36C25618R0563-0001000.docx
DOCX document 29 KB Posted
- Attached to
- 564-18-3-691-0001 PROJECT 564-17-105 Replace and Monitor UPS in IT Closets (VA-18-00058605) VA256-18-AP-5580
- Solicitation number
- 36C25618R0563
About this file
36C25618R0563 0001 36C25618R0563 0001.docx
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25618C0153-000.docx | DOCX document | |
| 36C25618R0563-0002000.docx | DOCX document | |
| 36C25618R0563-001.docx | DOCX document | |
| 36C25618R0563-005.pdf | ||
| 36C25618R0563-006.docx | DOCX document | |
| 36C25618R0563-003.xlsx | XLSX spreadsheet | |
| 36C25618R0563-004.pdf | ||
| 36C25618R0563-002.pdf | ||
| 36C25618R0563-007.docx | DOCX document | |
| 36C25618R0563-000.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2.
AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE
OF PAGES
10A. MODIFICATION OF
CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV.
11/2016) is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO:
Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITE M 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR
43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes r eference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS
ENTERED INTO
PURSUANT TO AUTHORITY OF:
D. OTHER
BY
Contractor
16C. DATE SIGNED
14.
DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME
AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS
OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 07-30-2018 564-17-105 Department of Veterans Affairs Veterans Health Administration Network Contracting Office 16 2575 Keystone Crossing Fayetteville AR 72703 Department of Veterans Affairs Veterans Healthcare System of the Ozarks Network Contracting Office 16 Keystone Crossing Fayetteville AR 72703 To all Offerors/Bidders
36C25618R0563 07-13-2018
X X X
JULY 30, 2018 2:00PM (CST)
X
A. THE PROPOSAL DUE DATE HAS BEEN EXTENDED TO: JULY 30, 2018
B. SEE ATTACHED RFI QUESTIONS AND ANSWERS
SONYA D TRENTHAM
CONTRACTING OFFICER
564-17-105 Replace-Monitor UPS in IT Closets Pre-Bid Request for Information (RFI)
RFI 1. Do you need 107 x 1500VA and 13 x 3 kVA? Or 129 x 1500 VA and 16 x 3 kVA? Can you explain what you mean by “spare” at the bottom of the Excel sheet.
Response: The Contractor must furnish and install a total of 150 each 1500kva units including spare units and a total of 16 each 3kva units including spare units. Spare units (quantity determined by COR) must be furnished to the VA but not installed.
RFI 2. Is there a requested back-up time, or should we quote standard units with built-in batteries?
Response: There is no specific back-up time.
RFI 3. Point “k” page 7 says: UPS units will be capable of supporting the following communication protocols for remote monitoring, Modbus Serial, USB Power Summary, HTTP, SNMP, and Telnet. Clearly you’re asking a compatibility with SNMP protocol but do you need the SNMP card itself? Should we quote it separately?
Response: The Contractor must furnish and install UPS units in accordance with the SOW including, but not limited to options and accessories for remote monitoring, recording and reporting live environmental information.
RFI 4. Are 20 Amp power outlets available where you want to place the 1500 VA units, or only 15 Amp outlets? If 20 Amps are available, can we submit a proposal that includes a more capable 2000 VA unit?
Response: Contractor must furnish and install UPS units and plug into existing electrical outlets.
RFI 5. Will the VA provide receptacle for any location where 208V is needed?
Response: The VA will furnish receptacles for any location that requires 208V.
RFI 6. Is there any electrical work required (running new lines to data closets, changing outlet types, etc.)?
Response: No.
RFI 7. Are all locations ready electrically for the new units?
Response: Yes.
RFI 8. Is there any construction work required (installing 2 or 4 post racks, etc.)?
Response: No.
RFI 9. Is there room in the racks for the new units?
Response: Yes.
RFI 10. What is the quantity of 2 post racks?
Response: The Contractor must verify locations and quantities in accordance with the SOW.
RFI 11. What is the quantity of UPS’s going into 2 post racks?
Response: The Contractor must verify locations and quantities in accordance with the SOW.
RFI 12. Do you want center mount or flush mount for the in UPS’s in two post racks?
Response: Center mount for the in UPS’s in two post racks.
RFI 13. What is the quantity of 4 post racks?
Response: The Contractor must verify locations and quantities in accordance with the SOW.
RFI 14. What is the quantity of UPS’s going into 4 post racks?
Response: The Contractor must verify locations and quantities in accordance with the SOW.
RFI 15. What units are coming out? Are they like units to the ones going in?
Response: The units coming out are multiple makes/models/sizes. The new units may or may not be a direct replacement of like units.
RFI 16. What outputs are needed for the new units? (quantity and type). Or are these all connecting to PDU’s making the outputs irrelevant?
Response: Outputs must be in accordance with the UPS units specified in the SOW.
RFI 17. Are there any specific requirement for the UPS’s except those mentioned on page 7 of the solicitation?
Response: UPS Units must be in accordance with the SOW.
RFI 18. When can work be performed? During work hours? After hours?
Response: Work hours must be in accordance with the SOW.
RFI 19. Who will be responsible for downing the current network and bringing it back up again?
Response: The VA will be responsible for taking down and bringing back up the network.
RFI 20. Is there a minimum or maximum number of units to be swapped out per day/night?
Response: No.
RFI 21. Does the VA have any preferred brands or brands it will not consider?
Response: UPS Units must be in accordance with the SOW.
RFI 22. Can we ship the new units directly to the VA or do we need to deliver them as needed to the various sites?
Response: The Contractor must furnish UPS units as needed to various sites.
RFI 23. Do you have a loading dock available for use?
Response: There is a loading dock available at the VA main campus Building 2.
RFI 24. Are there facilities to dispose of the packing material for the new units?
Response: The Contractor’s disposal must be in accordance with the SOW.
RFI 25. As discussed at site visit, have all the switches been replaced in closets?
Response: Yes.
RFI 26. As discussed at site visit, are we to now provide and install equipment at Springfield and Joplin locations?
Response: The Contractor must furnish and install UPS units at Springfield and furnish UPS units to VA for Joplin.
RFI 27. We would like to request the CAD drawings in addition to the pdf drawings that were put on FBO, as the spec booklet mentions we need to provide as built drawings.
Response: If available, then the VA will furnish CAD drawings but not guarantee accuracy.
RFI 28. Just to verify, does the equipment need to comply with Buy American?
Response: The Contractor must furnish materials and equipment in accordance with the Buy American Act.
RFI 29. Are all UPSs to be 120V or are any 208V?
Response: The UPS Units must be in accordance with the SOW.
RFI 30. Will the person assisting with the software install be required to have any specific certifications i.e.( C++)?
Response: The software installation and setup must be in accordance with the SOW.
RFI 31. Is iUPSGuard by GE an approved software to be used on VA networks?
Response: The Contractor must furnish and install UPS monitoring and control software in accordance with the SOW.