This solicitation is for construction services to reconfigure an existing basement area at the Dallas VA Medical Center to serve as an overflow COVID-19 patient waiting area and to replace the HVAC system. Key requirements include demolishing and removing existing structures and systems; installing new partitions, finishes, structural elements, MEP systems, and site work; and conducting infection prevention measures. The total budget is between $2-5 million. The North American Industry Classification code is 236220 and the period of performance is 365 calendar days. The opportunity is set aside 100% for Service-Disabled Veteran-Owned Small Businesses. The pre-bid site visit will be held on a specified date and contractors must comply with various documentation requirements regarding COVID-19 vaccination or testing status. The response due date is also provided.

View the file

Other files

File Type Posted
site visit no 3 549-21-400.pdf PDF
36C25723B0019 0004.docx DOCX document
RFIs-23B0019 (001).docx DOCX document
BLDG6 asbestos.pdf PDF
36C25723B0019 0003.docx DOCX document
second visit 549-21-400 012623.pdf PDF
36C25723B0019 0002.docx DOCX document
36C25723B0019 0001.docx DOCX document
signin sheet 549-21-400.pdf PDF
549-21-400 BID Drawings.pdf PDF
549-21-400 Bound Specifications.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. SOLICITATION NUMBER

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

6. PROJECT NUMBER

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

a. NAME

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)

STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES

NO

a.

Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b.

An offer guarantee is, is not required.

c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

36C25723B0019 X 12-29-2022

TBD

549-21-400 Department of Veterans Affairs Central Texas Veterans HCS 1901 Veterans Memorial Dr. Building #171 Temple

TX

76504 Department of Veterans Affairs Central Texas Veterans HCS 1901 Veterans Memorial Dr. Building 171 Temple

TX

76504 Rhonda Richardson none Acquisition Title: TO CONSTRUCT COVID 19 WAITING AREA AND HVAC BUILDBACK

Contractor shall provide all necessary labor, materials, equipment, and supervision to complete all required project work in accordance with the provided SOW, Specifications, and Drawings. Project is located at the VANTHCS hospital grounds, 4500 S Lancaster Rd., Dallas, TX 75216

This is a "Competitive" requirement Set Aside 100% Service Disabled Veteran Owned Small Business (SDVOSB).

Magnitude of the Construction Project: $2 Mil to $5 Mil per VAAR 836.204 The applicable North American Industry Classification System (NAICS) code for this project is 236220 ($39.5 Mil)

Pre-Bid Site Visit shall be held on January 10, 2023 at 1000CST. All interested Contactors shall meet at the VANTHCS hospital grounds, Building 6, 4500 S Lancaster Rd., Dallas, TX 75216

All Contractors attending the Pre-Bid Site Visit may be required to be COVID Screened to enter the facility. Please ensure you arrive early to allow enough time to go through screening. Face Masks and picture ID is required.

Cut off for submission of RFI(s)/Questions shall be January 16, 2023 @ 2:00 PM CST. All RFI(s)/Questions must be emailed to the following email: rhonda.richardson5@va.gov. Please include the solicitation number on the subject line. RFI(s)/Questions must be submitted in word format.

All Bidders must submit a Bid Guarantee as part of their Bid Package. Additionally, the Awardee must be able to obtain the necessary level of Performance and Payment Bonds.

SUBMISSION OF BIDS: All bids shall be submitted via email to the following email address: rhonda.richardson5@va.gov by the date and time as stated in Block 13a below. Please include the solicitation number on the subject line of your email when submitting your bid package.

**All Contractors are required to comply with EO 14042 regarding COVID vaccines.

Note: All Bidders must comply with submission of the required documentation as stated on Page 16, Standard of Responsibility.

Funds are not currently available for this solicitation. Award of a contract as a result of this solicitation is contingent upon the availability of appropriated funds from which payment of this contract may be made.

There shall be no legal liability on the part of the Government for contract purposes until funds are made available to the Contracting Officer. The Contracting Officer will confirm availability of funds prior to award of a contract.

X X 52.211-10 X 10:00

CST

02-03-2023 X

14. NAME AND ADDRESS OF OFFEROR

15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (

26. ADMINISTERED BY

27. PAYMENT WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

Department of Veterans Affairs Central Texas Veterans HCS 1901 Veterans Memorial Dr. Building 171 Temple

TX

76504 This is accomplished through the Tungsten Network located at:

http://www.fsc.va.gov/einvoice.asp This is mandatory and the sole method for submitting invoices.

(877) 353-9791

(512) 460-5540

Table of Contents

PART I - THE SCHEDULE1
SECTION A - SOLICITATION/CONTRACT FORM1
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)1
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK2
SCHEDULE OF PRICES/DESCRIPTION6
Bid Submission Instructions6
VHA Supplemental Contract Requirements for Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors6
SPECIAL STANDARD OF RESPONSIBILITY7
OSHA -EMR Requirement8
INSTRUCTIONS FOR CALCULATION OF SELF-PERFORMED WORK IAW “Limitations on Subcontracting” (VAAR 852.219-73)8
STATEMENT OF WORK9
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS34
2.1 52.216-1 TYPE OF CONTRACT (APR 1984)34
2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014)34
2.3 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)34
2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)35
2.5 52.228-1 BID GUARANTEE (SEP 1996)36
2.6 52.233-2 SERVICE OF PROTEST (SEP 2006)37
2.7 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)38
2.8 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)38
2.9 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009)39
2.10 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)39
2.11 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018)39
REPRESENTATIONS AND CERTIFICATIONS41
3.1 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)41
3.2 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)43
3.3 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—CERTIFICATION (NOV 2021)45
GENERAL CONDITIONS48
4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014)48
4.2 52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB AND OTHER COVERED ENTITIES (NOV 2021)48
4.3 52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)49
4.4 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)50
4.5 52.211-18 VARIATION IN ESTIMATED QUANTITY (APR 1984)50
4.6 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (OCT 2022)51
4.7 52.222-35 EQUAL OPPORTUNITY FOR VETERANS (JUN 2020)53
4.8 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT (DEC 2010)54
4.9 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022)55
4.10 SUPPLEMENTAL INSURANCE REQUIREMENTS60
4.11 52.236-4 PHYSICAL DATA (APR 1984)61
4.12 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)61
4.13 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUN 2020)63
4.14 52.236-14 AVAILABILITY AND USE OF UTILITY SERVICES (APR 1984)64
4.15 52.236-16 QUANTITY SURVEYS (APR 1984) ALTERNATE I (APR 1984)64
852.219-73 VA Notice of Total Set-Aside for Verified Service-Disabled Veteran-Owned Small Businesses.65
4.16 VAAR 852.219-75 SUBCONTRACTING COMMITMENTS MONITORING AND COMPLIANCE (JUL 2018)69
4.17 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)69
4.18 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019)71
4.19 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)72
4.20 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)72
4.21 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020)72
4.22 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020)74
4.23 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019)74
4.24 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008)75
4.25 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)76
4.26 VAAR 852.246-75 WARRANTY OF CONSTRUCTION—GUARANTEE PERIOD SERVICES (OCT 2018)76
4.27 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008)76
4.28 VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (WITHOUT NAS– CPM) (NOV 2018)76

SCHEDULE OF PRICES/DESCRIPTION

Construction Building 6 Covid-19/HVAC Build back Project No. 549-21-400

DESCRIPTION: The Contractor shall provide all labor, supervision, materials, and equipment to complete all required project work in strict accordance with the SOW, Specifications, and Drawings to construct COVID 19 waiting area and HVAC build back, Project No. 549-21-400, located at the VANTHCS hospital grounds, 4500 S Lancaster Rd., Dallas, TX 75216.

BID ITEM(s):

ITEMUNITTOTAL
NO.DESCRIPTION OF SERVICEQTYPRICEAMOUNT
0001PROVIDE ALL NECESSARY LABOR,1 JB$____________ $___________
MATERIALS, SUPPLIES, TOOLS,
EQUIPMENT, AND SUPERVISION
NECESSARY TO CONSTRUCT COVID 19
WATING ARE AND HVAC BUILDBACK IAW
SOW, SPECIFICATIONS AND DRAWINGS
0002COST OF PERFORMANCE AND1 EA $____________ $___________
PAYMENT BONDS

BASE BID TOTAL (Line Items 0001 & 0002) $_____________

TOTAL PROJECT DURATION for Base Bid: 365 Calendar days from issuance of the Notice to Proceed to complete the project work.

Bid Submission Instructions

A. All bid packages shall be submitted via email to the following email address: rhonda.richardson5@va.gov, by the specified Bid Closing date and time as stated on the SF1442, Page 1, Block 13a. The applicable Solicitation Number for this IFB must be included on the subject line of the email.

B. A public Bid Opening will not be held. Bids shall be opened by the Contracting Officer and Contract Specialist, witnessed, and recorded on an official Bid Abstract. Bid Abstracts will be available upon request via email.

VHA Supplemental Contract Requirements for Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors

1. Contractor employees who work in or travel to VHA locations must comply with the following:

a. Documentation requirements:

1) If fully vaccinated, shall show proof of vaccination.

i. NOTE: Acceptable proof of vaccination includes a signed record of immunization from a health care provider or pharmacy, a copy of the COVID-19 Vaccination Record Card (CDC Form MLS-319813_r, published on September 3, 2020), or a copy of medical records documenting the vaccination.

2) If unvaccinated and granted a medical or religious exception, shall show negative COVID-19 test results dated within three calendar days prior to desired entry date. Test must be approved by the Food and Drug Administration (FDA) for emergency use or full approval. This includes tests available by a doctor’s order or an FDA approved over-the-counter test.

3) Documentation cited in this section shall be digitally or physically maintained on each contractor employee while in a VA facility and is subject to inspection prior to entry to VA facilities and after entry for spot inspections by Contracting Officer Representatives (CORs) or other hospital personnel.

4) Documentation will not be collected by the VA; contractors shall, at all times, adhere to and ensure compliance with federal laws designed to protect contractor employee health information and personally identifiable information.

2. Contractor employees are subject to daily screening for COVID-19 and may be denied entry to VA facilities if they fail to pass screening protocols. As part of the screening process contractors may be asked screening questions found on the COVID-19 Screening Tool. Check regularly for updates.

a. Contractor employees who work away from VA locations, but who will have direct contact with VA patients shall self-screen utilizing the COVID-19 Screening Tool, in advance, each day that they will have direct patient contact and in accordance with their person or persons who coordinate COVID-19 workplace safety efforts at covered contractor workplaces. Contractors shall, at all times, adhere to and ensure compliance with federal laws designed to protect contractor employee health information and personally identifiable information.

3. Contractor must immediately notify their COR or Contracting Officer if contract performance is jeopardized due to contractor employees being denied entry into VA Facilities.

SPECIAL STANDARD OF RESPONSIBILITY

Solicitation Submittal Requirements:

The Offeror shall submit the following information as part of your Bid Package: (For a partnership or joint venture, the following submittal requirements are required for each Contractor who is part of the partnership or joint venture and for the entity itself., EMR shall not be submitted for subcontractors.)

1. OSHA or EPA Violation(s): Offerors shall provide Summary of Work-Related Injuries and Illnesses, affirming that the Offeror has no more than three serious, or one repeat, or one willful OSHA or EPA violation(s) in the past 3 years.

2. Experience Modification Rate (EMR): Offerors shall provide documentation to show that the offeror has an Experience Modification Rate (EMR) of equal to or less than 1.0.

3. Limitation on Subcontracting:

IAW VAAR 852.219-75 each offeror will review the clause and complete the certificate included in the clause. This certificate will be complete prior to solicitation closing and submitted with the proposal, bid, or quote documents. Failure to comply with this requirement will result in removal from consideration for award.

Page 1 of Page 1 of OSHA -EMR Requirement OSHA or EPA Violation(s):

(1) Offerors shall provide Summary of Work-Related Injuries and Illnesses, affirming that the

(2) Offeror has no more than three serious, or one repeat, or one willful OSHA or EPA violation(s) in the past 3 years Experience Modification Rate (EMR):

(1) Offerors shall provide documentation to show that the offeror has an Experience Modification Rate (EMR) of equal to or less than 1.0.

INSTRUCTIONS FOR CALCULATION OF SELF-PERFORMED WORK IAW “Limitations on Subcontracting” (VAAR 852.219-73)

OFFEROR’S SELF PERFORMED ESTIMATED CALCULATIONS

At the time of proposal Offeror’s are required to complete.

1. Offeror’s total proposed price: $ __________

1. Cost of Materials $ __________

1. Total excluding materials (a-b) $ __________

1. Amount projected to be paid to non-VIP listed SDVOSBs: $ __________

1. Offeror’s percentage of estimated Non VIP work (d/c X 100 = %) __________%

1. Offeror’s percentage of estimated self-performed work (100 – e = %) __________%

A/E-Services. In the case of a contract for services (except construction), it will not pay more than 50% of the amount paid by the government to it to firms that are not VIP-listed VOSBs.

General construction. In the case of a contract for general construction, it will not pay more than 85% of the amount paid by the government to it to firms that are not VIP-listed SDVOSBs.

Special trade contractors. In the case of a contract for special trade contractors, it will not pay more than 75% of the amount paid by the government to it to firms that are not VIP-listed SDVOSBs

STATEMENT OF WORK

Project: Building 6 Covid 19 waiting area and HVAC build back.

Project No. 549-21-400

I. GENERAL SCOPE OF WORK

The project purpose is to reconfigure 1700sf of existing basement to facilitate the COVID-19 patient overflow waiting area for processing. This project will replace the HVAC system with Government furnished equipment as noted on the drawings, which will include primarily the air handlers, and controls, support systems, ancillary equipment such as ductwork, grills, and insulation will also be replaced as determined necessary. This project will include asbestos abatement as necessary to replace the identified mechanical systems. This project will also provide renovations as required to create isolation spaces that are able to be used for infectious patients and pandemic care. The Contractor will provide a Phasing Plan and Schedule which reflects the least impact on the daily operations of Building 6 services. Fire sprinkler system will be extended to all areas for complete coverage.

II. BACKGROUND:

The project is located at 4500 S Lancaster Rd., Dallas, TX 75216. Building 6 is located on the VANTHCS hospital grounds – west of building 5 and TT-49 originally built in 1939 and refreshed in 1968. The basement of this historic building will be reconfigured to provide a waiting area for COVID-19 patients waiting to be processed. To this end the Building 6 will be brought to a level to provide this service safely.

III. STATEMENT OF PROJECT OBJECTIVES:

This statement of work will describe the work required to re-purpose portion of the historic building 6 to accommodate the overflow of COVID-19 patients. The building must meet all current requirements of VA design guidelines, VA Electronic Health Record Management standards, VA Physical Security Design Manual, NFPA, International Building Codes, ASHREA, and any applicable state or local codes. The project objectives are as follows:

1.1 GENERAL INTENTION

A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, utilities, vegetation, site fixtures, and paving; excavation; demolition and removal of interior construction, including partitions, floor slabs for metal building being demolished, doors, frames, hardware, windows, equipment and fixtures ; demolition of wall, floor, and ceiling finishes; demolition and removal of mechanical, electrical, and plumbing systems and components; construction of new partitions, frames, doors, hardware, glass, glazing, windows, storefront systems, railings, screens, millwork/casework, and thermal and moisture protection ; new wall, ceiling and floor finishes; new structural framing, floors and roof; new structural carbon fiber reinforcement; sitework, including utilities, landscaping, irrigation, sidewalks, and other paving; new MEP systems and subsystems (both interior and exterior); new interior and exterior signage; including but not limited to the following: building access control system, CCTV, cable TV, window coverings, IT and phone equipment, casework/millwork in offices, blood draw; break room equipment, equipment for conference room. Contractor shall furnish labor and materials and perform work as required by drawings, specifications, and addenda.

B. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the Project Manager/Contracting Officer’s Representative (PM/COR) in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three workdays unless otherwise designated by the PM/COR. Any reference within bid documents to Resident Engineer shall be equal to the position of PM/COR.

C. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access. All General Contractor personnel including Sub-Contractors will have to attend a Safety Orientation Meeting to be coordinated through the PM/COR

D. Prior to commencing work, general contractor shall provide proof that a OSHA certified “competent person” (CP) (29 CFR 1926.20(b)(2) will maintain a presence at the work site whenever the general or subcontractors are present.

E. Training:

1. All employees of general contractor or subcontractors shall have the 10-hour certified Construction Safety course and supervisors or other “competent person” shall have the 30-hour certified course per OSHA requirements.

2. Submit training records of all such employees for approval before the start of work.

F. Applicable Documents:

1. The following laws, regulations, policies, and procedures in effect on date of contract issuance and all subsequent changes or updates apply:

a. Federal Acquisition Regulation

b. Veterans Administration Acquisition Regulation

c. Service Contract Act (SCA) Directory of Occupations (Fifth Edition) http://www.dol.gov/whd/contracts/sca.htm

d. ANSI: https://pdflakekxng.files.wordpress.com/2015/04/ansi-z133-safety-standard-pdf.pdf

e. VA Directive 0058- VA Green Purchasing Program

f. VA Directive 0057- VA Environmental Program

g. Master Construction Specification: https://www.cfm.va.gov/TIL/spec.asp#03

2. Glossary: Acronyms used in this SOW are listed below for easy reference:

a. CO Contracting Officer

b. COR Contracting Officer’s Representative

c. FAR Federal Acquisition Regulation

d. CFM Construction & Facilities Management

e. VA Veteran Affairs

f. EPA Environmental Protection Agency

g. PPE Personal Protective Equipment

h. SOW Statement of Work

i. OSHA Occupational Safety and Health Administration

j. NEC National Electrical Code

k. NTP Notice to Proceed

1.2 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. AFTER AWARD OF CONTRACT, .pdf files of the specifications and drawings will be available for the contractors use to produce hardcopies as needed. The hardcopy production will be at the Contractor's expense. Any sets returned to the Contracting Officer by unsuccessful bidders will be made available for the awarded contractor’s use.

1.3 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.

2. For working outside the “regular hours” as defined in the contract, The General Contractor shall give 3day notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.

3. No photography of VA premises is allowed without written permission of the Contracting Officer.

4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of an emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.

C. Key Control:

1. The General Contractor shall provide duplicate keys and lock combinations to the PM/COR for the purpose of security inspections of every area of project including toolboxes and parked machines and take any emergency action including safety review.

2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See Section 08 71 00, DOOR HARDWARE and coordinate.

3. The Contractor will be financially responsible for any loss of assigned keys/ key cards by the government.

D. Document Control:

1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.

2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.

3 Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”. Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.

4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting Officer.

5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.

6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.

7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document Management Software (EDMS).

a. Security, access, and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.

b. “Sensitive information” including drawings and other documents may be attached to email provided all VA encryption procedures are followed.

E. Motor Vehicle Restrictions

1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.

2. Separate permits shall be issued for General Contractor and its employees for parking in designated areas only.

1.4 FIRE SAFETY

A. Applicable Publications: Publications listed below form part of this Article to extent referenced. Use Latest Standards

Publications are referenced in text by basic designations only.

1. American Society for Testing and Materials (ASTM):

E84-2008..............................Surface Burning Characteristics of Building Materials

2. National Fire Protection Association (NFPA): Use Latest Standards as of NTP 10-2006................................Standard for Portable Fire Extinguishers 30-2007................................Flammable and Combustible Liquids Code 51B-2003..............................Standard for Fire Prevention During Welding, Cutting and Other Hot Work 70-2007................................National Electrical Code 241-2004..............................Standard for Safeguarding Construction, Alteration, and Demolition Operations

3. Occupational Safety and Health Administration (OSHA):

29 CFR 1926........................Safety and Health Regulations for Construction

B. Fire Safety Plan: Establish and maintain a fire protection program in accordance with 29 CFR 1926. Prior to start of work, prepare a plan detailing project-specific fire safety measure, including periodic status reports, and submit to PM/CR and Facility Safety Officer for review for compliance with contract requirements in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA AND SAMPLES Prior to any worker for the contractor or subcontractors beginning work, they shall undergo a safety briefing provided by the general contractor’s competent person per OSHA requirements. This briefing shall include information on the construction limits, VAMC safety guidelines, means of egress, break areas, work hours, locations of restrooms, use of VAMC equipment, etc. Documentation shall be provided to the PM/COR that individuals have undergone contractor’s safety briefing.

C. Site and Building Access: Maintain free and unobstructed access to facility emergency services and for fire, police and other emergency response forces in accordance with NFPA 241.

D. Separate temporary facilities, such as trailers, storage sheds, and dumpsters, from existing buildings and new construction by distances in accordance with NFPA 241. For small facilities with less than 6 m (20 feet) exposing overall length, separate by 3m (10 feet).

E. Temporary Heating and Electrical: Install, use and maintain installations in accordance with 29 CFR 1926, NFPA 241 and NFPA 70.

F. Means of Egress: Do not block exiting for occupied buildings, including paths from exits to roads. Minimize disruptions and coordinate with PM/COR and facility Safety Officer.

G. Egress Routes for Construction Workers: Maintain free and unobstructed egress. Inspect daily. Report findings and corrective actions weekly to PM/COR and facility Safety Officer.

H. Fire Extinguishers: Provide and maintain extinguishers in construction areas and temporary storage areas in accordance with 29 CFR 1926, NFPA 241 and NFPA 10.

I. Flammable and Combustible Liquids: Store, dispense and use liquids in accordance with 29 CFR 1926, NFPA 241 and NFPA 30.

J. Hot Work: Perform and safeguard hot work operations in accordance with NFPA 241 and NFPA 51B. Coordinate with PM/COR. Obtain permits from facility Safety Officer at least 24 hours in advance. Designate contractor's responsible project-site fire prevention program manager to permit hot work.

K. Fire Hazard Prevention and Safety Inspections: Inspect entire construction areas weekly.

Coordinate with, and report findings and corrective actions weekly to PM/COR and facility Safety Officer.

L. Smoking: Smoking is prohibited on VA Facility Including Grounds.

M. Dispose of waste and debris in accordance with NFPA 241. Remove from buildings daily.

N. Perform other construction, alteration, and demolition operations in accordance with 29 CFR 1926.

O. If required, submit documentation to the PM/COR that personnel have been trained in the fire safety aspects of working in areas with impaired structural or compartmentalization features.

1.5 OPERATIONS AND STORAGE AREAS

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers, and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting Officer, the buildings and utilities may be abandoned and need not be removed.

C. The Contractor shall, under regulations prescribed by the Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

D. Working space and space available for storing materials shall be as shown on the drawings and/or as determined by the PM/COR.

E. Workmen are subject to rules of Medical Center applicable to their conduct.

F. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by PM/COR where required by limited working space.

1. Do not store materials and equipment in other than assigned areas.

2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of Veterans Affairs in quantities sufficient for not more than two workdays. Provide unobstructed access to Medical Center areas required to remain in operation.

3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.

G. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by PM/COR. All such actions shall be coordinated with the Utility Company involved:

1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.

H. The building defined herein will be unoccupied during the performance of work by the Contractor.

I. Construction Fence: If Construction fencing around building is erected the contractor will provide a safe and secure access way to the Building for Staff and Veterans. Contractor to coordinate with the PM/COR. Chain link construction fence, 2.1m (seven feet) minimum height, Bottom of fences shall extend to 25mm (one inch) above grade. Remove the fence when directed by PM/COR. Reference section 32 31 13 Chain Link Fences and Gates for more detailed information on the construction fencing.

J. When an area within the building is turned over to Contractor, Contractor shall accept entire responsibility, therefore.

1. Contractor shall always maintain a minimum temperature of 4 degrees C (40 degrees F), except as otherwise specified.

2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from Contractor's employee or watchman.

K. Utilities Services: always maintain existing utility services for Medical Center. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by PM/COR.

1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of PM/COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 27 05 11 REQUIREMENTS FOR COMMUNICATIONS INSTALLATIONS and 28 05 11, REQUIREMENTS FOR ELECTRONIC SAFETY AND SECURITY INSTALLATIONS for additional requirements.

2. Contractor shall submit a request to interrupt any such services to PM/COR, in writing, 48 hours in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.

3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center.

Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.

4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the PM/COR.

5. In case of a contract construction emergency, service will be interrupted on approval of PM/COR. Such approval will be confirmed in writing as soon as practical.

6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.

L. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged-in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.

M. To minimize interference of construction activities with flow of Medical Center traffic, comply with the following:

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Wherever excavation for new utility lines cross existing roads, at least one lane must be always open to traffic.

2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the PM/COR.

N. Coordinate the work for this contract with other construction operations as directed by PM/COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.

1.6 INFECTION PREVENTION MEASURES

A. Implement the requirements of VAMC’s Infection Control Risk Assessment (ICRA) team. ICRA Group may monitor dust in the vicinity of the construction work and require the Contractor to take corrective action immediately if the safe levels are exceeded.

B. Establish and maintain a dust control program as part of the contractor’s infection preventive measures in accordance with the guidelines provided by ICRA Group as specified here. Prior to start of work, prepare a plan detailing project-specific dust protection measures, including periodic status reports, and submit to Resident Engineer and Facility ICRA team for review for compliance with contract requirements in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA AND SAMPLES.

1. All personnel involved in the construction or renovation activity shall be educated and trained in infection prevention measures established by the medical center.

C. Medical center Infection Control personnel shall monitor for airborne disease (e.g., aspergillosis) as appropriate during construction. A baseline of conditions may be established by the medical center prior to the start of work and periodically during the construction stage to determine impact of construction activities on indoor air quality. In addition:

1. The RE and VAMC Infection Control personnel shall review pressure differential monitoring documentation to verify that pressure differentials in the construction zone and in the patient care rooms are appropriate for their settings. The requirement for negative air pressure in the construction zone shall depend on the location and type of activity. Upon notification, the contractor shall implement corrective measures to restore proper pressure differentials as needed.

2. In case of any problem, the medical center, along with assistance from the contractor, shall conduct an environmental assessment to find and eliminate the source.

D. In general, following preventive measures shall be adopted during construction to keep down dust and prevent mold.

1. Dampen debris to keep down dust and provide temporary construction partitions in existing structures were directed by PM/COR.

E. Final Cleanup:

1. Upon completion of project, or as work progresses, remove all construction debris from above ceiling, vertical shafts and utility chases that have been part of the construction.

2. Perform HEPA vacuum cleaning of all surfaces in the construction area. This includes walls, ceilings, cabinets, furniture (built-in or free standing), partitions, flooring, etc.

3. All new air ducts shall be cleaned prior to final inspection.

1.7 DISPOSAL AND RETENTION

A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows Coordinate with COR and GEMS Manager:

1. Reserved items which are to remain property of the Government are noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items were directed by

PM/COR.

2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.

3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.

4. PCB Transformers and Capacitors: The Contractor shall be responsible for disposal of the Polychlorinated Biphenyl (PCB) transformers and capacitors. The transformers and capacitors shall be taken out of service and handled in accordance with the procedures of the Environmental Protection Agency (EPA) and the Department of Transportation (DOT) as outlined in Code of Federal Regulation (CFR), Titled 40 and 49 respectively. The EPA's Toxic Substance Control Act (TSCA) Compliance Program Policy Nos. 6-PCB-6 and 6-PCB-7 also apply. Upon removal of PCB transformers and capacitors for disposal, the "originator" copy of the Uniform Hazardous Waste Manifest (EPA Form 8700-22), along with the Uniform Hazardous Waste Manifest Continuation Sheet (EPA Form 8700-22A) shall be returned to the Contracting Officer who will annotate the contract file and transmit the Manifest to the Medical Center's Chief.

a. Copies of the following listed CFR titles may be obtained from the Government Printing Office:

40 CFR 261 ...................Identification and Listing of Hazardous Waste 40 CFR 262 ...................Standards Applicable to Generators of Hazardous Waste 40 CFR 263 ...................Standards Applicable to Transporters of Hazardous Waste 40 CFR 761 ...................PCB Manufacturing, Processing, Distribution in Commerce, and use Prohibitions 49 CFR 172 ...................Hazardous Material tables and Hazardous Material Communications Regulations 49 CFR 173 ...................Shippers - General Requirements for Shipments and Packaging 49 CRR 173...................Subpart A General 49 CFR 173 ...................Subpart B Preparation of Hazardous Material for Transportation 49 CFR 173 ...................Subpart J Other Regulated Material; Definitions and Preparation TSCA.............................Compliance Program Policy Nos. 6-PCB-6 and 6-PCB-7

Expectation: All projects and project designs shall contain language that addresses all applicable EOSH requirements see Regulatory Compliance- EOSH requirements for work performed at the above location can be found in:

a. Volume 29 of the Code of Federal Regulations, Part 1910- Occupational Safety for General industry.

b. Volume 29 of the Code of Federal Regulations, Part 1926- Occupational Safety for the Construction Industry.

c. Volume 40 of Code of Federal Regulations, Protecting of the Environment.

d. Volume 49 of the Code of Federal Regulations, Part 397- Transportation of Hazardous Materials.

Specification: The VA Master Construction Specification contains work procedures and material requirements designed to meet regulatory compliance requirements. Whenever possible, the Master Construction Specification must be used as the basis for the project designs.

6. Contractor and Subcontractor to following specifications:

a. 00 11 21 Request for Proposal to Design Build

b. 01 00 00 General Requirements

c. 01 32 16.17 Project Schedules Small Projects – Design-Build

d. 01 33 23 Shop Drawings, Product Data, and Samples

e. 01 35 26 Safety Requirements

f. 01 42 19 Reference Standards

g. 02 21 13 Site Surveys

h. 03 30 00 Cast-in-Place Concrete

i. 09 06 00 Schedule for Finishes

j. 26 05 11 Requirements for Electrical Installations

k. 26 05 19 Low-Voltage Electrical Power Conductors and Cables

l. 26 05 26 Grounding and Bonding for Electrical Systems

m. 26 05 33 Raceway and Boxes for Electrical Systems

n. 26 05 41 Underground Electrical Construction

o. 26 09 23 Lighting Controls

p. 26 56 00 Exterior Lighting

q. 28 23 00 Video Surveillance

r. 31 20 00 Earthwork

s. 32 05 23 Cement and Concrete for Exterior Improvements

t. 32 17 23 Pavement Markings

u. 32 31 40 High Security Fences and Gates

1.8 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS

A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.

B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor. (FAR 52.236-9)

C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and "Operations and Storage Areas" for additional instructions concerning repair of damage to…