564-17-117 Pre-Bid RFIs Responses.pdf
PDF 68 KB Posted
- Solicitation number
- 36C25622R0079
About this file
This document contains responses to pre-bid requests for information (RFIs) for a federal contract opportunity to refurbish an oval drive at a Veterans Affairs medical center. The opportunity is set aside for service-disabled veteran-owned small businesses and involves replacing roadways, parking areas, curbs, gutters, signage, lighting, utilities, and landscaping. The contractor must remove 40 remaining trees as indicated on the drawings, plant new trees of 4-inch diameter, and reuse or match existing tree rings. Temporary striping must be maintained throughout construction. Some interior work will require infection control barriers. The contractor must perform a land survey and relocate the construction entrance as specified. The solicitation will be issued on July 6th with a 120-day acceptance period and bonds required. The project value is between $2-5 million under NAICS code 237310.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
564-17-117 Pre-Bid RFIs Responses Page 1 of 3
Project Title: Refurbish Oval of Circle Drive
Project Number: 564-17-117
Pre-Bid RFI Responses
RFI 1. Re: Sheet CD101/Spec 024100, Are we replacing the 49 trees that are to be removed? If we are replanting, what kind/size of trees are going back in?
RFI 1. Response:
a) Drawing Title: “CIVIL SITE PLAN – DEMOLITION” Drawing Number:
CD101 in SYMBOL & WORK legend states “REMOVE TREE INCLUDING STUMP (49) IN ACCORDANCE W/THE SPECIFICATIONS.” Drawing Number CD101 depicts remove tree including stump 50 in lieu of 49. Ten of the 50 trees have been removed including stump by others. Contractor must remove the remaining 40 trees including stump in accordance with specifications.
b) Spec section 024100 part 3.1.B states, “…trees that were removed including stumps and roots, grass that has been removed or damaged during construction and similar materials shall become property of the Contractor and shall be disposed of by him daily….”
c) Planting plan CS103 shows new trees to be planted and notes the species of each tree.
d) The contract requires removed trees are not to be replanted; but rather, new trees are to be planted as indicated on CS103.
e) Tree sizes must be 4-inch diameter. Also note that the contractor is to preserve the existing block tree rings and reuse them for the newly installed trees. Return any excess block tree rings in reusable condition to the VA. If additional block tree rings are needed to complete the project, then match the existing tree rings.
RFI 2. Re: Sheet CSD 101, Are the Handicap sign posts Square Tube posts as the traffic sign are?
RFI 2. Response:
a) REGULAR SPACES and ACCESSIBLE SPACES signposts must be installed per detail 4 on Drawing Number CSD101.
b) Location of all REGULAR SPACES and ACCESSIBLE SPACES signpost must be relocated from position as shown on Drawing Number: CSD101 detail 6 to the opposite side of sidewalk, centered on parking spaces, and 6 inches from interior edge of sidewalk.
RFI 3. Temporary Striping Paint shows to be painted, then removed. Why not use Foil back tape, that way there will be no scaring from the removal on the new asphalt?
RFI 3. Response: The Government takes no exception to installing temporary striping as suggested. However, to uphold safety requirements, the temporary striping must be
564-17-117 Pre-Bid RFIs Responses Page 2 of 3 maintained and/or replaced by the Contractor as directed by VA-COR throughout the construction period at no additional cost to the Government. Any temporary striping used must be non-scaring type.
RFI 4. I Didn't see wheel stops at the Handicap spaces. Is this correct?
RFI 4. Response: Yes.
RFI 5. During the 4 phases of traffic control, will the signs need to be on post or stands? There are a lot of utilities to think about when driving post.
RFI 5. Response: Any of the temporary signage installation details from MUTCD
Chapter 6 are acceptable. However, the temporary signage must be maintained and/or replaced by the Contractor as directed by VA-COR throughout the construction period at no additional cost to the Government.
RFI 6. Re: Sheets ES102, EE501: There are 2 drawings referenced but missing from the file. The drawing schedule shows drawings ES102 and EE501 which do not exist in the file. Can we please get those posted?
RFI 6. Response: The attached Oval Circle Drive Submission drawings and specifications sent on 3/31/2021 supersede previous drawings and specifications. See attachment “Oval Circle Drive Submission drawings 20210331” and “Oval Circle Drive
Submission specifications 20210331”.
RFI 7. Reviewing the drawings and specs, all work appears to be outside. Please explain the following requirements in the Statement of Work pg. 6/15: a) ZipWall, 2)
Negative air pressure with ICRA barrier, 3) Ball-In-The-Wall-Dome-On-The-Wall Room
Pressure Monitor.
RFI 7. Response: No, please review drawings carefully. Some work occurs within existing buildings. Where this interior work occurs, ICRA requirements must be followed.
RFI 8. Re: Spec 014500: Specs pg. 105/305 paragraph D. Is Construction Quality
Management for Construction course required for CQC System Manager and Alternate
CQC System Manager?
RFI 8. Response: Yes
RFI 9. Re: Sheet TS101: Drawing TS101 is a Topographic drawing. However, page
148/305 of the specs calls out Topographic survey. Is the SDVOSB GC required to perform another Topographic survey?
RFI 9. Response: Yes.
RFI 10. Re: Spec 022113: Pages 147/148 of 305 in the specs calls out Site Surveys.
Is the SDVOSB GC required to perform the listed surveys to include land and boundary surveys?
564-17-117 Pre-Bid RFIs Responses Page 3 of 3
RFI 10. Response: Contractor must perform land survey. No boundary survey is required.
RFI 11. Re: Drawing Number: CE101 and CTC101: Can Phase 1 construction entrance, gate, and concrete washout be relocated to Southeast end of Phase 1 fenced in construction area.
RFI 11. Response: Contractor must relocate construction entrance, gate, and concrete washout to Southeast end of Phase 1 fenced in construction area.