMENT OF WORK with Data Sheets and/or Shop Drawings.
2.4 OTHER DELIVERABLES
A. Period of Performance: 30 Calendar days after Notice to Proceed, Inclusive of 5-day cure in environmental condition, prior to VA inspection, and any rework as applicable.
B. Performance and Payment bonds: Due 3 Calendar days after Notice of Award.
C. Proof of Insurance: Due 3 Calendar days after Notice of Award.
D. Submittals CD: As part of the closeout documentation, the contractor shall provide the COR, 1 CD containing all the approved submittals.
E. Warranty: Contractor shall provide a minimum one (1) certified year warranty, unless specified otherwise in the specs, from both the manufacturer and installer including parts and labor to include normal, premium or holidays hours. The Warranty period shall start on the date of Final Payment issued in IPPS from VA.
2.5 ACCEPTANCE
A. For the purposes of Warranty and payment for the work performed at a location, government “Acceptance” will be provided by the VA upon the completion of all the following:
B. The Contractor has all work completed, inclusive of cure and rework.
C. The Contractor has provided electronic closure out package including the following: Contractor certified executed Quality Control Inspection documentation (electronic pdf format), approved submittals, Certified Warranty Letter.
2.6 CONFIDENTIALITY AND NONDISCLOSURE
A. The preliminary and final deliverables and all associated working papers, application source code, and other material deemed relevant by the VA which has been generated by the contractor in the performance of this Order are the exclusive property of the U.S. Government and shall be submitted to the VA-COR at the conclusion of the contract.
B. The Contracting Officer will be the sole authorized official to release in writing, any data, the draft deliverables, the final deliverables, or any other written or printed materials pertaining to this contract. No information shall be released by the contractor. Any request for information relating to this contract presented to the contractor shall be submitted to the CO for response.
C. Press releases, marketing material or any other printed or electronic documentation related to this project, shall not be publicized without the written approval of the CO.
D. To the extent that the work under this contract requires that the contractor be given access to proprietary business, technical or financial information belonging to the Government or other companies, the contractor shall treat such information as proprietary business sensitive and agrees not to appropriate such information to its own use or to disclose such information to third parties unless specifically authorized by the CO in writing. A mutually agreed to agreement for exchange of sensitive information or nondisclosure agreement may be required.
E. General Requirements for Privacy Information: • Information Systems Officer, Information Protection: The contractor will not have access to VA Desktop computers, nor will they have access to online resources belonging to the government while conducting services.
Privacy Officer: The contractor will not have access to Patient Health Information (PHI) nor will they have the capability of accessing patient information during the services provided to the VA Records Manager: There will be no patient records created, maintained, used or dispositioned with this contract; regardless of format [paper, electronic, etc.] or mode of transmission [e-mail, fax, etc.].
END OF STATEMENT OF WORK
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
PART I - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS
PART I/SECTION A – REQUEST FOR QUOTE
This is a Request for Quote in accordance with FAR Part 13. Potential offerors must follow all instructions to be compliant with the solicitation.
It is the responsibility of the offeror to verify that their offer is complete. The offeror is responsible for submitting all required forms and documents with the offer.
The Government will award a single contract resulting from this solicitation to a responsible SDVOSB offeror whose offer conforming to the solicitation will be most advantageous to the Government based on Past Performance and Price.
I.1A JOINT VENTURES
If submitting an offer as a joint venture, an offeror must provide a copy of the joint venture agreement specific to the project that is consistent with the percentage of required work and net proceed. Additionally, the offeror must provide a breakdown or labor of which is to be performed by the SDVOSB firm and that which is performed by the small business joint venture firm and that which is sub-contracted. All Joint Ventures will be required to be registered and verified as an entity in Veteran Small Business Certification (vetcert@sba.gov ).
I.2A SELECTION CRITERIA/QUOTE PREPARATION INSTRUCTIONS
Quotes will be evaluated in accordance with FAR 13.106 Simplified Acquisition Procedures Award will be made based on the following factors:
Factor 1 – Past Performance Factor 2– Price Offerors are encouraged to provide their best offers with the past performance information requested for evaluation. The Government, based on the offered material presented, will award to the offeror that best demonstrates to be most advantageous for the Government.
Factor 1 - Past Performance: Offerors shall provide past performance information on two (2) federal, state, local government or private contract of similar type, scope, size and complexity. If a completed Contractor Performance Assessment Reporting System (CPARS) evaluation is available, it shall be submitted with the quote. The Government may also evaluate recent and relevant past performance, based upon sources available to the contracting officer that may include Federal Awardee Performance and Integrity Information System (FAPIIS) and Electronic Subcontract Reporting System (eSRS). IF THE OFFEROR CANNOT PROVIDE A CPARS FOR PROJECTS LISTED IN FACTOR 1, then the offeror shall submit Past Performance Questionnaires (PPQ).
Completed PPQs should be submitted directly from your client via email to jose.reveles@va.gov. If you have any questions, please contact Contract Specialist Bobby Reveles at jose.reveles@va.gov . If the offeror is unable to contact a client for a project(s) before closing date, the offeror should complete and submit with the quote the first page of the PPQ, which will provide contract and client information for the respective project(s). Offerors should follow-up with clients/references to ensure timely submittal of questionnaires.
Basis of Evaluation: Past Performance will be evaluated in accordance with FAR 13.106-2 and award will be made to the offeror presenting the best value to the Government.
Factor 2 - Price: Offerors shall provide pricing as requested in the Schedule of Service identified within the SF1442.
The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered.
SAFETY
(a) Solicitation Submittal Requirements:
The Offeror shall submit the following information: (For a partnership or joint venture, the following submittal requirements are required for each Contractor who is part of the partnership or joint venture and for the entity itself. EMR shall not be submitted for subcontractors.)
(1) OSHA or EPA Violation(s):
Offerors shall provide Summary of Work-Related Injuries and Illnesses, affirming that the Offeror has no more than three serious, or one repeat, or one willful OSHA or EPA violation(s) in the past 3 years
(2) Experience Modification Rate (EMR):
Offerors shall provide documentation to show that the offeror has an Experience Modification Rate (EMR) of equal to or less than 1.0.
PART I/SECTION B - INSTRUCTIONS, CONDITIONS AND NOTICES TO
OFFERORS
I.1B MAGNITUDE OF CONSTRUCTION PROJECT: Less than $25,000 If a product is manufactured to metric dimensions and those dimensions exceed the tolerance specified in the inch-pound units, a request should be made to the Contracting Officer to determine if the product is acceptable. The Contracting Officer, in concert with the Contracting Officer’s Representative (COR) will accept or reject the product.
I.2B SITE VISIT INFORMATION:
A Site Visit will be conducted on Thursday, Aug 23, 2023, at 3:00 PM CST. Vendors will meet at the conference room 3409 of the Engineering Building 34 at Amarillo VAMC - (6010 W Amarillo Blvd, Amarillo, TX 79106). Vendors gather at the conference room 3409 before going to the site.
There is no requirement for security access for the site visit. Vendors will park their vehicles at the general parking lots except designated areas for patient and special lots.
POC for this site visit is Nathan Duc.
I.3B REQUESTS FOR INFORMATION:
All requests for information must be submitted in writing to jose.reveles@va.gov for action no later than the date shown in Block 10 of the Standard Form 1442, Solicitation, Offer and Award.
I.4B QUOTE REQUIREMENTS
General – Quotes shall be submitted in response to this solicitation. Quotes shall be submitted.
via email to jose.reveles@va.gov . Emails are limited to five (5) MB. The quote, in its entirety, shall not exceed two emails (one email for price, and one email for technical/past performance) of 5MB each. Price shall be in a separate electronic document from the technical and past performance portions of the quote. Failures to submit in the format required and clearly address those factors may result in rejection of the offer. Further details on electronic submission are outlined below. Offerors shall include all required Representations and Certifications and complete their registration in System for Award Management (SAM). See FAR 52.204-7 and 52.204-8 of this solicitation.
Quotes shall be received by 5:00 PM Central Standard Time on September 19, 2023. Submit quotes to: jose.reveles@va.gov .
2.1 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
(End of Provision)
2.2 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)
(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers.
(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
(End of Provision)
2.3 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for—
(c) Participants will meet at—
(End of Provision)
2.4 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
https://www.acquisition.gov/browse/index/far https://www.va.gov/oal/library/vaar/
(End of Provision)
| FAR Number |
| Title |
| Date |
| 52.204-7 |
| SYSTEM FOR AWARD MANAGEMENT |
| OCT 2018 |
| 52.204-16 |
| COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING |
| AUG 2020 |
| 52.204-22 |
| ALTERNATIVE LINE ITEM PROPOSAL |
| JAN 2017 |
| 852.239-75 |
| INFORMATION AND COMMUNICATION TECHNOLOGY ACCESSIBILITY NOTICE |
| FEB 2023 |
REPRESENTATIONS AND CERTIFICATIONS
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2023)
(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 238110.
(2) The small business size standard is $19 Million.
(3) The small business size standard for a concern that submits an offer, other than on a construction or service acquisition, but proposes to furnish an end item that it did not itself manufacture, process, or produce is 500 employees, or 150 employees for information technology value-added resellers under NAICS code 541519, if the acquisition—
(i) Is set aside for small business and has a value above the simplified acquisition threshold;
(ii) Uses the HUBZone price evaluation preference regardless of dollar value, unless the offeror waives the price evaluation preference; or
(iii) Is an 8(a), HUBZone, service-disabled veteran-owned, economically disadvantaged women-owned, or women-owned small business set-aside or sole-source award regardless of dollar value.
(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.
(2) If the provision at 52.204–7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:
[ ] (i) Paragraph (d) applies.
[ ] (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.
(c)(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:
(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—
(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;
(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or
(C) The solicitation is for utility services for which rates are set by law or regulation.
(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.
(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements—Representation. This provision applies to all solicitations.
(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.
(v) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—
(A) Are not set aside for small business concerns;
(B) Exceed the simplified acquisition threshold; and
(C) Are for contracts that will be performed in the United States or its outlying areas.
(vi) 52.204-26, Covered Telecommunications Equipment or Services—Representation. This provision applies to all solicitations.
(vii) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations—Representation.
(viii) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.
(ix) 52.209-11, Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law. This provision applies to all solicitations.
(x) 52.214-14, Place of Performance—Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.
(xi) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.
(xii) 52.219-1, Small Business Program Representations (Basic, Alternates I, and II). This provision applies to solicitations when the contract is for supplies to be delivered or services to be performed in the United States or its outlying areas, or when the contracting officer has applied part 19 in accordance with 19.000(b)(1)(ii).
(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.
(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.
(C) The provision with its Alternate II applies to solicitations that will result in a multiple-award contract with more than one NAICS code assigned.
(xiii) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract is for supplies to be delivered or services to be performed in the United States or its outlying areas, or when the contracting officer has applied part 19 in accordance with 19.000(b)(1)(ii).
(xiv) 52.222-22, Previous Contracts and Compliance Reports. This provision applies to solicitations that include the clause at 52.222-26, Equal Opportunity.
(xv) 52.222-25, Affirmative Action Compliance. This provision applies to solicitations, other than those for construction, when the solicitation includes the clause at 52.222-26, Equal Opportunity.
(xvi) 52.222-38, Compliance with Veterans' Employment Reporting Requirements. This provision applies to solicitations when it is anticipated the contract award will exceed the simplified acquisition threshold and the contract is not for acquisition of commercial products or commercial services.
(xvii) 52.223-1, Biobased Product Certification. This provision applies to solicitations that require the delivery or specify the use of USDA-designated items; or include the clause at 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts.
(xviii) 52.223-4, Recovered Material Certification. This provision applies to solicitations that are for, or specify the use of, EPA-designated items.
(xix) 52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals--Representation. This provision applies to solicitations that include the clause at 52.204-7.)
(xx) 52.225-2, Buy American Certificate. This provision applies to solicitations containing the clause at 52.225-1.
(xxi) 52.225-4, Buy American—Free Trade Agreements—Israeli Trade Act Certificate. (Basic, Alternates II and III.) This provision applies to solicitations containing the clause at 52.225-3.
(A) If the acquisition value is less than $50,000, the basic provision applies.
(B) If the acquisition value is $50,000 or more but is less than $92,319, the provision with its Alternate II applies.
(C) If the acquisition value is $92,319 or more but is less than $100,000, the provision with its Alternate III applies.
(xxii) 52.225-6, Trade Agreements Certificate. This provision applies to solicitations containing the clause at 52.225-5.
(xxiii) 52.225-20, Prohibition on Conducting Restricted Business Operations in Sudan—Certification. This provision applies to all solicitations.
(xxiv) 52.225-25, Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran—Representation and Certifications. This provision applies to all solicitations.
(xxv) 52.226-2, Historically Black College or University and Minority Institution Representation. This provision applies to solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions.
(A) Solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions; and
(B) For DoD, NASA, and Coast Guard acquisitions, solicitations that contain the clause at 52.219-23, Notice of Price Evaluation Adjustment for Small Disadvantaged Business Concerns.
(2) The following representations or certifications are applicable as indicated by the Contracting Officer:
[X](i) 52.204-17, Ownership or Control of Offeror.
[X](ii) 52.204-20, Predecessor of Offeror.
[](iii) 52.222-18, Certification Regarding Knowledge of Child Labor for Listed End Products.
[](iv) 52.222-48, Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment—Certification.
[](v) 52.222-52, Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services—Certification.
[](vi) 52.223-9, with its Alternate I, Estimate of Percentage of Recovered Material Content for EPA-Designated Products (Alternate I only).
[](vii) 52.227-6, Royalty Information.
[](A) Basic.
[](B) Alternate I.
[](viii) 52.227-15, Representation of Limited Rights Data and Restricted Computer Software.
(d) The Offeror has completed the annual representations and certifications electronically in SAM accessed through https://www.sam.gov. After reviewing the SAM information, the Offeror verifies by submission of the offer that the representations and certifications currently posted electronically that apply to this solicitation as indicated in paragraph (c) of this provision have been entered or updated within the last 12 months, are current, accurate, complete, and applicable to this solicitation (including the business size standard applicable to the NAICS code referenced for this solicitation), as of the date of this offer and are incorporated in this offer by reference (see FAR 4.1201); except for the changes identified below [offeror to insert changes, identifying change by clause number, title, date]. These amended representation(s) and/or certification(s) are also incorporated in this offer and are current, accurate, and complete as of the date of this offer.
| FAR Clause # |
| Title |
| Date |
| Change |
Any changes provided by the offeror are applicable to this solicitation only, and do not result in an update to the representations and certifications posted on SAM.
(End of Provision)
3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021) The Offeror shall not complete the representation at paragraph (d)(1) of this provision if the Offeror has represented that it ‘‘does not provide covered telecommunications equipment or services as a part of its offered products or services to the Government in the performance of any contract, subcontract, or other contractual instrument’’ in paragraph (c)(1) in the provision at 52.204–26, Covered Telecommunications Equipment or Services—Representation, or in paragraph (v)(2)(i) of the provision at 52.212–3, Offeror Representations and Certifications–Commercial Products and Commercial Services. The Offeror shall not complete the representation in paragraph (d)(2) of this provision if the Offeror has represented that it ‘‘does not use covered telecommunications equipment or services, or any equipment, system, or service that uses covered telecommunications equipment or services’’ in paragraph (c)(2) of the provision at 52.204–26, or in paragraph (v)(2)(ii) of the provision at 52.212–3.
(a) Definitions. As used in this provision— Backhaul, covered telecommunications equipment or services, critical technology, interconnection arrangements, reasonable inquiry, roaming, and substantial or essential component have the meanings provided in the clause 52.204–25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.
(b) Prohibition. (1) Section 889(a)(1)(A) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L. 115–232) prohibits the head of an executive agency on or after August 13, 2019, from procuring or obtaining, or extending or renewing a contract to procure or obtain, any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system. Nothing in the prohibition shall be construed to—
(i) Prohibit the head of an executive agency from procuring with an entity to provide a service that connects to the facilities of a third-party, such as backhaul, roaming, or interconnection arrangements; or
(ii) Cover telecommunications equipment that cannot route or redirect user data traffic or cannot permit visibility into any user data or packets that such equipment transmits or otherwise handles.
(2) Section 889(a)(1)(B) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .