36C25625R0067 - SOW - Replace Roof and Windows of Bldg 4.docx
DOCX document 38 KB Posted
- Solicitation number
- 36C25625R0067
About this file
This document is a Statement of Work (SOW) for a roof and window replacement project at Building 4 of the Alexandria VA Health Care System in Pineville, Louisiana. The project involves comprehensive renovation of a 22,000 square foot, 2-story historic building constructed in 1929, including demolition and replacement of the existing clay tile and flat roofs, installation of a new TPO roofing system, replacement of exterior windows, repairs to the stucco facade, repainting, and installation of new copper gutters and downspouts.
The project is a pre-solicitation opportunity specifically targeted at Service-Disabled Veteran-Owned Small Businesses (SVOSBs), with a construction cost range between $2,000,000 and $5,000,000. The contract will be awarded using the FAR 15.101-1 Tradeoff Process, with a total performance period of 455 calendar days from the Notice to Proceed. Key requirements include maintaining food service operations during construction, preserving the building's historic register status, implementing energy-efficient windows with low-E coating, and ensuring minimal disruption to the operational VA hospital campus. The official solicitation will be issued on SAM.gov on or around 04/01/2025, with the Contracting Officer being Jennings.herbst@va.gov.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25625R0067 Pre Sol.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Rev_02 Statement of Work
Project No. 502-21-118 Replace Roof and windows of Bldg. 4 Alexandria VA Health Care System, Pineville, LA
Scope:
This project includes the demolition of the existing roof and windows for Building 4, and the installation of a new clay tile roof, TPO roofing, and two metal canopies at the loading docs.
New windows are also to be installed in the same location as the existing windows. The existing building was originally constructed in 1929 and is listed on the National Historic Register as the dining and kitchen facility for the Alexandria VA Medical Facility. The building is a 2-story building totaling approximately 22,000 SF with covered connecting corridors to adjacent buildings. The project will also include repairs to the existing stucco façade and repainting the entire exterior of the building. New copper gutters, downspouts and flashing are included in the project scope. The project scope will require phasing of the work to not impact meal preparation operations for the hospital patients. The goal of the project is to successfully replace the roof and windows without interruptions of the food service operations and ensure roof and windows that no longer allow water infiltration into the building. The facility is 95 years old, originally constructed in 1929 and listed as a significant contributing building on the historic register for the Alexandria VAMC. The scope of this project includes replacing the existing clay tile roof and existing flat roof areas on a 2-story 22,000 SF building with limited storm drainage site work as required for connection of gutters. The scope also includes replacing all the exterior windows on the building and repairs to several areas of the building exterior for stucco repairs and painting. Lastly, the loading dock area metal canopy roofs and covered walkway roof flat roofs will be replaced. The building is an existing 2-story slab-on-grade structure. The existing building is constructed with a structural steel frame on concrete foundations.
The building exterior is stucco on metal lathe. The exterior windows are aluminum storefront with operable glazing units. A covered canopy at the rear of the building provides wet weather protection for food deliveries. There are two areas on the east and west wall in which the stucco is failing and separation from the wall is occurring. These locations are above two banks of windows from the existing CMU wall backing. Above both areas are undersized and leaking roof scuppers which has caused water damage to the wall systems resulting in the stucco wall failure. The walls will be repaired and the building repainted. The original building windows were casement style single pain windows. Most of the windows have been replaced with single hung windows over time. Due to the facility listed on the historic register, it will be necessary to replace the windows with a window that has the look of a casement window. This look can be accomplished using a fixed double pain insulated glazing units with low “E” coating to meet energy efficiency requirements of the ASHRAE 90.1 guide.
All roof insulation will be located above the structural concrete deck. The roofing system will be a white color 80 mil TPO adhered system over a tapered polyisocyanurate insulation and cover board. All roof drainage will be directed to the site storm water drainage system via underground piping. All of the gutters and downspouts will be copper to match existing.
Roof drains and overflow roof drains are on the exterior wall via scupper head and downspouts to drain into stormwater management on the site. Several of the openings in the parapet walls have been identified to be enlarged to allow for properly sized systems for the roof areas they serve. The roof assembly insulation will have a minimum value of R-25 in the TPO flat roof areas. The roofing system shall have a minimum slope of 1/4” per foot to primary roof drains.
The clay tile roof will have poly-ISO insulation with a cover board installed on the concrete deck within the attic space of a minimum value of R-38.
The clay tile will be a 14-inch tile to match the clay tile by Ludowici on the adjacent building 3 roof currently being replaced. Additional support collar bracing may be necessary to provide for unsupported length greater than 12 feet in the attic roof framing. Lastly, new eave vents will be installed with roof power vents for free air circulation.
A new dormer to match the existing three dormers is planned on the rear of the building to provide access to the attic for maintenance purposes. The new dormer exterior will be finished in clay tile on the vertical walls and covered with a copper roof for historical purposes.
No interior construction is planned. If necessary for window replacement, the wall finished will be repaired to match existing. Existing finishes have been identified as paint wall gypsum board and ceramic tile wainscot. Temporary partitions to accommodate construction phasing will be provided as necessary to allow for the removal of existing windows and installation of new windows to allow food preparation, cooking, and serving of meals. These partitions will be wood or light gauge metal framing with poly film and gypsum board to prevent the spread of construction debris. Similar measures will also be instituted in the attic and ceiling plenum as the existing roof is removed and a new roof is installed to prevent any construction dust from falling into occupied spaces below.
The roof curbs of the active equipment were tall enough that the units would not need to be removed for re-roofing. Another aspect of this project is removing existing window air-conditioning units. To provide the cooling that was previously provided by these units, wall-mounted ductless mini-split airconditioning units will be installed in their place. They are all on the second floor or the elevator machine room at the roof level, therefore the condensing units are proposed to be on the roof. Also, there are two exhaust fans in the attic that are no longer in use and will be demolished. Only one of those fans still had an electrical connection to it. Attic ventilation will be added at a rate of 1 CFM/sqft with intake using the dormer louver and vents in the eaves then exhausted through an in-line fan mounted in the attic and discharging through a roof vent. This fan will be controlled by a thermostat to come on when the temperature reaches a selected temperature. The existing window units will be replaced with like kind and sized window units connected to the same electrical source as existing rather than providing new mini-split air conditioning units except for the elevator machine room.
Electrical work will consist of removing existing circuits from the mechanical equipment that is no longer in use, disconnect / reconnect equipment that needs to be temporarily removed for the re-roofing process and installing lights in the attic space. The window AC units will be replace with new window units with the exception of the elevator equipment room, which will get a new split unit. Power for the new AC units will utilize existing circuits..
Contract objective:
1. To ensure all requirements of contract drawings and specifications are met and completed by the completion date provided in contract documents.
2. To ensure that all construction activities are performed in such a manner as to ensure safe and correct operation and in compliance with applicable local, state and federal regulations and contract drawings and specifications.
Tasks:
Furnish all labor, tools, materials, equipment and supervision necessary for the work to replace the existing Alexandria VAHCS Roof and windows of Building 4 as detailed in the Drawings and Specifications for this project.
The work for this project includes, but is not limited to the following improvements:
Contractor shall completely prepare site for operations, including demolition and removal of existing roof and windows, and furnish labor and materials and perform work to provide new roof and windows along with other items detailed above and in the drawings and specifications.
Phasing:
Refer to sepcifications for phasing breakdown.
Special Condition:
Prior to mobilization and commencement of any construction, the contractor shall conduct a mandatory thorough survey and investigation of all the work sites for the Replace Roof and windows of Bldg. 4 Project. This information will be documented to include pictures.
Delivery:
All personnel in the contractor’s services shall have certified or proper training on the tasks they perform.
The Project Engineer or COR shall be informed by the contractor of the following situations/events in writing:
· The anticipated start date of any contract work.
· As soon as it is known that the work will take longer than expected.
· As soon as it is known that a possible change order will have to happen.
· To provide a written plan for corrective action for any work that cannot be completely within contract specified time.
· Inform COR if contractor needs to stay outside of normal operating hours. Estimated 5% of work to be completed after hours.
· Contractor Payment Application shall be provided at the beginning of each month for the previous month work that has been completed.
All work shall be completed in accordance with contract drawings and specifications.
All required contract works completed shall be approved and accepted by Project Engineer or COR prior to accepting and approving contractor application for payment.
Security and General Requirements:
All on-site work should be completed between the hours of 8am and 4:30pm CST, Monday through Friday excluding holidays unless otherwise listed in the tasks section or other working hours are approved by the COR.
Contractor shall obtain an access badge from the VA Police Departmentwhile performing work on-site for their self, their employees and all subcontractors under their authority.
Security and privacy requirements vary depending on the equipment to be serviced and the service being performed. Contractor personnel may be required to complete any or all of the following but not limited to:
· Online training.
· Read, sign, and comply with ‘Contractor Rules of Behavior’.
· Submit to finger printing and background investigation.
· Provide network security information as requested for any equipment used in the VA facilities.
· The extent of these requirements shall be determined by Project Engineer or COR using current facility Information Technology and Privacy rules in cooperation with experts in those departments.
Parking shall be limited to established concrete or improved rock parking lots, Project Engineer or COR will advise which parking lots to use. Contractors and personnel are not allowed on the grass area unless specifically authorized by the Project Engineer. U.S. District Court Violation Notices shall be issued for parking violations.
The contractor and all employees shall comply with all applicable Alexandria VA Health Care System fire, safety, and traffic regulations.
The contractor is to field verify existing conditions.
All work is to be performed within all ASME, OSHA, EPA, VA, and Federal, State and local codes and regulations.
Proper Lock-out/Tag-out procedures shall be used when appropriate.
No roadway, drainage ditch, pedestrian walkway, or any other service, utility, or access to any of the above is to be blocked or rendered unusable for any length of time during this project unless previously approved by the Project Engineer.
All work, materials, storage of materials and equipment, repair procedures and unforeseen problems or circumstances are to be coordinated with the Project Engineer.
Work on this project shall not begin until authorized by the Contracting Officer.
The title Project Engineer or COR shall refer to the Contracting Officer’s Representative.
Work to be conducted on a Fully Operational VA Hospital Campus, in and around Mental Health and Long Term Care facilities. Tools and equipment shall be kept under close watch to prevent patient injury.
Place of Performance:
· Work shall be performed, with issuance of Notice to Proceed, at the Alexandria VA Health Care System, Pineville, LA, or in the immediate vicinity as required by this Scope of Work.
· Equipment or Government property may be removed from the facilities with prior permission from Project Engineer or COR and the Department Director.
Period of Performance:
All contractually required work and tests must be successfully completed within 455 calendar days of issuance of Notice to Proceed. This includes the 3 month submittal phase.
ISO Requirements:
· The C&A requirements do not apply, therefore a Security Accreditation Package is not required.