This document is an Amendment of Solicitation/Modification of Contract (Standard Form 30) issued by the Department of Veterans Affairs, Overton Brooks VA Medical Center in Shreveport, Louisiana. The amendment modifies RFQ 36C25626Q0473, extending the closing date and time to March 20, 2026 at 4:00 PM Central Daylight Time. The amendment incorporates questions and answers submitted by interested parties regarding chiller compressor replacement work. Offerors must acknowledge receipt of this amendment by completing the form and returning it with their offer, acknowledging receipt on each copy of their offer, or submitting a separate letter or electronic communication referencing the solicitation and amendment numbers prior to the extended deadline.
The questions and answers address technical specifications and execution methods for the compressor replacement project. Key clarifications include: the suction and discharge isolation valves function properly with no need for replacement; the replacement compressors require computer programming to integrate with the existing BAC chiller system; the two existing 500 series compressors have no mechanical failures but cannot communicate with the BAC unit; refrigerant loss during construction will be 5 pounds or less of freon; and compressor removal may be accomplished using either a ramp over the blue hoses that must remain connected or an extended boom forklift. The contracting officer is Bennett W Smith (bennett.smith2@va.gov).
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25626Q0473 0001.pdf | ||
| 36C25626Q0473.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE 7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO. 1. CONTRACT ID CODE
FACILITY CODE CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30 PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243
(Type or print) (Type or print)
(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code)
(If other than Item 6)
(Specify type of modification and authority)
(such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
1 2
0002 03-18-2026
Department of Veterans Affairs Overton Brooks VA Medical Center (90C) 510 East Stoner Avenue Shreveport LA 71101
Department of Veterans Affairs Overton Brooks VA Medical Center (90C) 510 East Stoner Avenue Shreveport LA 71101
To all Offerors/Bidders
36C25626Q0473
X
X X
** HOUR & DATE for Receipt of Offers is EXTENDED to: 03-20-2026 4:00 PM CDT
The purpose of this RFQ amendment is to post questions submitted by interested parties along with the answers. See page 2 for the questions and answers.
The RFQ closing day and time are changed to 3/20/2026 at 4:00 PM Central.
Ensure you sign and include a copy of this amendment with any offer you submit.
Bennett W Smith bennett.smith2@va.gov
Question: Do the suction and discharge isolation valves function properly? (Do they “hold”). If not, should we provide alternate pricing to drain the lines? Should we also include pricing to replace the valves that have failed?
Answer: Yes, the suction and discharge valves function properly.
Question: Are there any controller or communication issues we should be made aware of?
Answer: Yes, the compressors after installation need to be computer programmed to the existing chiller system.
Question: Compressor Failure: Is there any available information regarding the cause of failure of the existing compressors (e.g., mechanical failure, electrical fault, bearing failure, etc.)?
Answer: There is nothing wrong with the 2 existing 500 series compressors. They just do not communicate with the BAC unit.
Question: Refrigerant Handling: After recovery of the refrigerant per EPA requirements, should the contractor plan to reuse the recovered refrigerant, or should the system be recharged with new refrigerant after installation of the replacement compressors?
Answer: The refrigerant loss would be 5# or less of freon during construction.
Question: Is there a specific route to take when removing the compressor, due to the 2 blue hoses that must stay connected? Can we use a ramp over the hoses?
Answer: Yes, a ramp could be used but also a extended boom forklift to reach in and remove the chiller compressors.