36C25723B0030_1.docx
DOCX document 203 KB Posted
- Solicitation number
- 36C25723B0030
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25723B0030 0001.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C25723B0030
1. SOLICITATION NUMBER
2. TYPE OF SOLICITATION
3. DATE ISSUED
PAGE OF PAGES
4. CONTRACT NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
6. PROJECT NUMBER
7. ISSUED BY
CODE
8. ADDRESS OFFER TO
a. NAME
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014)
STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION
SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).
YES
NO
a.
Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b.
An offer guarantee is, is not required.
c.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d.
Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
36C25723B0030 X 01-29-2023 519-22-700 36C257 Department of Veterans Affairs Network Contracting Office (NCO) 17 Central Texas Veterans HCS 1901 Veterans Memorial Dr. Building #171 Temple TX 76504 Department of Veterans Affairs Network Contracting Office (NCO) 17 Central Texas Veterans HCS 1901 Veterans Memorial Dr. Building 171 Temple TX 76504 Jennifer Stringer 512-949-1553 Project Title: WTX Replace Domiciliary Dining Room Floor, Big Spring VA
Description: Contractor shall provide all materials, labor, and supervision to (1) Remove old flooring, (2) remove cove base, (3) install new tile flooring, (4) install new cove base; in BLDG 18 at 300 Veterans BLVD, Big Spring, TX 79720.
This Invitation for Bids corresponds with Pre-Solicitation Notice 36C25723Q0324 posted on SAM.gov Contract Oppor tunities on 1/19/2023 and, subsequently, Pre-Solicitation notice 36C25723B0030 posted on 1/26/2023.
Magnitude of Construction Project: $25,000 to $100,000.
The North American Industry Classification System (NAICS) code for this requirement is 238330.
This requirement is a "competitive" offer, Set-Aside for 100% Service Disabled Veteran Owned Small Business (SDVOSB).
The Pre-Bid Site-Visit shall be held on Friday, February 17, 2023 at 11:00 AM CST at BLDG 3 Room 10, 300 Veterans BLVD, Big Spring, TX 79720. POC for site visit is Eric Landrum. Please contact POC with intent to attend site visit.
Email: Eric.Landrum@va.gov.
All Questions/Inquiries about this solicitation shall be directly submitted via email to the Contracting Officer:
jennifer.stringer@va.gov. No phone or faxed inquiry will be accepted. Deadline for all Questions/Inquiries shall be Wednesday, February 22, 2023, no later than 11:00 AM CST.
The public bid opening shall be an electronic public bid opening. Bid Abstracts will be available upon request via email to jennifer.stringer@va.gov.
All offerors must provide evidence of SDVOSB status by submitting a copy of VetBiz Registry printout showing your firm as verified SDVOSB or SBA Veteran Small Business Certification Program ( VetCert ) verification.
Please see Statement of Work for pictures and specific, project-related information.
All applicable Specifications and Drawings are issued as part of this solicitation. Please refer to VA website http://www.cfm.va.gov/tile for VA Master Specifications and Design Criteria.
X X 52.211-10 X 09:00
CST
03-01-2023 X
14. NAME AND ADDRESS OF OFFEROR
15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE
FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (
26. ADMINISTERED BY
27. PAYMENT WILL BE MADE BY
PHONE:
FAX:
28. NEGOTIATED AGREEMENT
29. AWARD
Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code) (Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror) (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
36C257 Department of Veterans Affairs Network Contracting Office (NCO) 17 Central Texas Veterans HCS 1901 Veterans Memorial Dr. Building 171 Temple TX 76504 This is accomplished through the Tungsten Network located at:
http://www.fsc.va.gov/einvoice.asp This is mandatory and the sole method for submitting invoices.
(877) 353-9791
(512) 460-5540 Jennifer Stringer Contracting Officer
SECTION B – SCHEDULE OF PRICES DESCRIPTION
B.1 SCHEDULE
Division 1: General Requirements
| Item Number |
| Description |
| Qty/Unit |
| Price |
| Total Bid Amount |
| 0001 |
| Mobilization |
| 1 JB |
| $ |
| $ |
| 0002 |
| Project Manager |
| 1 EA |
| $ |
| $ |
| 0003 |
| Superintendent |
| 1 EA |
| $ |
| $ |
| 0004 |
| Demobilization |
| 1 JB |
| $ |
| $ |
Total
Division 9: Finishes
| Item Number |
| Description |
| Qty/Unit |
| Price |
| Total Bid Amount |
| 0005 |
| Labor & supervision to remove old flooring* |
| 1 JOB |
| $ |
| $ |
| 0006 |
| Labor & supervision to remove cove base* |
| 1 JOB |
| $ |
| $ |
| 0007 |
| Labor & supervision to install new tile flooring* |
| 1 JOB |
| $ |
| $ |
| 0008 |
| Labor & supervision to install new cove base* |
| 1 JOB |
| $ |
| $ |
Total
*Materials needed are included in pricing.
TOTAL BID AMOUNT $ _____________________
Table of Contents
| PART I - THE SCHEDULE | 1 |
| SECTION A - SOLICITATION/CONTRACT FORM | 1 |
| A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair) | 1 |
| A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK | 2 |
| SECTION B – SCHEDULE OF PRICES DESCRIPTION | 3 |
| B.1 SCHEDULE | 3 |
| B.2 STATEMENT OF WORK | 6 |
| B.3 STATEMENT OF WORK-ATTACHMENT A-DRAWING | 11 |
| INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS | 12 |
| INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS | 14 |
| 2.1 52.216-1 TYPE OF CONTRACT (APR 1984) | 17 |
| 2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) | 17 |
| 2.3 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999) | 17 |
| 2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014) | 18 |
| 2.5 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995) | 19 |
| 2.6 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) | 20 |
| 2.7 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018) | 20 |
| 2.8 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018) | 21 |
| REPRESENTATIONS AND CERTIFICATIONS | 22 |
| 3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAY 2022) (JUL 2020) (DEVIATION) | 22 |
| 3.2 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018) | 26 |
| 3.3 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—CERTIFICATION (NOV 2021) | 27 |
| GENERAL CONDITIONS | 30 |
| 4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014) | 30 |
| 4.2 52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB AND OTHER COVERED ENTITIES (NOV 2021) | 30 |
| 4.3 52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018) | 31 |
| 4.4 52.210-1 MARKET RESEARCH (NOV 2021) | 32 |
| 4.5 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) | 33 |
| 4.6 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (OCT 2022) | 33 |
| 4.7 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022) | 36 |
| 4.8 52.228-13 ALTERNATIVE PAYMENT PROTECTIONS (JULY 2000) | 40 |
| 4.9 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 41 |
| 4.10 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT (DEC 2010) | 43 |
| 4.11 VAAR 852.219-10 VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (JUL 2019) (DEVIATION) | 44 |
| 4.12 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING AND COMPLIANCE (JUL 2018) | 46 |
| 4.13 VAAR 852.219-77 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (SEP 2021) (DEVIATION) | 47 |
| 4.14 VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (WITHOUT NAS– CPM) (NOV 2018) | 49 |
| 4.15 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018) | 51 |
| 4.16 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019) | 53 |
| 4.17 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019) | 53 |
| 4.18 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020) | 53 |
| 4.19 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020) | 55 |
| 4.20 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019) | 55 |
B.2 STATEMENT OF WORK
Statement of Work West Texas VA Health Care System Replace flooring in Bldg. 18
BACKGROUND: The West Texas VA Health Care System (WTVAHCS) located at 300 Veterans Blvd., Big Spring, TX 79720. Currently has a requirement for services to replace the flooring in the domiciliary dining room.
STATEMENT OF WORK:
Contractor shall provide all equipment, labor, material, transportation, and supervision to remove current flooring/cove base and replace the dining room floor in Bldg.18 at 300 Veterans Blvd., Big Spring, TX. with ceramic tile/cove base in a timely fashion with minimal impact on patient care. The contractor will be responsible for visiting the site and interfacing with the COR responsible for onsite contract management. The contractor will be responsible for storage and removal of old flooring. Contractor will be responsible for sealing elastomeric grout and installing cove base All materials must be approved by the VA prior to purchasing.
Period of performance: 120 Days after notice to proceed is issued.
OBJECTIVE:
· Remove all furniture in an orderly fashion.
· Removal of existing floor and cove base
· Install New Ceramic Tile floor and cove base to specifications.
· Seal grout joints
· Address any transition issues between floors.
· Clean up and dispose of old flooring and cove base
TASKS AND DELIVERABLES: The vendor shall provide the specific services and deliverables described below:
a. Task One: The vendor shall provide a detailed work plan and briefing for the VA, which presents the vendor’s plan for completing the task order.
b. Contractor will provide tile, grout, and cove base selected from samples
c. In general, electrical & plumbing shall be the only utility systems utilized for this project. In addition, there may be several utility systems conditions and requirements which apply to this project that may result in the need for more or less work depending upon the system. The following is a brief description of utility conditions and requirements for this project.
d. Any material the contractor finds suspicious and thought to contain asbestos shall be tested and or removed by the VA. Any material that is adjacent to the work area shall be left in place and undisturbed. If work cannot be conducted without disturbing said material, then it shall be tested or abated by the VA. The contractor shall survey all work areas and report any suspicious material before starting work. If material must be tested or abated the contractor could have to wait up to two weeks for this work to be performed.
e. Work shall be coordinated with the COR. And Infection control because this work is in a patient care area. Infection control barriers, signage, and general cleanliness are a priority on this project. Any deviation from construction safety, infection control, or other mandated measures will be cause for construction to terminate until these deficiencies are corrected.
f. The contractor shall be solely responsible for the management of installation, including all labor, equipment, materials, and inspection, to meet requirements of the contract.
g. The VA shall provide the contractor any schematic design (layout) or basic construction drawings they have on file.
h. Contractor superintendent shall be on station at all times to address any needs the VA may have during the construction period.
i. Contractor shall thoroughly clean inside and outside of construction site daily with contractor’s own equipment, including vacuums, mops, buckets, wash rags, dust mops, etc.…
j. Contractor shall adhere to basic VA specifications for all work. Contractor shall reference the VA Technical Information Library (TIL).
k. This shall be a turn-key project. Material purchased by the contractor must meet the specifications and submittals shall be approved prior to purchasing the material.
l. Workmanship and materials shall be warranted for one-year from the date of final acceptance.
The contractor shall provide all applicable safety signage and barricades applicable to OSHA and VHA. Contractor shall comply with VHA DIRECTIVE 7715 and all VA Center Policy Memorandums, including but not limited to the following.
1. Protection of patients, visitors, and employees from traumatic injury, as well as occupational and facility–associated infections.
2. Compliance with OSHA and State construction safety regulations.
3. Compliance with EPA and State environmental regulations.
4. Ensuring that on-site general and sub-contractor’s construction workers have completed the OSHA 10-hour construction worker course.
5. Project Superintendent shall posses an OSHA 30-hour certification.
SECURITY: This service does not involve contractor connection of one or more contractor-owned IT devices (such as laptop computer or remote connection from a contractor system) to a VA internal trusted (i.e., non-public network); therefore, Information Technology (IT) Security certification and accreditation (authorization) (C&A) requirements do not apply per VA Handbook 6500.6 The C&A requirements do not apply and that a Security Accreditation is not required.
REQUIREMENTS AND CONSIDERATIONS:
a. The Contractor is required to comply with security measures and policies set in place by the VA.
b. The Contractor shall be responsible for replacing any damaged surrounding areas during the removal and installation of the components.
e. The Contractor is responsible for labeling all electrical and fire suppression components.
f. The Contractor shall survey all work areas and report any suspicious material before starting work.
g. Any material the contractor finds suspicious and thought to contain asbestos shall be tested and or removed by the VA. Any material that is adjacent to the work area shall be left in place and undisturbed. If work cannot be conducted without disturbing said material, then it shall be tested or abated by the VA.
h. All contractor personnel must report to the Engineering Office at the Facility prior to and after any work performed and sign out after completion of services. The contractor must furnish to the Chief of Engineering a detailed field report, or equivalent, showing work completed before leaving the Facility.
i. The Contractor shall not perform any service that will result in additional charges without prior approval from the Contracting Officer.
j. The Contractor shall comply with the standards in the Occupational Safety and Health Act (OSHA).
k. The Contractor is responsible for his employees while on Facility grounds including any accidents while performing the service.
l. Contractor must refer to the master spec in the technical information library (TIL) https://www.cfm.va.gov/til/spec.asp
DELIVERY LOCATION: All work related to this contract shall be accomplished at the WTVAHCS, 300 Veterans Blvd. Big Spring, Texas.
COMPETENCY OF PERSONNEL: Personnel shall be authorized by the contractor to perform the services. All work shall be performed by fully qualified and competent personnel. The government reserves the right to authenticate training requirements, request training certificates and credentials from the contractor at any time during the course of this contract through written request by the Contracting Officer (CO).
BADGES: All Contractor personnel are required to wear I.D. badges during the entire time he/she is on Government property. I.D. badges must have an identification picture and shall state the name of the individual and the company he/she represents. The Contractor is to coordinate with the COR to obtain the I.D. badge from the Police Service. The Contractor is to provide a list of personnel who shall be performing the service.
1. Contractor will contact VA COR or Alternative COR 72 hours prior to start of the work.
A. Program Office Point of Contact:
a. Contracting Officer’s Representative (COR): Eric Landrum, M&R Supervisor – Engineering Service, Office: 432-263-7361 ex. 7427, Cell: 432-816-8840; Email: Eric.Landrum@va.gov
2. Coordinate with VA COR before the start of this service and completion. See information below:
A. Government Holidays:
(a) The Government hereby provides notice and Contractor hereby acknowledges receipt that Government personnel observe the listed days as holidays:
| New Year's Day | January 1st |
| Martin Luther King's Birthday | Third Monday in January |
Washington’s Birthday Third Monday in February
| Memorial Day | Last Monday in May | |
| Juneteenth | June 19th | |
| Independence Day | July 4th | |
| Labor Day | First Monday in September | |
| Columbus Day | Second Monday in October |
Veterans Day November 11th Thanksgiving Day Fourth Thursday in November Christmas December 25th
(b) In addition to the days designated as holidays, the Government observes the following days:
a. Any other day designated by Federal Statute
b. Any other day designated by Executive Order
c. Any other day designated by the President’s Proclamation
It is understood and agreed between the Government and the Contractor that observance of such days by Government personnel shall not otherwise be a reason for an additional period of performance, or entitlement of compensation. In the event the Contractor's personnel work during the holiday, they may be reimbursed by the Contractor, however, no form of holiday or other premium compensation will be reimbursed either as a direct or indirect cost, other than their normal compensation for the time worked.
3. Submit the proper documentation and reports to receive payment on this service. See information below:
A. Invoices and Payment
1. Payment to be made monthly, in arrears, following satisfactory performance by Contractor’s personnel and upon receipt of a properly prepared invoice.
1. Contractor shall be required to invoice through the Tungsten System at http://www.tungsten-network.com/us/en/veterans-affairs/. Additional information regarding Tungsten shall be provided upon award.
1. The contract shall have current registration in the System for Award Management (SAM) for this solicitation; URL: www.sam.gov.
1. The invoice MUST be itemized to include the following information. Any information listed below, and not provided on an invoice, will render that invoice incomplete and the invoice will be returned for immediate correction.
i. Time period being invoiced for.
ii. Description of services performed.
iii. Unit Cost billed.
iv. Extended amount due.
v. Invoice number, date, and; amount partial or full Contract and obligation numbers
“VHA Supplemental Contract Requirements for Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors”
COVID-19 Mandated Protocol (Executive Order 14042)
1. Contractor employees who work in or travel to VHA locations must comply with the following:
1. Documentation requirements:
0. If fully vaccinated, shall show proof of vaccination
0. NOTE: Acceptable proof of vaccination includes a signed record of immunization from a health care provider or pharmacy, a copy of the COVID-19 Vaccination Record Card (CDC Form MLS-319813_r, published on September 3, 2020), or a copy of medical records documenting the vaccination
0. If unvaccinated and granted a medical or religious exception, shall show negative COVID-19 test results dated within three calendar days prior to desired entry date. Test must be approved by the Food and Drug Administration (FDA) for emergency use or full approval. This includes tests available by a doctor’s order or an FDA approved over-the-counter test.
0. Documentation cited in this section shall be digitally or physically maintained on each contractor employee while in a VA facility and is subject to inspection prior to entry to VA facilities and after entry for spot inspections by Contracting Officer Representatives (CORs) or other hospital personnel.
0. Documentation will not be collected by the VA; contractors shall, at all times, adhere to and ensure compliance with federal laws designed to protect contractor employee health information and personally identifiable information.
2. Contractor employees are subject to daily screening for COVID-19 and may be denied entry to VA facilities if they fail to pass screening protocols. As part of the screening process contractors may be asked screening questions found on the following website: COVID-19 Screening Tool. Regularly check the website for updates.
1. Contractor employees who work away from VA locations, but who will have direct patient contact with VA patients shall self-screen utilizing the COVID-19 Screening Tool, in advance each day that they will have direct patient contact and in accordance with their person or persons who coordinate COVID-19 workplace safety efforts at covered contractor workplaces. Contractors shall, at all times, adhere to and ensure compliance with federal laws designed to protect contractor employee health information and personally identifiable information.
3. Contractor must immediately notify their COR or Contracting Officer if contract performance is jeopardized due to contractor employees being denied entry into VA Facilities.”
B.3 STATEMENT OF WORK-ATTACHMENT A-DRAWING
Page 1 of Page 1 of
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS
1. Bidding materials consisting of drawings and specifications are issued as attachments to this solicitation for the respective qualified General (Prime) Contractors interested in submitting bids directly to the Department of Veterans Affairs.
a) Currently there are no drawings or specifications available for this IFB. Picture is included in Statement of Work Attachment A.
2. One set of drawings and specifications may be obtained by Builders Exchanges, Chambers of Commerce, Quantity Surveyors, trade, and microfilming organizations.
b) Currently there are no drawings or specifications available for this IFB. Picture is included in Statement of Work Attachment A.
3. Bidding materials may be obtained only upon written application to the issuing office. Bidders should allow 5 working days after receipt of their request by the issuing office for reproduction, in addition to mail delivery time when requesting bidding material.
c) Currently there are no drawings or specifications available for this IFB. Picture is included in Statement of Work Attachment A.
4. While no deposit will be necessary, return of the bidding material, postage prepaid, to the issuing office within 10 days after date of opening bids will be required. In case no bid is to be submitted, the return of the bidding material, as soon as this fact has been determined and before the date of opening bids, is requested. If you decide not to bid on this project, please advise the issuing office of your reasons (the contracting officer should modify accordingly if a deposit is required).
d) Currently there are no drawings or specifications available for this IFB. Picture is included in Statement of Work Attachment A.
5. A bid guarantee is required in an amount not less than 20 percent of the bid price but shall not exceed $3,000,000. Failure to furnish the required bid guarantee in the proper form and amount, by the time set for opening of bids, will require rejection of the bid in all cases except those listed in FAR 28.101-4, and may be cause for rejection even then.
e) A bid guarantee is not required for this IFB. A contracting officer shall not require a bid guarantee unless a performance bond or a performance and payment bond is also required. 40 U.S.C. Chapter 31 Subchapter III Bonds - Requires performance and payment bonds for any construction contract exceeding $150,000.00. Cost Range Current IFB: Between $25,000 and $100,000.
6. If the contract will exceed $100,000 (see FAR 28.102-1 for lesser amount), the bidder to whom award is made will be required to furnish two bonds, a Payment Bond, SF 25A, and a Performance Bond, SF 25, each in the penal sum as noted in the General Conditions of the Specification. Copies of SFs 25 and 25A may be obtained upon application to the issuing office.
f) Performance and Payment Bonds are not required for IFB. Cost Range Current IFB: Between $25,000 and $100,000.
7. DESCRIPTION OF WORK: West Texas (WTX), Replace Domiciliary Dining Room Floor, Big Spring VA
8. Cost Range: Between $25,000 and $100,000.
9. FAR 52.222-6 Construction Wage Rate Requirements: Davis Bacon Act WD TX20230156, dated 1/6/2023 – Link: SAM.GOV
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
PREPARATION OF BIDS
To assure responsiveness of submitted bids, bidders shall follow the instructions contained herein. These instructions prescribe the format of the bid and describe the approach for development and presentation of the bid package. These instructions are designed to ensure the submission of necessary information. Bidders are required to meet all solicitation requirements, including terms and conditions, representations, and certifications. The contracting officer has determined there is a high probability of adequate price competition in this acquisition. Interested bidders shall be solely responsible for all costs associated with this solicitation including but not limited to the preparation of bids.
1. Bids shall be (1) submitted on the forms furnished by the Government or on copies of those forms; and (2) manually signed. The person signing a bid shall initial each erasure or change appearing on any proposal form.
2. Bidders shall submit proposed prices for ALL bid items as listed in the bid schedule. Failure to submit proposed prices for ALL bid items will result in the proposal being rejected as nonresponsive without further consideration.
3. Alternate bids Will NOT be considered unless this solicitation authorizes their submission.
4. The following documents shall be submitted to the Contracting Officer on the due date and time listed on the SF 1442. Electronic bids transmitted through email are the only authorized form of submission under this solicitation. One (1) emailed electronic PDF document of the bid shall be submitted at the time of the bid opening. The emailed electronic PDF document of the bid shall be organized as follows:
a) Pricing: Page 2 of the SF1442 shall be completed and signed by the signatory authority. All blocks under section “OFFER” on page 2 of SF1442 (Item 14 thru 20C) shall be completed.
b) Section B – Schedule of Prices/Description shall be completed by the offeror
c) Bidders shall be solely responsible for monitoring Government’s website www.sam.gov for amendments to this solicitation if any and acknowledge them in accordance with the requirements stipulated in this solicitation and amendments.
d) Duly executed Bid Bond/Guarantee: Bid Bond not required for this IFB.
e) 52.204-8 Annual Representations and Certifications: since 52.204-7 is incorporated by reference in this solicitation, paragraph (d) under clause 52.204-8 applies to this contract. Bidder shall check the box in front of paragraph (2)(i) under clause 52.204-8 and indicate any changes under paragraph (d) of clause 52.204-8. If no change has been made to offeror’s Online Representations and Certifications Application (ORCA), please indicate “NONE”. Print out this clause in its entirety and submit it with the bid or you can submit your on-line ORCA printout.
f) Evidence of SDVOSB Status: Copy of VetBiz Registry printout showing your firm as a verified SDVOSB or SBA Veteran Small Business Certification Program (VetCert) verification.
g) Please be advised that to be eligible for award, Offerors are required to register their businesses at http://www.vetbiz.gov/ and https://www.sam.gov/portal/public/SAM/ (Previously known as www.ccr.gov) and complete the ORCA. Bidders shall submit a printout of their ORCA.
h) Acknowledgement of Amendments
i) Failure to submit all aforementioned document (a, b, c, d, e, f, g, and h) shall result in a nonresponsive offer and the bid shall not be considered.
5. Bids shall be submitted electronically to the email address below by or on the due date set forth in this solicitation, Page 1, Form SF1442, Block 13:
a) Contracting Officer: Jennifer Stringer | Email: jennifer.stringer@va.gov
The Email Subject Line Shall Read: 36C25723B0030 WTX Replace Domiciliary Dining Room Floor - Contracting Officer Jennifer Stringer
It is solely the responsibility of the bidders to ensure the Government receives the bids before or on the exact due date and time set forth in this solicitation.
INQUIRY ON THE SOLICITATION AND DEADLINE FOR INQUIRY
1. All Questions/Inquiries about this solicitation shall be directly submitted via email to the contracting officer: jennifer.stringer@va.gov. No phone or faxed inquiry will be accepted.
2. Deadline for all Questions/Inquiries: February 22, 2023 No Later Than 11:00AM; submit all questions/inquiries via email directly to jennifer.stringer@va.gov . No phone or fax inquiries/questions will be accepted.
3. Government’s responses to inquiries will be issued in the form of Amendment(s) to be posted on the same website where this solicitation is posted: www.sam.gov. All interested bidders including those submitting inquiries are required to monitor the above website for any posted amendments and acknowledge them in accordance with the instructions provided in the amendments as well as in this solicitation.
BID OPENING
1. A public Bid Opening will not be held. Bids shall be opened by the Contracting Officer and Contract Specialist, witnessed, and recorded on an official Bid Abstract. Bid Abstracts will be available upon request via email to: jennifer.stringer@va.gov
BID EVALUATION
1. All bids submitted on time and in accordance with provision 52.214-5 will be evaluated for the conformance to all requirements of this solicitation. Any bid that fails to conform to the requirements of this solicitation will be determined non-responsive and therefore rejected.
2. Bid prices will be evaluated as follows:
a) For the purpose of determining the low bid conforming to the solicitation, the Government will evaluate the proposed total schedule bid items and make an award on the proposed total schedule bid items to the bidder whose bid conforms to this solicitation and is deemed the most advantageous to the Government.
BASIS FOR CONTRACT AWARD
1. Award will be made to the lowest responsible bidder whose bid conforms to this solicitation and is deemed the most advantageous to the Government, considering only price and price-related factors specified in this solicitation.
2. Award will be made in accordance with provision 52.214-19 Contract Award—Sealed Bidding—Construction incorporated by reference in this solicitation.
3. Determination of Responsibility:
a) Pursuant to FAR 9.103 prescribing that purchases shall be made from, and contracts shall be awarded to, responsible prospective contractors only, the Government will perform the determination of responsibility on the apparently lowest bidder whose bid is deemed conforming to the solicitation as stated under paragraph a). The Government’s determination of responsibility will be performed in accordance with FAR 9.1 and will include but not limited to the review of all federal excluded or debarred lists from different U.S. departments, and from the Federal Awardee Performance and Integrity Information System (FAPIIS), available at www.ppirs.gov.
b) Since this solicitation is set aside 100% for Service-Disabled Veteran-Owned Small Business (SDVOSB), the Government will refer the matter to the Small Business Administration which will decide whether to issue a Certificate of Competency if the Government deems a potential SDVOSB awardee nonresponsible.
2.1 52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm Fixed Price contract resulting from this solicitation.
(End of Provision)
2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
(End of Provision)
2.3 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
| Goals for minority participation for each trade |
| Goals for female participation for each trade |
| 47.8 % |
| 6.9 % |
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the—
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Howard County
(End of Provision)
2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)
(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers.
(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
(End of Provision)
2.5 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for—
2/27/2023, 11:00 AM CST
(c) Participants will meet at— 300 Veterans BLVD, BLDG 3, Room 10, Big Spring, TX 79720
(d) POC: Eric Landrum at eric.landrum@va.gov , phone: 432-816-8840 (End of Provision)
2.6 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
http://www.acquisition.gov/far/index.html http://www.va.gov/oal/library/vaar/
(End of Provision)
| FAR Number |
| Title |
| Date |
| 52.204-7 |
| SYSTEM FOR AWARD MANAGEMENT |
| OCT 2018 |
| 52.204-16 |
| COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING |
| AUG 2020 |
| 52.204-22 |
| ALTERNATIVE LINE ITEM PROPOSAL |
| JAN 2017 |
| 52.214-3 |
| AMENDMENTS TO INVITATIONS FOR BIDS |
| DEC 2016 |
| 52.214-4 |
| FALSE STATEMENTS IN BIDS |
| APR 1984 |
| 52.214-5 |
| SUBMISSION OF BIDS |
| DEC 2016 |
| 52.214-6 |
| EXPLANATION TO PROSPECTIVE BIDDERS |
| APR 1984 |
| 52.214-7 |
| LATE SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS |
| NOV 1999 |
| 52.214-18 |
| PREPARATION OF BIDS—CONSTRUCTION |
| APR 1984 |
| 52.214-19 |
| CONTRACT AWARD—SEALED BIDDING—CONSTRUCTION |
| AUG 1996 |
| 52.214-34 |
| SUBMISSION OF OFFERS IN THE ENGLISH LANGUAGE |
| APR 1991 |
| 52.214-35 |
| SUBMISSION OF OFFERS IN U.S. CURRENCY |
| APR 1991 |
2.7 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018)
(a) Any protest filed by an interested party shall—
(1) Include the name, address, fax number, email and telephone number of the protester;
(2) Identify the solicitation and/or contract number;
(3) Include an original signed by the protester or the protester’s representative and at least one copy;
(4) Set forth a detailed statement of the legal and factual grounds of the protest, including a description of resulting prejudice to the protester, and provide copies of relevant documents;
(5) Specifically request a ruling of the individual upon whom the protest is served;
(6) State the form of relief requested; and
(7) Provide all information establishing the timeliness of the protest.
(b) Failure to comply with the above may result in dismissal of the protest without further consideration.
(c) Bidders/offerors and Contracting Officers are encouraged to use alternative dispute resolution (ADR) procedures to resolve protests at any stage in the protest process. If ADR is used, the Department of Veterans Affairs will not furnish any documentation in an ADR proceeding beyond what is allowed by the Federal Acquisition Regulation.
(End of Provision)
2.8 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)
(a) As an alternative to filing a protest with the Contracting Officer, an interested party may file a protest by mail or electronically with: Executive Director, Office of Acquisition and Logistics, Risk Management and Compliance Service (003A2C), Department of Veterans Affairs, 810 Vermont Avenue NW, Washington, DC 20420 or Email: EDProtests@va.gov.
(b) The protest will not be considered if the interested party has a protest on the same or similar issue(s) pending with the Contracting Officer.
(End of Provision)
REPRESENTATIONS AND CERTIFICATIONS
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAY 2022) (JUL 2020) (DEVIATION) (a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 238330.
(2) The small business size standard is $16.5 Million.
(3) The small business size standard for a concern that submits an offer, other than on a construction or service acquisition, but proposes to furnish an end item that it did not itself manufacture, process, or produce is 500 employees if the acquisition—
(i) Is set aside for small business and has a value above the simplified acquisition threshold;
(ii) Uses the HUBZone price evaluation preference regardless of dollar value, unless the offeror waives the price evaluation preference; or
(iii) Is an 8(a), HUBZone, service-disabled veteran-owned, economically disadvantaged women-owned, or women-owned small business set-aside or sole-source award regardless of dollar value.
(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.
(2) If the provision at 52.204–7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:
[ ] (i) Paragraph (d) applies.
[ ] (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.
(c)(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:
(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—
(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;
(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or
(C) The solicitation is for utility services for which rates are set by law or regulation.
(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.
(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements—Representation. This provision applies to all solicitations.
(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.
(v) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—
(A) Are not set aside for small business concerns;
(B) Exceed the simplified acquisition threshold; and
(C) Are for contracts that will be performed in the United States or its outlying areas.
(vi) 52.204-26, Covered Telecommunications Equipment or Services—Representation. This provision applies to all solicitations.
(vii) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations—Representation.
(viii) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.
(ix) 52.209-11, Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law. This provision applies to all solicitations.
(x) 52.214-14, Place of Performance—Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.
(xi) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.
(xii) 52.219-1, Small Business Program Representations (Basic, Alternates I, and II). This provision applies to solicitations when the contract is for supplies to be delivered or services to be performed in the United States or its outlying areas, or when the contracting officer has applied part 19 in accordance with 19.000(b)(1)(ii).
(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.
(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.
(C) The provision with its Alternate II applies to solicitations that will result in a multiple-award contract with more than one NAICS code…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .