This document contains a bidding request for information (RFI) related to federal contract opportunity number 36C25622R0079 for the refurbishment of the oval of circle drive at the Veterans Healthcare System of the Ozarks in Fayetteville, Arkansas. The project involves full depth replacement of roadways and parking areas, curbs and gutters, traffic control devices, pavement markings, pedestrian amenities, site and pedestrian lighting, emergency call boxes, earthwork, landscaping, site utilities, and storm water management. The contract will be awarded as a 100% service-disabled veteran-owned small business set-aside with a value between $2-5 million. The solicitation will be issued on July 6th with a 120-day proposal acceptance period and will require bid, performance, and payment bonds. Offerors must be registered in SAM, ORCA, and with the assigned NAICS code 237310 prior to the solicitation due date. The RFI document addresses various technical questions about drawings, specifications, and requirements for the project.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT # 564-17-117
Refurbish Oval of Circle Drive
Department of Veterans Affairs
Veterans Healthcare System of the Ozarks
Fayetteville, AR
DATE: August 18, 2022
ITEM 1– Bidding Requests for Information
# Reference Question Answer
1 Sheet
CD101/
Spec 024100
Are we replacing the 49 trees that are to be removed? If we are replanting, what kind/size of trees are going back in?
1. Demolition plan CD101 states “Remove tree including stump (49) in accordance w/the specifications.”
2. Spec section 024100 part 3.1.B states, “…trees that were removed including stumps and roots, grass that has been removed or damaged during construction and similar materials shall become property of the Contractor and shall be disposed of by him daily….”
3. Planting plan CS103 shows new trees to be planted and notes the species of each tree.
4. The contract requires removed trees are not to be replanted; but rather, new trees are to be planted as indicated on CS103.
5. Tree sizes shall be 6-inch diameter.
Also note that the contractor is to preserve the existing block tree rings and reuse them for the newly installed trees. Return any excess block tree rings in reusable condition to the VA. If additional block tree rings are needed to complete the project, then match the existing tree rings.
2 Sheet
CSD101
Are the Handicap sign posts Square Tube posts as the traffic sign are?
Handicap signposts shall be installed per details 4 and 6 on sheet CSD101.
3 Temporary Striping Paint shows to be painted, then removed. Why not use Foil back tape, that way there will be no scaring from the removal on the new asphalt?
AE takes no exception to installing temporary striping as suggested.
However, to uphold safety requirements, the temporary striping must be maintained and/or replaced by the Contractor as directed by VA-COR throughout the construction period.
4 I Didn't see wheel stops at the Handicap spaces.
Is this correct?
Yes.
5 During the 4 phases of traffic control, will the signs need to be on post or stands? There are a lot of utilities to think about when driving post.
Any of the temporary signage installation details from MUTCD Chapter 6 are acceptable.
However, the temporary signage must be maintained and/or replaced by the Contractor as directed by VA-COR throughout the construction period.
6 Sheets
ES102,
EE501
There are 2 drawings referenced but missing from the file. The drawing schedule shows drawings ES102 and EE501 which do not exist in the file.
Can we please get those posted?
Uploaded to sam.gov.
7 Reviewing the drawings and specs, all work appears to be outside.
Please explain the following requirements in the Statement of Work
pg. 6/15: a) ZipWall, 2) Negative air pressure
No, please review drawings carefully. Some work occurs within existing buildings. Where this interior work occurs, ICRA requirements must be followed.
with ICRA barrier, 3) Ball- In-The-Wall-Dome-On- The-Wall Room Pressure Monitor.
8 Spec 014500
Specs pg. 105/305 paragraph D. Is Construction Quality Management for Construction course required for CQC System Manager and Alternate CQC System Manager?
9 Sheet
TS101
Drawing TS101 is a Topographic drawing.
However, page 148/305 of the specs calls out Topographic survey. Is the SDVOSB GC required to perform another Topographic survey?
10 Spec 022113
Pages 147/148 of 305 in the specs calls out Site Surveys. Is the SDVOSB GC required to perform the listed surveys to include land and boundary surveys?
No Boundary Survey is required.