36C25723B0060_1.docx
DOCX document 143 KB Posted
- Attached to
- Y1DA--INSTALL A CHILLER FOR USP 797 Federal contract opportunity
- Solicitation number
- 36C25723B0060
About this file
This document is a solicitation for the installation of a chiller for USP 797 at a VA medical center. The solicitation requests bids for a firm fixed-price contract to provide all labor, equipment, materials and supervision to install a new standalone chiller processing unit. The project involves connecting the new unit to an existing air handler and tying into utilities. Bids are due by the date and time specified in Block 13a and will be opened in a Teams meeting. The contract will have a period of performance of 120 calendar days from notice to proceed. The solicitation is set aside 100% for Service-Disabled Veteran-Owned Small Businesses and requires bid guarantees, performance and payment bonds from the awardee.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C25723B0060 0001.docx | DOCX document | |
| Sign In Sheet for Install Chiller 797.pdf | ||
| 504-22-115 Drawings.pdf | ||
| 504-22-115 Specifications.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C25723B0060
1. SOLICITATION NUMBER
2. TYPE OF SOLICITATION
3. DATE ISSUED
PAGE OF PAGES
4. CONTRACT NUMBER
5.
REQUISITION/PURCHASE REQUEST NUMBER
6. PROJECT NUMBER
7. ISSUED BY
CODE
8. ADDRESS OFFER TO
a. NAME
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE
DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL
SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014)
STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION
SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
1. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See
YES
NO
a.
Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b.
An offer guarantee is, is not required.
c.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d.
Offers providing less than ____ ___________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
36C25723B0060 X 504-22-115 Department of Veterans Affairs Central Texas Veterans HCS 1901 Veterans Memorial Dr. Building #171 Temple TX 76504 Department of Veterans Affairs Central Texas Veterans HCS 1901 Veterans Memorial Dr. Building 171 Temple TX 76504 Barbara Dustin 254-878-2622
PROJECT TITLE: CONSTR. INSTALL CHILLER FOR USP 797; PROJECT NUMBER: 504-22-115
DESCRIPTION: Contractor shall furnish all necessary labor, materials, equipment, supervision and construction services necessary for the construction to Install Chiller for USP 797 in Bldg. 28 at the Thomas E. Creek VA Medical Center, located at 6010 Amarillo Blvd. West, Amarillo, TX 79106.
All work shall be done in accordance with (IAW) the prepared drawings and specifications.
Magnitude of Construction Project: Between $500,000.00 and $1,000,000.00
The applicable North American Industry Classification System (NAICS) code for this requirement is 236220. ($45.0M)
This requirement is a "competitive" offer, Set-Aside 100% Service-Disabled Veteran Owned Small Business (SDVOSB) in accordance with Public Law 109-461 (38 US 8127).
*NOTE: All offeror(s) must submit a Bid Guarantee as part of their Bid Package. Awardee must be able to obtain the necessary level of Performance and Payment Bonds.
The Pre-Bid Site Visit t o be held on 11 Oct. 2023 at 10:00AM CST.
CUT OFF FOR SUBMISSION OF RFI(S)/QUESTIONS SHALL BE TUESDAY,17 October, 2023 at 10:00 AM, CST. All RFIs/Questions shall be mailed to the following email address: barbara.dustin@va.gov SUBMISSION OF BIDS - All bids shall be emailed to the address above; Reference # 36C25723B0060.
THERE WILL BE A TEAMS MEETING SCHEDULED FOR THE BID OPENING.
**All Offeror(s) must comply with FAR 4-1103(a) and be registered in SAM.Gov database and certified in SBA Vet Cert to be eligible to participate.
All applicable Specifications and Drawings are issued as part of this solicitation. Please refer to VA website:
https//www.cfm.va.gov/tile for VA Master Specifications and Design Criteria.
**NOTE: Funds are not currently available for this solicitation. Award of a contract as a result of this solicitation is contingent upon the availability of appropriated funds from which payment of this contract may be made.
There shall be no legal liability on the part of the Government for contract purposes until funds are made available to the Contracting Officer. The Contracting Officer will confirm availability of funds prior to award of a contract.
x x 52.211-10 X 10:00
CST
11-02-2023 X
14. NAME AND ADDRESS OF OFFEROR
15.
TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE
FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a.
NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER
20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
ITEM
25. OTHER THAN FULL AND OPEN
COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (
26. ADMINISTERED BY
27. PAYMENT WILL BE MADE BY
PHONE:
FAX:
28. NEGOTIATED AGREEMENT
29. AWARD
Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code) (Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror) (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
Department of Veterans Affairs Central Texas Veterans HCS Veterans Memorial Dr. Building 171 Temple TX 76504 This is accomplished through the Tungsten Network located at:
http://www.fsc.va.gov/einvoice.asp This is mandatory and the sole method for submitting invoices.
(877) 353-9791
(512) 460-5540
Table of Contents
| PART I - THE SCHEDULE | 1 |
| SECTION A - SOLICITATION/CONTRACT FORM | 1 |
| A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair) | 1 |
| A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK | 2 |
| Statement of Work | 6 |
| OSHA -EMR Requirement | 14 |
| SPECIAL STANDARD OF RESPONSIBILITY | 15 |
| INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS | 16 |
| INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS | 17 |
| 2.1 52.216-1 TYPE OF CONTRACT (APR 1984) | 17 |
| 2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) | 17 |
| 2.3 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999) | 17 |
| 2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014) | 18 |
| 2.5 52.228-1 BID GUARANTEE (SEP 1996) | 19 |
| 2.6 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE) (FEB 2021) | 20 |
| 2.7 52.233-2 SERVICE OF PROTEST (SEP 2006) | 20 |
| 2.8 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995) | 21 |
| 2.9 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) | 21 |
| 2.10 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) | 22 |
| 2.11 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018) | 22 |
| 2.12 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009) | 22 |
| 2.13 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018) | 23 |
| 2.14 VAAR 852.239-75 INFORMATION AND COMMUNICATION TECHNOLOGY ACCESSIBILITY NOTICE (FEB 2023) | 23 |
| REPRESENTATIONS AND CERTIFICATIONS | 25 |
| 3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2023) | 25 |
| 3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021) | 29 |
| 3.3 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—CERTIFICATION (NOV 2021) | 31 |
| GENERAL CONDITIONS | 34 |
| 4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014) | 34 |
| 4.2 52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB AND OTHER COVERED ENTITIES (NOV 2021) | 34 |
| 4.3 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (MAR 2023) | 35 |
| 4.4 52.222-35 EQUAL OPPORTUNITY FOR VETERANS (JUN 2020) | 38 |
| 4.5 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT (DEC 2010) | 38 |
| 4.6 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022) | 40 |
| 4.7 SUPPLEMENTAL INSURANCE REQUIREMENTS | 45 |
| 4.8 52.236-4 PHYSICAL DATA (APR 1984) | 45 |
| 4.9 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 46 |
| 4.10 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUN 2020) | 47 |
| 4.11 VAAR 852.201-70 CONTRACTING OFFICER'S REPRESENTATIVE (DEC 2022) | 49 |
| 4.12 VAAR 852.211-72 TECHNICAL INDUSTRY STANDARDS (NOV 2018) | 49 |
| 4.13 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (JAN 2023) (DEVIATION) | 50 |
| 4.14 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (NOV 2022) | 53 |
| 4.15 VAAR 852.219-76 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SUPPLIES AND PRODUCTS (NOV 2022) | 54 |
| 4.16 VAAR 852.223-71 SAFETY AND HEALTH (SEP 2019) | 56 |
| 4.17 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008) | 58 |
| 4.18 VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (WITHOUT NAS– CPM) (NOV 2018) | 58 |
| 4.19 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018) | 61 |
| 4.20 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019) | 62 |
| 4.21 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019) | 63 |
| 4.22 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019) | 63 |
| 4.23 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020) | 63 |
| 4.24 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020) | 65 |
| 4.25 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019) | 65 |
| 4.26 VAAR 852.246-71 REJECTED GOODS (OCT 2018) | 66 |
Bid Schedule
The contractor shall furnish all labor, equipment, materials, and supervision to complete all required project work in strict accordance with the SOW, Specifications, and Drawings to Install a Chiller for USP 797 in Bldg. 28 at the Thomas E. Creek VAMC, in Amarillo, Texas, all to meet the increased demands of the center in accordance with the SOW and solicitation.
| CLIN |
| Description |
| Qty |
| Unit of issue |
Firm Fixed Price Lump Sum amount
| 0001 |
| Base Pricing to provide all necessary labor, |
Supplies, tools, equipment, and supervision necessary to Install a Chiller for USP 797, Bldg. 28 at the VAMC Amarillo, Texas in accordance with the SOW, specifications, and drawings.
| 1 |
| Job |
| $_________ |
0002 COST OF PERFORMANCE AND 1 Job $__________
PAYMENT BONDS
BASE BID TOTAL (Line Items 0001 & 0002) $__________
TOTAL PROJECT DURATION for Base Bid: 365 Calendar Days from issuance of the Notice to Proceed to complete the project work.
Page 1 of Page 1 of Statement of Work
Install a Chiller for USP 797
504 – 22 – 115
PROJECT OVERVIEW
1.1 PURPOSE:
The Department of Veterans Affairs (VA) intends to install a chiller for USP 797 in building 28 at the Thomas E. Creek VA Medical Center, located at 6010 Amarillo Blvd. West, Amarillo, Texas 79106.
This project will construct a N +1 Stand-alone chiller processing unit for the USP 797 and USP 800 Pharmacy Buffer rooms. This unit will tie into the new Air Handler Unit located in the mechanical room designed for the pharmacy compounding unit. The pharmacy compounding unit, which consist of 3 rooms (1 USP 797 Pharmaceutical Compounding - Sterile Preparations (CSP) lab room, 1 USP 800 Hazardous Drug Handling in Health Care Settings lab room, and shared USP 797/800 Ante room) having an area of approximately 421 square feet. This renovation will be done in accordance with the prepared drawings and specifications. All work will be performed at the Thomas E. Creek VA Medical Center.
SCOPE OF WORK
2.1 GENERAL: Provide all labor, materials, supplies, tools, equipment, supervision, and construction services necessary for the install a chiller for USP 797. All necessary testing will be required.
Work shall include:
The project will include all labor, material, equipment and supervision to perform the required work on this project. This work will include but not limited to, thermal & moisture protection, plumbing, electrical, and HVAC. Also included in the work will be installing a new roof curb, the installation of the new chiller, the new electrical work and other work as shown on the drawings and specifications.
A pre-award site visit is recommended and this visit will be coordinated by the Contracting Officer (CO) and the Contracting Officers Representative (COR). A pre-construction meeting is required and regular coordination meetings during construction work may be scheduled.
All numbers and measurements are for reference only. Contractor needs to verify all amounts and measurements. If there is a discrepancy in the amounts provided and or any condition affecting work shall be brought to the attention of the VA Representative before proceeding with the work.
All work as shown in the drawings and specs are the responsibility of the general contractor. Any subdivision of this work to subcontractors remains the sole responsibility of the general contractor.
O&M Manuals, As-Built drawings in CAD and PDF, applicable permits, installation, and testing, are also required.
Normal hours of operation for VA sites are 8:00AM to 4:30 PM Monday through Friday except for Federal Holidays. If the Contractor desires to work on Saturday, Sunday, holidays, or outside the project site’s normal working hours the contractor must submit a written request for approval to the VA-COR at least ten (10) working days prior to the proposed start of such work.
2.2 DESCRIPTION OF WORK
A. Existing Conditions
a. Before disabling any of the following systems, the contractor needs to coordinate with COR at least 3 working days in advance. Contractor shall be responsible for relocating and temporary installing all utilities and controls, including, but not limited to, telephone, data, electrical, med/gas, etc. It is the contractor’s responsibility to immediately repair any tampered with system at no additional cost to the government.
b. The buildings and the surrounding site areas will be occupied, and Government operations will continue as normal, temporary, or restricted basis for the duration of the contract. The Contractor shall take all precautions to ensure that his operations are conducted in a manner so as not to interfere with the normal operation of surrounding facilities. The Contractor shall execute work in a safe manner and shall not subject personnel to unsafe conditions. The Contractor shall provide safety barricades, devices, and equipment to protect personnel and property and repair damage caused by construction operations. Take all precautions to protect the building, equipment, and occupants during the construction period. Demolition and renovation shall take place with minimal disruption to adjacent areas.
c. Contractor will coordinate all work with existing work to remain and existing conditions.
d. Contractor shall be responsible for complying with all the construction documents and applicable Department of Veterans Affairs Master Specifications as part of this project.
e. Contractor must also comply with all applicable city, county, state, and federal regulations / codes and applicable OSHA standards project. In addition, the contractor shall flow federal codes including but not limited to the following:
1. NEC
2. NFPA
3. ADA
4. Life Safety Code
5. ASHRAE
6. OSHA Standards
7. JCAHO Standards
8. EPA regulations
9. ASME
10. ASPE
11. National and Local Building Codes
12. Others as applicable
f. On-site staging will be provided on the VA premises. The stage area will be determined at a later date.
g. Contractor will be allowed to park on the VA campus in designated areas.
h. Demolition and renovation shall take place with minimal disruption to adjacent areas.
i. Demolition debris shall be recycled to the best ability of the contractor. Reports of weight and deposition of all waste are to accompany the monthly progress payments.
j. The contractor shall repair any damage to the adjacent facilities and will return the area to the government with in a condition like that before the construction started. This work is the contractor’s responsibility to replace at no additional cost to the government.
k. All work shall be in accordance with VA specifications. All costs shall be included in the base bid. All work shall be coordinated with the VA prior to any demolition work being performed.
B. Additional Requirements
a. Housekeeping - Accumulation of trash, paper, wood shavings, sawdust, excelsior, boxes and other packing materials will be cleaned up as often as necessary and at the end of each work day. Contractor to remove and dispose of excavated material and any trees that are to be removed off the VA property. Any material such as concrete washout etc. will also be removed from the VA property at the completion of the project.
b. Fire Watch - Provide fire watch for impairments more than 4 hours in a 24-hour period. Request interruptions in accordance with Article, OPERATIONS AND STORAGE AREAS, and coordinate with COR and facility safety officer. All existing or temporary fire protection systems (fire alarms, sprinklers) located in construction areas shall be tested as coordinated with the medical center. Parameters for the testing and results of any tests performed shall be recorded by the medical center and copies provided to the COR.
c. Smoking is strictly prohibited in all facilities at all Amarillo VA facilities.
d. Security – Contractors will always wear security badge in plain sight above the waist. Contractors found without a badge will be immediately removed from VA property by VA Police.
e. Parking – Contractor vehicles found parked in undesignated VA parking areas will be issued an United States District Court Violation Notice and immediately removed and banned from VA property.
f. OSHA 10 & 30 -Hour Training Course – All construction workers are required to have the OSHA 10-hour Construction Safety training certification. The construction safety manager and superintendent shall have the 30-hour Construction Safety course certification. Proof of certification shall be on site at all times.
g. Infection Control (IC) and Safety–Construction sign and copy of IC permit (attached) shall be posted in project site at all times. All IC and dust control measures shall be implemented at all times.
h. All construction and installation work shall comply with VA specifications for material and workmanship, NEC, NFPA and all applicable city, county, state, and federal regulations and codes and OSHA standards. Refer construction drawings and specs for requirements.
i. All incidental work associated with the installation and construction works in the exterior and interior of the building shall be included in the base bid.
j. Conduct work as to interfere as least as possible with facility operations. All coordination for utilities shutdown shall be coordinated at least 2 weeks prior to event with COR.
2.3 OTHER DELIVERABLES
A. Period of Performance: 120 Calendar days after Notice to Proceed
B. Performance and Payment bonds: Due 10 Calendar days after Notice of Award
C. Proof of Insurance: Due 10 Calendar days after Notice of Award
D. Contractor Quality Control Plan (CQCP): The contractor shall develop a quality control plan and shall furnish to VA for review no later than 30 calendar days after the receipt of notice to proceed. The plan shall identify personnel, procedures, control, instructions, tests, records, and forms to be used. VA will consider an interim plan for the first 45 calendar days of operation. Installation will be allowed to begin only after acceptance of the CQCP or acceptance of an interim plan applicable to the particular feature of the work to be started. Work outside of the features of the work included in an accepted interim plan will not be permitted to begin until acceptance of a CQCP or another interim plan containing the additional features of the work to be started. After acceptance of the CQCP, the Contractor shall notify the Contracting Officer Representative (COR) in writing of any proposed change. Proposed changes are subject to acceptance by the Contracting Officer. Please see Appendix H for additional details.
a. The Quality Control Plan shall include as a minimum, the following:
| i. | A description of the quality control organization, including chart showing lines of authority and acknowledgement that the CQC staff shall report to the project manager or someone higher in the contractor’s organization. |
| ii. | The qualifications, duties, responsibilities, and authorities of each person assigned a quality control function. |
| iii. | A copy of the letter to the Quality Control Manager, signed by an authorized official of the firm, which describes the responsibilities and delegates the authorities of the Quality Control Manager, shall be furnished. |
| iv. | Procedures for scheduling and managing submittals, including those of subcontractors, offsite fabricators, suppliers, and purchasing agents. |
| v. | Control testing procedures for each specific test performed on any task order will be submitted and approved prior to the start of construction on that task order (Laboratory facilities will be approved by the Contracting Officer). |
| vi. | Reporting procedures, including proposed reporting formats and distribution of the documents. |
E. Safety Plan: Contractor shall develop and implement a Comprehensive safety plan to eliminate injuries occurring relative to providing the design and installation services for this project. Contractor shall furnish to VA for review no later than 15 calendar days after the receipt of notice to proceed. The plan shall also describe how final system installation will meet all applicable requirements of NFPA30 and NFPA30A. Construction/Renovation work will be allowed to begin only after VA’s acceptance of the Safety Plan. Contractor is responsible for providing enough project lead time to allow for VA review of Safety Plan before acceptance. The Department of Labor OSHA requires that all Contractors involved in installation on VA owned or leased property comply with the Incorporation of General Industry Safety and Health Standards applicable to Installation Work and Technical Amendments, Final Rule 29 CFR Parts 1910 and 1926 as published in the Federal Register Volume 58, No. 124, June 30, 1993. In addition, any Contractor that performs construction type work on any VA project as defined by the Scope of the referenced regulation is required to; (1) Provide and maintain his own protective equipment and devices, etc; and (2) Require all sub-contractors used on site to follow these same provisions in the regulation.
F. Operations and Maintenance Manuals (O&M): The Contractor shall provide two (2) complete sets of O&M manuals including a recommended spare parts list identifying components adequate for competitive supply procurement for operation and maintenance of the system. The O&M Manuals shall include maintenance and inspection for all equipment. A three-ring binder containing all the O&M and electronic files on CD-ROM shall be provided within the binder.
G. Submittals CD: As part of the closeout documentation, the contractor shall provide the COR, 1 CD containing all the approved submittals.
H. Operations and Maintenance Training: The Contractor shall provide on-site O&M training for the location which will consist of two (2) formal on-site training sessions during a 30-day period to including but not limited to system operation, corrective and preventive maintenance and inspections.
The contractor shall provide training manuals that include the hands-on exercises, O&M data and troubleshooting guides necessary for personnel to assume full O&M responsibility for the system after completion of the training. The contractor shall provide a written training syllabus for the topics and detailed training content for review and approval by the COR at least 30 days prior to the scheduled training. The contractor will coordinate with the COR the scheduling of any training classes in advance. The COR may require the classes to be provided on non-consecutive days at the convenience of the VA Staff. The Contractor shall video tape this training for official use and forward CD (2 copies) including those training videos.
O. Warranty: Contractor shall provide a minimum one (1) year warranty, unless specified otherwise in the specs, from both the manufacturer and installer including parts and labor to include normal, premium or holidays hours. The Warranty period shall start on the date of Substantial Completion.
2.4 ACCEPTANCE
A. For the purposes of Warranty and payment for the work performed at a location, government “Acceptance” will be provided by the VA upon the completion of all the following:
a. The Contractor has all the punch list items identified during the commissioning have been resolved.
b. The Contractor has provided electronic closeout package including the following: Contractor certified executed Quality Control Inspection documentation (electronic pdf format), approved submittals, As-builts and Certified Warranty Letter.
c. The Contractor has provided O&M manuals.
d. The Contractor has provided Record drawings to include a CD with all as builds CAD files, one full set, one half set and one Mylar full set.
2.5 CONFIDENTIALITY AND NONDISCLOSURE
A. The preliminary and final deliverables and all associated working papers, application source code, and other material deemed relevant by the VA which has been generated by the contractor in the performance of this Order are the exclusive property of the U.S. Government and shall be submitted to the VA-COR at the conclusion of the contract.
B. The Contracting Officer will be the sole authorized official to release verbally or in writing, any data, the draft deliverables, the final deliverables, or any other written or printed materials pertaining to this contract. No information shall be released by the contractor. Any request for information relating to this contract presented to the contractor shall be submitted to the CO for response.
C. Press releases, marketing material or any other printed or electronic documentation related to this project, shall not be publicized without the written approval of the CO.
D. To the extent that the work under this contract requires that the contractor be given access to proprietary business, technical or financial information belonging to the Government or other companies, the contractor shall treat such information as proprietary business sensitive and agrees not to appropriate such information to its own use or to disclose such information to third parties unless specifically authorized by the CO in writing. A mutually agreed to agreement for exchange of sensitive information or nondisclosure agreement may be required.
E. General Requirements for Privacy Information:
· Information Systems Officer, Information Protection: The contractor will not have access to VA Desktop computers nor will they have access to online resources belonging to the government while conducting services.
· Privacy Officer: The contractor will not have access to Patient Health Information (PHI) nor will they have the capability of accessing patient information during the services provided to the VA.
· Records Manager: There will be no federal records created, maintained, used or dispositioned with this contract; regardless of format [paper, electronic, etc.] or mode of transmission [e-mail, fax, etc.].
OSHA -EMR Requirement
OSHA or EPA Violation(s):
(1) Offerors shall provide Summary of Work-Related Injuries and Illnesses, affirming that the
(2) Offeror has no more than three serious, or one repeat, or one willful OSHA or EPA violation(s) in the past 3 years
Experience Modification Rate (EMR):
(1) Offerors shall provide documentation to show that the offeror has an Experience Modification Rate (EMR) of equal to or less than 1.0.
Page 1 of
Page 1 of
INSTRUCTIONS FOR CALCULATION OF SELF-PERFORMED WORK IAW “Limitations on Subcontracting” (VAAR 852.219-75)
OFFEROR’S SELF PERFORMED ESTIMATED CALCULATIONS
At the time of proposal Offeror’s are required to complete.
a) Offeror’s total proposed price: $ __________
b) Cost of Materials $ __________
c) Total excluding materials (a-b) $ __________
d) Amount projected to be paid to non-VIP listed SDVOSBs: $ __________ (not including materials)
e) Offeror’s percentage of estimated Non VIP work (d/c X 100 = %) __________%
f) Offeror’s percentage of estimated self-performed work (100 – e = %) __________%
A/E-Services. In the case of a contract for services (except construction), it will not pay more than 50% of the amount paid by the government to it to firms that are not VIP-listed VOSBs.
General construction. In the case of a contract for general construction, it will not pay more than 85% of the amount paid by the government to it to firms that are not VIP-listed SDVOSBs.
Special trade contractors. In the case of a contract for special trade contractors, it will not pay more than 75% of the amount paid by the government to it to firms that are not VIP-listed SDVOSBs.
SPECIAL STANDARD OF RESPONSIBILITY
Solicitation Submittal Requirements:
The Offeror shall submit the following information as part of your Bid Package: (For a partnership or joint venture, the following submittal requirements are required for each Contractor who is part of the partnership or joint venture and for the entity itself., EMR shall not be submitted for subcontractors.)
1. OSHA or EPA Violation(s): Offerors shall provide Summary of Work-Related Injuries and Illnesses, affirming that the Offeror has no more than three serious, or one repeat, or one willful OSHA or EPA violation(s) in the past 3 years.
2. Experience Modification Rate (EMR): Offerors shall provide documentation to show that the offeror has an Experience Modification Rate (EMR) of equal to or less than 1.0.
3. Limitation on Subcontracting:
IAW VAAR 852.219-76 each offeror will review the clause and complete the certificate included in the clause. This certificate will be complete prior to solicitation closing and submitted with the proposal, bid, or quote documents. Failure to comply with this requirement will result in removal from consideration for award.
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS
A. All bid packages shall be submitted via email to the following email address: Barbara.dustin@va.gov , by the specified Bid Closing date and time as stated on the SF1442, Page 1, Block 13a. The applicable Solicitation Number for this IFB must be included on the subject line of the email.
B. A public Bid Opening will not be held. Bids shall be opened by the Contracting Officer and Contract Specialist, witnessed and recorded on an official Bid Abstract. Bid Abstracts will be available upon request via email.
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
2.1 52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.
(End of Provision)
2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
(End of Provision)
2.3 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
| Goals for minority participation for each trade |
| Goals for female participation for each trade |
| 9.3 % |
| 6.9 % |
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the—
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Potter County, Texas
(End of Provision)
2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)
(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers.
(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
(End of Provision)
2.5 52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—
(1) To unsuccessful bidders as soon as practicable after the opening of bids; and
(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000.00, whichever is less.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of Provision)
2.6 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE) (FEB 2021)
(a) Offerors shall obtain from each person acting as an individual surety on a bid guarantee—
(1) A pledge of assets that meets the eligibility, valuation, and security requirements described in the Federal Acquisition Regulation (FAR) 28.203–1; and
(2) Standard Form 28, Affidavit of Individual Surety.
(b) The Offeror shall include with its offer the information required at paragraph (a) of this provision within the timeframe specified in the provision at FAR 52.228–1, Bid Guarantee, or as otherwise established by the Contracting Officer.
(c) The Contracting Officer may release the security interest on the individual surety’s assets in support of a bid guarantee based upon evidence that the offer supported by the individual surety will not result in contract award.
(End of Provision)
2.7 52.233-2 SERVICE OF PROTEST (SEP 2006)
Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:
Hand-Carried Address:
Department of Veterans Affairs Central Texas Veterans HCS 1901 Veterans Memorial Dr. Building 171 Temple TX 76504 Mailing Address:
Department of Veterans Affairs Central Texas Veterans HCS 1901 Veterans Memorial Dr, Building 171 Temple TX 76504
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
(End of Provision)
2.8 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for— 11 October, 2023; 10:00AM CST
(c) Participants will meet at— Engineering Office (End of Provision)
2.9 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
https://www.acquisition.gov/browse/index/far https://www.va.gov/oal/library/vaar/
(End of Provision)
| FAR Number |
| Title |
| Date |
| 52.204-7 |
| SYSTEM FOR AWARD MANAGEMENT |
| OCT 2018 |
| 52.204-16 |
| COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING |
| AUG 2020 |
| 52.204-22 |
| ALTERNATIVE LINE ITEM PROPOSAL |
| JAN 2017 |
2.10 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 120 days after receipt of notice to proceed. The time stated for completion shall include final cleanup of the premises.
(End of Clause)
| FAR Number |
| Title |
| Date |
| 52.214-3 |
| AMENDMENTS TO INVITATIONS FOR BIDS |
| DEC 2016 |
| 52.214-4 |
| FALSE STATEMENTS IN BIDS |
| APR 1984 |
| 52.214-5 |
| SUBMISSION OF BIDS |
| DEC 2016 |
| 52.214-6 |
| EXPLANATION TO PROSPECTIVE BIDDERS |
| APR 1984 |
| 52.214-7 |
| LATE SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS |
| NOV 1999 |
| 52.214-18 |
| PREPARATION OF BIDS—CONSTRUCTION |
| APR 1984 |
| 52.214-19 |
| CONTRACT AWARD—SEALED BIDDING—CONSTRUCTION |
| AUG 1996 |
| 52.214-34 |
| SUBMISSION OF OFFERS IN THE ENGLISH LANGUAGE |
| APR 1991 |
| 52.214-35 |
| SUBMISSION OF OFFERS IN U.S. CURRENCY |
| APR 1991 |
2.11 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)
The Contractor shall not make reference in its commercial advertising to Department of Veterans Affairs contracts in a manner that states or implies the Department of Veterans Affairs approves or endorses the Contractor’s products or services or considers the Contractor’s products or services superior to other products or services.
(End of Clause)
2.12 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009) Prime contractors are encouraged to assist service-disabled veteran-owned and veteran-owned small business potential subcontractors in obtaining bonding, when required. Mentor firms are encouraged to assist protégé firms under VA's Mentor-Protégé Program in obtaining acceptable bid, payment, and performance bonds, when required, as a prime contractor under a solicitation or contract and in obtaining any required bonds under subcontracts.
(End of Clause) PLEASE NOTE: The correct mailing information for filing alternate protests is as follows:
| Deputy Assistant Secretary for Acquisition and Logistics, |
| Risk Management Team, Department of Veterans Affairs |
| 810 Vermont Avenue, N.W. |
| Washington, DC 20420 |
Or for solicitations issued by the Office of Construction and Facilities Management:
| Director, Office of Construction and Facilities Management |
| 811 Vermont Avenue, N.W. |
| Washington, DC 20420 |
2.13 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018)
(a) Any protest filed by an interested party shall—
(1) Include the name, address, fax number, email and telephone number of the protester;
(2) Identify the solicitation and/or contract number;
(3) Include an original signed by the protester or the protester’s representative and at least one copy;
(4) Set forth a detailed statement of the legal and factual grounds of the protest, including a description of resulting prejudice to the protester, and provide copies of relevant documents;
(5) Specifically request a ruling of the individual upon whom the protest is served;
(6) State the form of relief requested; and
(7) Provide all information establishing the timeliness of the protest.
(b) Failure to comply with the above may result in dismissal of the protest without further consideration.
(c) Bidders/offerors and Contracting Officers are encouraged to use alternative dispute resolution (ADR) procedures to resolve protests at any stage in the protest process. If ADR is used, the Department of Veterans Affairs will not furnish any documentation in an ADR proceeding beyond what is allowed by the Federal Acquisition Regulation.
(End of Provision)
2.14 VAAR 852.239-75 INFORMATION AND COMMUNICATION TECHNOLOGY ACCESSIBILITY NOTICE (FEB 2023)
(a) Any offeror responding to this solicitation must comply with established VA Information and Communication Technology (ICT) (formerly Electronic and Information (EIT)) accessibility standards. Information about Section 508 is available at http://www.section508.va.gov/.
(b) The Section 508 accessibility standards applicable to this solicitation are stated in the clause at 852.239–75, Information and Communication Technology Accessibility. In order to facilitate the Government’s determination whether proposed ICT supplies meet applicable Section 508 accessibility standards, offerors must submit appropriate VA Section 508 Checklists, in accordance with the checklist completion instructions. The purpose of the checklists is to assist VA acquisition and program officials in determining whether proposed ICT supplies, or information, documentation and services conform to applicable Section 508 accessibility standards. The checklists allow offerors or developers to self-evaluate their supplies and document—in detail—whether they conform to a specific Section 508 accessibility standard, and any underway remediation efforts addressing conformance issues.
(c) Respondents to this solicitation must identify any exception to Section 508 requirements. If an offeror claims its supplies or services meet applicable Section 508 accessibility standards, and it is later determined by the Government, i.e., after award of a contract or order, that supplies or services delivered do not conform to the described accessibility standards, remediation of the supplies or services to the level of conformance specified in the contract will be the responsibility of the Contractor at its expense.
(End of Provision)
REPRESENTATIONS AND CERTIFICATIONS
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2023)
(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 236220.
(2) The small business size standard is $45 Million.
(3) The small business size standard for a concern that submits an offer, other than on a construction or service acquisition, but proposes to furnish an end item that it did not itself manufacture, process, or produce is 500 employees, or 150 employees for information technology value-added resellers under NAICS code 541519, if the acquisition—
(i) Is set aside for small business and has a value…
This is the start of the file's text. The full file is on GovTribe.