This is a Request for Information (RFI) document containing 35 questions and answers related to federal solicitation 36C25627Q0087 for turn-key chiller equipment purchase and installation at a Department of Veterans Affairs facility in Pineville, Louisiana (Rapides Parish). The project involves removing and replacing an existing chiller system serving the surgery department at the VA medical center.
Key project requirements include: a superintendent must be provided by the prime contractor and be 100% full-time dedicated whenever work is performed on-site; the contractor may propose one qualified individual to serve as both superintendent and Site Safety Health Officer if applicable safety requirements necessitate the position; the contractor is responsible for all hazardous material compliance and notification if asbestos or lead-based paint is encountered; no Interim Containment and Restoration Area (ICRA) requirements have been identified, though facility infection-control requirements must be maintained; all state and local sales or use taxes must be included in the bid with no tax exemption available; wage determination LA20260051 for Rapides Parish applies; the contract is a firm-fixed-price lump-sum item (CLIN 0001) with progress payments permitted; and the existing electrical feeder, breaker, disconnect, and steel foundation are to be reused for the new Trane CGAM120 chiller. The chiller shutdown and cutover must occur during an approved weekend outage to minimize surgery disruption, with the entire operation potentially completed in one weekend; the contractor must coordinate crane access and staging limited to Building 7's loading dock; Siemens is the controls contractor responsible for BAS integration; authorized Trane Service startup and commissioning is sufficient; the contractor must remove and legally dispose of the existing chiller including proper refrigerant recovery; 30% glycol concentration is required; and the facility requires a minimum two-week advance outage request with scheduling to be finalized at award based on equipment lead times.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25627Q0087 EXHIBIT C.docx | DOCX document | |
| LA20260051.pdf | ||
| OR CHILLER REPLACEMENT SITE VISIT SIGN IN SHEET.pdf | ||
| 36C25627Q0087 0002.docx | DOCX document | |
| 36C25627Q0087 0001.docx | DOCX document | |
| 36C25627Q0087 EXHIBIT D.docx | DOCX document | |
| 36C25627Q0087 EXHIBIT B.docx | DOCX document | |
| LA20260031.pdf | ||
| 36C25627Q0087 EXHIBIT C.docx | DOCX document | |
| Final OR CHILLER REPLACEMENT SOW.docx | DOCX document | |
| 36C25627Q0087.docx | DOCX document | |
| 36C25627Q0087 EXHIBIT E.docx | DOCX document | |
| JA- BRAND NAME s.pdf | ||
| 36C25627Q0087 EXHIBIT A.docx | DOCX document |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C25627Q0087
1. Does the Superintendent need to be directly employed by the Prime Contractor?
The superintendent must be provided by the prime contractor’s staff during contract performance. A proposed superintendent who is not currently employed by the prime contractor may be proposed if the offeror submits the commitment letter required by Factor 2 and the individual becomes an employee of the prime contractor upon award.
2. Must the Superintendent be on site at all times while work is commencing?
Yes, the superintendent shall be 100% full-time dedicated and assigned to the project whenever work is being performed on site.
3. Does the VA require an SSHO (Site Safety Health Officer), and does this person need to be directly employed by the Prime Contractor?
The solicitation does not specify or mandate a separate SSHO position. It is the responsibility of each offeror to review the project scope, applicable safety requirements, and their own internal safety programs to determine whether an SSHO is required to successfully and safely perform the work.
4. Must the SSHO be on site at all times while work is commencing?
The solicitation does not specify or mandate a separate SSHO position. It is the responsibility of each offeror to review the project scope, applicable safety requirements, and their own internal safety programs to determine whether an SSHO is required to successfully and safely perform the work.
5. If both required, Can the Superintendent & SSHO be a dual-hatted individual assuming that individual is qualified for both roles?
The solicitation does not establish a separate SSHO position. If an SSHO is otherwise required by an applicable safety requirement or the contractor’s accepted safety plan, the contractor must provide qualified personnel and comply with all applicable requirements. Nothing in the solicitation expressly prohibits one qualified individual from performing both functions, provided all duties can be fully performed without conflict and the superintendent remains continuously present whenever onsite work is being performed.
6. Are there any concerns for Asbestos Containing Material or Lead in the areas being worked in?
The Government is not aware of asbestos-containing material or lead-based paint within the identified work area. No hazardous-material survey is included with the solicitation. The contractor remains responsible for complying with the contract requirements and immediately notifying the Contracting Officer if suspected hazardous material is encountered.
7. Are there any ICRA requirements for this project?
No project-specific ICRA requirement has been identified in the solicitation. The contractor must comply with any facility infection-control and interim life-safety requirements applicable to its means, methods, access route, dust generation, and shutdown activities.
8. Is this contract Tax Exempt?
No, offerors are hereby notified that all state and local sales or use taxes for construction materials must be included in their bid or proposal price. It is solely the responsibility of the offeror to include all other applicable taxes in their bid proposal as well. The Government has determined that this acquisition cannot take advantage of any sales or use tax exemptions that may be available to it under the applicable state law. Under no circumstances will any Contractor be designated as an agent of the Government for purposes of any tax exemption, nor will the Government Authorize any Contractor's use of any tax exemption directly applicable to the Government under this procurement
9. In Lieu of a PPQ for our Past Performance references, would a CPARS be sufficient?
Exhibit B (PPQ) is not mandatory; offerors will not be penalized if PPQs are not returned by respondents. The Department of Veterans Affairs will use all methods available to evaluate past performance.
10. Wage determination LA20260031 lists Louisiana Counties of Caddo, and Amendment 0001 corrects the place of work to Pineville, LA. Please confirm which wage determination applies to the Pineville site.
Wage Determination LA20260051 for Rapides Parish applies to the Pineville, Louisiana project location and is incorporated through this amendment. LA20260031 does not apply to this project.
11. The SF 1442, including Block 13a, and the divisional price distribution sheet required in A.4 are not in the posted files; please post both. Please also confirm whether CLIN 0001, 1.00 JB, is paid as one lump sum with progress payments
File name is 36C25627Q0087 Block 13A is on page 1 A.4 is on page 6. CLIN 0001 is a firm-fixed-price lump-sum item. Progress payments may be made for work accomplished in accordance with FAR 52.232-5 and VAAR 852.232-70, subject to the approved payment breakdown, satisfactory progress, and Government acceptance of the work included in each payment request.
12. Please provide the existing chiller manufacturer, model, operating weight, refrigerant type and charge, and available equipment drawings.
Additionally, please confirm the chilled-water piping sizes, material specifications, required modification lengths, existing system volume, and specified glycol type and concentration.
Not available.
13. LA20260031 lists Caddo Parish. Please confirm whether it applies to the work in Pineville, which we understand to be in Rapides Parish, or whether a different wage determination applies.
See #10.
14. SOW Section 6 describes an administrative NTP for submittals and ordering, then a formal NTP set by equipment lead times. Please confirm the formal NTP will accommodate long-lead equipment if the lead time exceeds the 30 calendar days.
Please also confirm that the 30 calendar days to complete the work (SOW Section
6) and the 10 calendar days to begin performance (SF 1442 continuation, item 9) both run from the formal NTP, and whether 06/01/2027 is the expected formal NTP.
The administrative NTP authorizes only the identified submittal and equipment-ordering activities. It does not begin the 30-calendar-day onsite construction period. Those periods begin upon issuance of the written formal NTP. June 1, 2027 is a fictitious date used solely for proposal scheduling and is not the anticipated formal NTP date. The final contractual period of performance will be established in the award based on the accepted equipment lead time and project schedule.
15. SOW Section 3 sets work hours of 8:00 a.m. to 4:30 p.m., Monday through Friday.
Is weekend or off-hours work required and/or permitted, and under what conditions?
Normal work hours remain Monday through Friday, 8:00 a.m. to 4:30 p.m. The chiller shutdown and cutover must be scheduled during an approved weekend outage to minimize disruption to surgery. Continuous or extended-hour work may be required during the approved cutover window to restore service within that window. All after-hours and weekend work must be coordinated with and approved by the facility in advance.
16. What areas does the chiller serve? Surgery
17. Can the chilled-water loop be shut down during weekday hours, and for how long? If not, what shutdown windows (nights, weekends) should the contractor plan for?
The shutdown timeframe depends on the contractor’s assessment of demo and install of new chiller system. (1) weekend should suffice the entire operation.
18.Removal and replacement requires a crane. Please identify the crane access and staging location, including any use of the Building 7 loading dock, the days and hours it is available, and any restrictions on traffic, deliveries or patient access.
Exact positioning, access times, traffic control, delivery coordination, and patient-access restrictions will be finalized through an approved lift and logistics plan after the equipment-delivery date is established. Crane setup and staging will be limited to the Building 7 loading dock zone.
18. Are existing drawings or as-builts for the chiller installation (piping, electrical, controls) available?
No
19. Is the intent for the existing chiller support frame, and the existing electrical feeder, conductors and overcurrent protection, to be reused as is?
Yes, The contractor must field-verify dimensions, condition, ratings, available fault current, conductor sizing, and compatibility with the proposed chiller before installation and promptly report any discrepancy to the VA.
20. Please provide the chilled-water loop volume and the current glycol concentration so the quantity needed after installation can be priced. Glycol in the system will be locked into place.
The chiller system will require filling and top off at install. The contractor shall include the glycol required to fill the replacement chiller and top off losses associated with the work. Offerors shall verify required quantities based on the proposed equipment and field conditions.
21. Is there a required or preferred VA controls vendor for the BAS tie-in? How is the scope split between the contractor (SOW 4.1 disconnect and reconnect) and the VA's controls vendor, including programming and points mapping? Are points lists available?
Siemens is our controls contractor. The prime contractor is responsible for coordinating and including all costs necessary for the BAS disconnect, reconnection, programming, points mapping, graphics, testing, and final integration required by the SOW.
22. SOW Section 4.3 has startup and commissioning performed by authorized Trane Service. Will the VA perform or require any third-party commissioning, or is startup and commissioning by authorized Trane Service, performed by the contractor, sufficient?
Startup and commissioning by authorized Trane Service, performed by the contractor in accordance with the SOW, is sufficient.
23. The package does not mention lightning protection. Does the existing chiller have lightning protection or grounding that must be disconnected, relocated or reconnected, and is that in this scope?
Existing grounding associated with the chiller shall be disconnected and reconnected as required for the replacement equipment and is included within the scope of work. Contractors shall field verify existing conditions.
24. Exhbit C The form text refers to a different solicitation and project (36C25626R0023, Project #598-19-
See corrected attachment.
25. Since this is a mission-critical facility, we need to know the timeline for the swap-out and cut-over. Is there a certain window of time to get the new unit up and running?
Preferably over a weekend period for demo and install of new chiller, TBD upon equipment ship date.
26. Will the work need to be done around the clock to reduce the downtime of the system?
Yes
27. Will temp cooling be required during the swap? If so, for what portions of the hospital?
No
28. Once the old chiller is removed, who disposes of it or recycles it? Is that part of the Scope of Work?
The contractor is responsible for removing the existing chiller from the site and legally disposing of or recycling it in accordance with the SOW and all applicable requirements, including proper recovery and documentation of refrigerant.
29. Is a rental chiller required to be provided during the duration of the project?
No
30. What percentage of glycol is required to be included in the system?
30%
31. Please say whether a pre-proposal site visit will be held, or provide photos and nameplate data for the existing chiller?
Site visit occurred on 11/04/26 as stated in the solicitation. No additional as-built drawings are available.
32. The SOW limits work to Monday through Friday, 8:00 AM to 4:30 PM CST (inferred), and the chiller serves critical HVAC and process cooling for the operating room. Please state the allowed chilled water outage window, and whether the contractor must provide temporary cooling or after-hours cutover.
Installation can be scheduled over weekends. The facility requires at minimum (2) week approved outage request prior to outage. Scheduling and phasing will be developed at award date.
33. The SOW requires completion within 30 calendar days from NTP and describes an administrative NTP for submittals and ordering, followed by a formal NTP based on lead times. Please confirm that the 30 calendar days and the 10-day start run from the formal NTP.
The awardee is required to express lead times of replacement chiller at the time of award to allow the POP to be extended for delivery, install and startup.
34. Can the existing electrical feeder, breaker, disconnect, and associated infrastructure be reused for the new Trane CGAM120 chiller?
Please provide the existing electrical single-line diagram, available electrical equipment data, BAS points list, and applicable controls integration requirements.
The existing electrical feeder, breaker, disconnect, and associated infrastructure is to be reused for the new Trane CGAM120 chiller.
35. Please confirm whether the existing chiller foundation is suitable for the proposed replacement equipment without structural modifications.
Are there any restrictions on crane positioning, lifting operations, access routes, or staging areas that bidders should incorporate into their estimates?
Steel foundation is capable for the new load. Crane location will be limited to the loading dock zone of BLDG 7.