About this file

This is a Pre-Solicitation Notice requesting Architectural and Engineering (A-E) SF 330 qualification submissions for the design of electrical infrastructure replacement at Marion VA Medical Center in Marion, Illinois. The project (657A5-24-108) involves replacing Medium Voltage Feeder 3 entirely and replacing transformers serving buildings 13, 38, and 43. The procurement is restricted to Service-Disabled Veteran-Owned Small Business (SDVOSB) firms and is being conducted under the Brooks Act and FAR Subpart 36.102. Responses must be submitted by November 10, 2026, at 12:00 PM Central Time via email to the Contracting Officer. This is a non-competitive request for qualifications only; no award will be made with this announcement. The anticipated contract award date is no later than December 30, 2026, contingent on fund availability. The Product Service Code is C222 (Engineering Services), and the NAICS code is 541330 with a small business size standard of $25.5 Million.

The A-E firm must provide comprehensive professional services including design development, construction documents, and construction period services within a 180-calendar-day timeline. The estimated construction budget is $2,484,000, and the design must incorporate a 20% budget reduction option through deductive alternates. Required disciplines include Project Manager, Electrical Engineer, Mechanical Engineer, Structural Engineer, Fire Protection Engineer, Certified Professional Industrial Hygienist, Plumbing Engineer, Life Safety Engineer, and Cost Estimator. The evaluation criteria assess professional qualifications, specialized experience and technical competence, capacity to accomplish the work, past performance on similar VA and government projects, reputation in the A-E community, and claims/termination history. Per VAAR 852.219-75, the prime contractor may not pay more than 50% of government-paid amounts to non-SDVOSB firms. The firm must register in SAM.GOV and comply with E-Verify requirements. SF 330 submissions must not exceed 10 MB in PDF format and 50 pages total, including all consultants and organizational charts.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUBJECT*

657A5-24-108, FCA Replace Medium Voltage Feeder 3 and Transformers l MC FY27 NRM VISN Base DE

GENERAL INFORMATION

CONTRACTING OFFICE’S ZIP CODE*
66048
SOLICITATION NUMBER*
36C25527R0013
RESPONSE DATE/TIME/ZONE
11-10-2026 12:00 PM CENTRAL TIME, CHICAGO, USA
ARCHIVE
90 DAYS AFTER THE RESPONSE DATE
SET-ASIDE
SDVOSBC
PRODUCT SERVICE CODE*
C222
NAICS CODE*
541330
PLACE OF PERFORMANCE
Marion VA Medical Center

2401 West Main Street

Marion Illinois

POSTAL CODE
62959
COUNTRY
USA

CONTACT INFORMATION

CONTRACTING OFFICE ADDRESS
Department of Veterans Affairs

Network Contracting Office (NCO) 15 3450 S 4th Street Trafficway

Leavenworth KS 66048

POINT OF CONTACT*

Contracting Officer Maria Hoover maria.hoover@va.gov 913-946-1130

ADDITIONAL INFORMATION

AGENCY’S URL

URL DESCRIPTION

AGENCY CONTACT’S EMAIL ADDRESS
maria.hoover@va.gov
EMAIL DESCRIPTION
office email

Presolicitation Notice Presolicitation Notice

DESCRIPTION

*=Required Field
Presolicitation Notice

Presolicitation Notice

Pre-Solicitation Notice: Request for Architectural and Engineer SF330 Submission for Solicitation: 36C25527R0013, Replace Medium Voltage Feeder 3 and Transformers, Project No. 657A5-24-108.

CONTRACT INFORMATION

This A-E Services requirement is being procured in accordance with the Brooks Act (Public Law (PL0582) and implemented in accordance with the Revolutionary Federal Acquisition Regulation (FAR) Overhaul (RFO) Subpart 36.102. Firms will be selected for negotiation based on demonstrated competence and qualifications for the required work.

This procurement is restricted to Service-Disabled Veteran Owned Small Business (SDVOSB) firms.

This is not a Request for Proposal, and an award will not be made with this announcement. This announcement is a request for SF 330’s from qualified Engineering contractors that meet the professional requirements.

The selection criteria for this acquisition will be in accordance with the evaluation factors listed below. The completed SF 330 will be evaluated by the Marion VA Medical Center Evaluation Board and the selection report shall serve as the final selection list, which will be provided directly to the Contracting Officer. Negotiations will be conducted beginning with the most highly qualified firm. The Government will not pay nor reimburse any costs associated with responding to this request. The Government is under no obligation to award a contract as a result of this announcement.

The most highly rated firm must physically come to the site and review the project before submitting a price proposal and letter of understanding at no cost to the government.

The contract is anticipated to be awarded no later than December 30, 2026.

Award of any resultant contract is contingent upon the availability of funds.

Personal visits to discuss this announcement will not be allowed.

The NAICS Code for this procurement is 541330, Engineering Services and the small business size standard of $25.5 Million. Award of a Firm Fixed Price contract is anticipated and award time for completion of design of this project is approximately 180 calendar days including time for VA reviews. The Engineering firm shall also be required to perform construction period services if award of a construction project contract is made.

DATABASE REGISTRATION INFORMATION:

Verification of the status of the apparently successful offeror: this acquisition is a 100% set-aside for a qualified Service-Disabled Veteran-Owned Small Business Architect/Engineer firm in compliance with VAAR 852.219-73. Only businesses listed as certified in the SBA certification database at https://veterans.certify.sba.gov/, shall be considered.

SYSTEM FOR AWARD MANAGEMENT (SAM.GOV):

Federal Acquisition Registrations require that federal contractors register in the System for Award Management (SAM.GOV) database at https://sam.gov/ and enter all mandatory information into the system. Award cannot be made until the contractor has registered. Offerors are encouraged to ensure that they are registered in SAM.GOV prior to submitting their qualifications package.

THE EXCLUDED PARTIES LIST SYSTEM (EPLS):

To ensure that the individuals providing services under the contract have not engaged in fraud or abuse regarding Sections 1128 and1128A of the Social Security Act regarding federal health care programs, the contractor is required to check the Excluded Parties List System (EPLS) located at https://sam.gov/content/ for each person providing services under this contract. Further the contractor is required to certify that all persons listed in the qualifications package have been compared against the EPLS list and are NOT listed. During the performance of this contract the Contractor is prohibited from using any individual or business listed on the List of Excluded Individuals/Entities.

E-VERIFY SYSTEM:

Companies awarded a contract with the federal government shall be required to enroll in E-Verify within 30 days of the contract award date. They shall also need to begin using the E-Verify system to confirm that all their new hires and their employees directly working on federal contracts are authorized to legally work in the United States. E-Verify is an Internet-based system that allows an employer, using information reported on an employee's Form I-9, to determine the eligibility of that employee to work in the United States. There is no charge to employers to use E-Verify. (RFO 52.222-54)

Qualified A-E firms are required to respond if interested by submitting one (1) original completed Standard Form 330 qualification package Parts I and II to include all consultants (form available on-line at: http://www.gsa.gov/portal/forms/download/116486). Must include in Part I Section H an organizational chart of the firm (excludes consultants) and a design quality management plan. Submission information incorporated by reference is not allowed. All submissions must be in pdf format and emailed. Email subject line shall clearly identify Solicitation number: 36C25527R0013 and project name, Replace Medium Voltage Feeder 3 and Transformers, Project No.657A5-24-108. Responses must be received by 12:00 PM Central on November 10, 2026 via e-mail to the Contracting Officer at maria.hoover@va.gov.

The 330 submissions must be a pdf document and must not exceed 10 MB.

The Engineering Firm must provide Basic Professional Services as delineated in the Scope of Work. As part of the Basic Professional Services, Marion VAMC Engineering Service expects the following primary A/E disciplines to be included: Project Manager, Supervisory, Architect, Electrical Engineer, Mechanical Engineer, Structural Engineer, Fire Protection Engineer, Certified Professional Industrial Hygienist, Plumbing Engineer, Life Safety Engineer, and Cost Estimator. Interested firms shall be required to respond to additional announcements separately from this announcement without further notice from the Government when posted to the Contract Opportunities website at https://sam.gov. The Contract Opportunities website is the only official site to obtain these documents. Additional information about this project will be issued on the System for Award Management website https://www.sam.gov once available.

PROJECT INFORMATION

This project will replace feeder 3 entirely and the transformers for building 13, 38 and 43 at the Marion VA Medical Center in Illinois. All work will be performed in accordance with the Statement of Work (SOW)/Supplement B, all local, state and federal codes, and all VA requirements. Feeder #3, one of the three primary electrical feeders, has exceeded its life expectancy. There are three feeders that run between a system of manholes on the VAMC campus. Most campus buildings have a dual electrical feed. Existing conduits run between manholes are in an unknow condition.

EVALUATION FACTORS:

Selection criteria are provided below. Prospective firms are required to address all selection criteria within submitted SF330 packages using additional pages as necessary. SF330 submissions including any additional pages are not to exceed fifty (50) pages. Each page cannot exceed 8 1/2 x 11 in size. Prospective firms are required to address all selection criteria within submitted SF330 packages using additional pages as required and SF330 submissions including any additional pages are not to exceed fifty (50) pages. SF330 must be submitted as a PDF and cannot exceed 10MB.

Qualifications (SF330) submitted by each firm for Project No. 657A5-24-108, “Replace Medium Voltage Feeder 3 and Transformers” will be reviewed and evaluated based on the following evaluation criteria listed below:

Evaluation Criteria:

1. Professional Qualifications: the qualifications of the individuals will be examined for experience and education and their record of working together as a team that are necessary for satisfactory performance of the services required. The architectural firm capable of preparing all design and construction documentation including, but not limited to advance planning, design, and construction oversite (including final as-built drawings) at the VA Medical Center in Marion, Illinois. The Engineering on staff representing the project or signing drawings in each discipline must be licensed to practice in one of the US States. Provide Professional License numbers and/or proof of licensure. The team shall have demonstrable expertise in their respective fields: Electrical Engineer, Mechanical Engineer, Structural Engineer, Fire Protection Engineer, Certified Professional Industrial Hygienist, Plumbing Engineer, Life Safety Engineer, and Cost Estimator with experience on projects of similar size and complexity.

2. Specialized Experience and Technical Competence: specific experience and technical skill in the type of work required for this project, including medical renovations to existing medical facilities, VA safety and physical security design, and experience in abatement of hazardous construction materials. Experience and qualification of personnel proposed for assignment and their record of working together as a team. The effectiveness of proposed project team (including management structure, coordination of disciplines, subcontractors, and prior working relationships) will be examined. The qualifications for Engineers shall include a summary of at least five similar projects that demonstrate technical capabilities and how well the proposal addresses technical capabilities in design quality management procedures, Computer-Aided Design and Drafting/Building Information Modeling, equipment resources, and laboratory requirements for the firm.

3. Capacity to Accomplish the Work: The prime contractor will be evaluated to determine if it has the general workload and staffing capacity within its design office which will be responsible for the design to accomplish the work in the required time. In accordance with VAAR 852.219-75 : In the case of a contract for services (except construction), the contractor will not pay more than 50% of the amount paid by the government to it to firms that are not certified SDVOSBs listed in the SBA certification database as set forth in 852.219-73 or certified VOSBs listed in the SBA certification database as set forth in 852.219-74. Any work that a similarly situated certified SDVOSB/VOSB subcontractor further subcontracts will count towards the 50% subcontract amount that cannot be exceeded. Other direct costs may be excluded to the extent they are not the principal purpose of the acquisition and small business concerns do not provide the service as set forth in 13 CFR 125.6. Prime contractor must include its certification of compliance with the limitations on subcontracting specified in 852.219-75 with its SF330 submissions.

4. Past Performance: The past performance of projects that are complete (design and construction) that the firm has designed relevant in scope to the advertised project that were accomplished with the Department of Veterans Affairs, other Government agencies, and private industry in terms of cost control, quality of work, and compliance with performance schedules will be examined. Project past performances that are older than 5 years will receive a lesser rating than those references for projects accomplished within the past 5 years. Projects that are submitted and not constructed will not be considered.

5. Reputation in A/E Community: Reputation and standing of the firm and its principal officers within the design community with respect to professional performance, general management and cooperativeness, including awards, merits and recommendations.

6. Claims and Terminations: Record of significant claims against the firm because of improper or incomplete architectural and engineering services.

7. Experience in construction period services to include professional field inspections during the construction period, review of construction submittals, support in answering requests for information during the construction period, and support of construction contract changes to include drafting statements of work, and cost estimates shall be included as an evaluation criterion when construction period services is included in the statement of work for A-E services.

Please submit the following VAAR clause 852.219-75 with your SF330s submissions:

852.219-75 VA Notice of Limitations on Subcontracting - Certificate of Compliance for Services and Construction.

As prescribed in 819.7011(b), insert the following clause:

VA Notice of Limitations on Subcontracting - Certificate of Compliance for Services and Construction (NOV 2022)

(a) Pursuant to 38 U.S.C. 8127(k)(2), the offeror certifies that -

(1) If awarded a contract (see FAR 2.101 definition), it will comply with the limitations on subcontracting requirement as provided in the solicitation and the resultant contract, as follows: [Contracting Officer check the appropriate box below based on the predominant NAICS code assigned to the instant acquisition as set forth in FAR 19.102.]

(i) X□ Services. In the case of a contract for services (except construction), the contractor will not pay more than 50% of the amount paid by the government to it to firms that are not VIP-listed SDVOSBs as set forth in 852.219-73 or VOSBs as set forth in 852.219-74. Any work that a similarly situated VIP-listed subcontractor further subcontracts will count towards the 50% subcontract amount that cannot be exceeded. Other direct costs may be excluded to the extent they are not the principal purpose of the acquisition and small business concerns do not provide the service as set forth in 13 CFR 125.6.

(ii) □ General construction. In the case of a contract for general construction, the contractor will not pay more than 85% of the amount paid by the government to it to firms that are not VIP-listed SDVOSBs as set forth in 852.219-73or VOSBs as set forth in 852.219-74. Any work that a similarly situated VIP-listed subcontractor further subcontracts will count towards the 85% subcontract amount that cannot be exceeded. Cost of materials are excluded and not considered to be subcontracted.

(iii) □ Special trade construction contractors. In the case of a contract for special trade contractors, the contractor will not pay more than 75% of the amount paid by the government to it to firms that are not VIP-listed SDVOSBs as set forth in 852.219-73 or VOSBs as set forth in 852.219-74. Any work that a similarly situated subcontractor further subcontracts will count towards the 75% subcontract amount that cannot be exceeded. Cost of materials are excluded and not considered to be subcontracted.

(2) The offeror acknowledges that this certification concerns a matter within the jurisdiction of an Agency of the United States. The offeror further acknowledges that this certification is subject to Title 18, United States Code, Section 1001, and, as such, a false, fictitious, or fraudulent certification may render the offeror subject to criminal, civil, or administrative penalties, including prosecution.

(3) If VA determines that an SDVOSB/VOSB awarded a contract pursuant to 38 U.S.C. 8127 did not act in good faith, such SDVOSB/VOSB shall be subject to any or all of the following:

(i) Referral to the VA Suspension and Debarment Committee;

(ii) A fine under section 16(g)(1) of the Small Business Act (15 U.S.C. 645(g)(1)); and

(iii) Prosecution for violating section 1001 of title 18.

(b) The offeror represents and understands that by submission of its offer and award of a contract it may be required to provide copies of documents or records to VA that VA may review to determine whether the offeror complied with the limitations on subcontracting requirement specified in the contract. Contracting officers may, at their discretion, require the contractor to demonstrate its compliance with the limitations on subcontracting at any time during performance and upon completion of a contract if the information regarding such compliance is not already available to the contracting officer. Evidence of compliance includes, but is not limited to, invoices, copies of subcontracts, or a list of the value of tasks performed.

(c) The offeror further agrees to cooperate fully and make available any documents or records as may be required to enable VA to determine compliance with the limitations on subcontracting requirement. The offeror understands that failure to provide documents as requested by VA may result in remedial action as the Government deems appropriate.

(d) Offeror completed certification/fill-in required. The formal certification must be completed, signed and returned with the offeror's bid, quotation, or proposal. The Government will not consider offers for award from offerors that do not provide the certification, and all such responses will be deemed ineligible for evaluation and award.

Certification I hereby certify that if awarded the contract, [insert name of offeror] will comply with the limitations on subcontracting specified in this clause and in the resultant contract. I further certify that I am authorized to execute this certification on behalf of [insert name of offeror].

Printed Name of Signee:

Printed Title of Signee:

Signature:

Date:

Company Name and Address:

36C25527R0013
Pre-solicitation Notice

SUPPLEMENT B (For Schematics, Design Development, Construction Documents, Construction Cost Estimate and Construction Period Services)

DESIGN TIMEFRAME: A/E shall deliver final construction documents No Later Than (NLT) 180 days after the Award/Notice to Proceed Letter.

CONSTRUCTION BUDGET/DESIGN LIMITATION: $2,484,000. A/E will also be required to incorporate bid items into the bid documents that will allow for a 20% budget reduction.

B1 SCHEDULE OF SERVICES:

I. INTRODUCTION:

The mission of the Veterans Affairs Marion, Il. Health Care System) is to provide the highest quality health care to our nation’s veterans. To accomplish this mission, Marion Facility Engineering Service (FES) intends to partner with an A/E Firm on a project to Repair the Electrical Feeder System and replace transformers on the Marion VAMC Campus.

The A/E Firm must provide Basic Professional Services as delineated in the Scope of Work. As part of the Basic Professional Services, FES expects the following primary A/E disciplines to be included: Supervisor, VPIH, Architectural, Mechanical, Electrical, Plumbing (Including Fire Protection) and Historical preservation.

II. SCOPE OF WORK FOR A/E:

1. Design Development:

a. The A/E shall make investigations necessary to thoroughly evaluate the area. All designs shall be in accordance with A/E Submission Instructions for Minor and NRM Construction Program, Program Guide PG-18-15, Volume C.

b. Upon completion of initial field survey and assessment, provide a comprehensive report of existing conditions and findings to Marion, IL. Facility Engineering Service. Report will include initial cost estimate for all work included in the Repair Electrical Feeder System and replace transformers. This report will be considered the Design Narrative as referenced in ”B5 DESIGN REVIEW AND COMPLETION SCHEDULE” below.

c. The A&E shall provide all the labor, materials, equipment, and expertise to replace feeder 3 entirely, replace transformers to buildings 13, 38, and 43, and connect building 13 to emergency generator. All work will be performed in accordance with this SOW, all local, state, and federal codes, and all VA requirements. Feeder number 3, one of the three co-located primary electrical feeders, have shorted to ground. The location of the ground short is unknown. There are three feeders that run between a system of manholes on the VAMC campus. Most of the campus buildings have dual electrical feed. Existing conduits run between manholes are in an unknown condition. Transformers to buildings 13 and 43 are currently 208-volt transformers and will be replaced with 480-volt transformers. Building 43 Transformer will need to be sized to accommodate planed future expansion. This will require additional step-down transformers to be installed to accommodate existing equipment.

2. Construction Document:

a. After the VAMC approves the A/E's design development, the A/E shall prepare construction documents necessary to accomplish the approved design development.

b. As part of the 100% design submission, the A/E shall provide a written synopsis describing the overall scope of the construction project as well as any pertinent information about the project that would assist potential bidders in preparing a comprehensive bid package. This synopsis is intended to be a general description of the project not to exceed two written pages in length.

c. The final design documents from a resultant task order will be subject to review and approval (by signature) of all members of an Integrated Project Team (IPT) consisting of medical center personnel. These individuals will be identified by the COR at the first design review meeting.

3. Construction Period Service: The A/E shall perform construction period services as detailed later in this scope of work.

4. Functional Product:

a. It is important to emphasize that the A/E shall perform design development and detailed design work, and prepare detailed construction documents, keeping in mind that the end result is a completely functional and fully operational system.

b. VPIH Survey: The A/E Firm will complete a survey, including testing, identifying any and all asbestos and lead containing materials within the project area. This project will remove all lead and asbestos in areas being renovated.

c. All spaces within the scope of work must be designed according to applicable codes and standards.

d. The A/E shall submit a design narrative and design plans (35%, 65%, 95%, 100% Contract Docs for Bidding, and Release for Construction Set) specifications, submittals schedule, estimates and other documentation in accordance with the “B4 DESIGN DELIVERABLES” section of this Supplement B. The construction work will be performed under a separate Firm-Fixed-Price contract awarded by the VA. As a result, the Construction Documents must conform to the estimated Total Construction Cost Price, not including any contingencies, and convey the entire construction work completely and clearly, such that any bidder can produce an accurate bid without surveying the work site.

e. The A/E will also participate in the Marion Il. Pre-Construction Risk Assessment to determine the requirements for Infection Control, Interim Life Safety Measures, occupational safety and health, patient safety, public safety, security controls for physical and logistical access, and environmental controls and limitations on vibrations, noise, and disruptions to operations and utilities. The results of these assessments will be included in documentation submitted by the A/E pursuant to, and inclusive of, the Construction Documents.

f. Prior to submittal of a response to this proposal the A/E shall meet with the Contracting Officer’s Representative (COR) at the proposed project site to review the scope of services and the project goals. The COR will provide A/E with a copy of the portions of the latest Facilities Condition Assessment (FCA) applicable to this project.

g. Overall site plans will be provided as a Reference Drawing with Room Numbers showing the areas within the project boundary.

h. The C&A requirements do not apply, and a Security Accreditation Package is not required.

5. Sustainability Requirements:

a. Design shall comply with the most current version of the VA Sustainable Design Manual at time of award found on the VA technical Information Library https://www.cfm.va.gov/til/sustain.asp

b. The following deviations are allowed: None

c. GUIDING PRINCIPLES CHECKLIST: AE shall complete and submit the appropriate Federal Energy Management Guiding Principles Checklist https://energy.gov/eere/femp/downloads/guiding-principles-checklists-new-construction- and-modernization-and-existing

IV. A/E FEE DETERMINATION:

The A/E is to present their fee proposal for evaluation and negotiation in the following format:

1. Submit completed Price Proposal on NCO 15 Form 10-6298. The spreadsheet is to have the work broken out in hours by position, by discipline and by design phase. Include a list of the number of drawings required for each design phase broken out by drawing type per discipline. Include a summary of the foregoing with the number of hours required for each drawing type and each major task. The spreadsheet will be used to facilitate review and comprehension of work effort and document fee. Submit the electronic file of the spreadsheet upon request.

2. Include a letter of understanding with the price proposal that presents a detailed understanding of the Supplement B. The letter of understanding shall include an analysis of the fee included and excluded from 6% fee limitation as compared to the estimated Construction Budget.

3. Reproduction and delivery costs of Design Review Material and other direct costs, such as travel costs, are included in the costs for each design phase and are not reimbursable. The costs of Bidding reproduction, delivery and other direct costs in accordance with the “Milestone Submittal Requirements” are included in the CD Phase. Unused site visits will be deducted at the end of the contract.

4. Provide an outline of the Quality Assurance/Quality Control actions that your firm will take during the design process and construction period. Monthly QA/QC reports are required, including actions taken to maintain project quality, schedule and budget, and will be submitted with project invoices using the NCO 15 invoice format.

5. Correction of A/E’s Errors and Omissions, including required site visits to ascertain remedial action, is included in scope of services at no additional cost to the VA.

V. REPORTS, DRAWINGS, SPECIFICATIONS AND SCHEDULES:

1. Kick-Off Meeting:

a. An initial kickoff meeting will be held with the Contracting Officer and local staff. This meeting will be intended to provide onsite familiarization with the project. The VA will provide workload data and as-built drawings.

b. A/E Design Submissions shall comply with the VA A/E Design Submission Requirements as found in the VA Technical Information Library (TIL). The VA will provide comments and guidance following each design review session. All meetings shall be held at the Marion, Il. VAMC.

2. Schematic Design:

a. The A/E firm shall conduct an onsite review of the existing locations of the various functions that will be relocated to and/or remodeled within the space to help understand the needs of the departments. They shall meet with the representatives of these departments to review and compare the VA design guides to the specific departmental needs. This will serve as an opportunity for the A/E to gain a further understanding of the direction the facility wants the project to go.

b. After meeting with the departments, the A/E shall prepare a minimum of three separate schematic layouts of the space for review. The A/E shall provide pros and cons for each option. The A/E shall present these options to the COR who will in turn present them to the departmental leads and senior leadership. The VA will select the preferred option for the design. Space layouts shall meet current VA Space Planning Criteria’s (7610 Building Design Guide) and be in compliance with the Uniform Federal Accessibility Standards (UFAS), and VA Barrier Free Design Guide (PG-18-13).

c. At the Schematic Design Review Meeting, the A/E should be prepared to discuss the scope of the project, provide examples of current VA standard room layouts, site drawings identifying the project area showing a basic schematic layout of the various functions, a timeline for design and a brief construction summary. The A/E shall record the minutes of the meeting to document the thoughts and concerns of the facility.

3. Design Development:

a. The A/E firm shall make investigations necessary to thoroughly evaluate the conditions of the existing space. There will not be a systems redesign for this process. The design shall include any energy efficiency improvements available for the application. All designs shall be in accordance with A/E Submission Instructions for Minor and NRM Construction Program, PG-18-15, Volume C.

b. Mechanical, plumbing, electrical, and fire and safety systems must meet current codes and standards, including VA Standards. All new space and utilities will be designed to meet the Interagency Security Committee’s and other relevant physical security guidelines. The completed project shall be capable of achieving LEEDS certification.

4. Construction Documents:

a. The A/E firm shall complete such further investigations to develop the accepted design development documents into working drawings and specifications for issuance through the competitive bid process.

b. The A/E firm shall provide a complete construction plan detailing all phases and sequencing of construction to minimize the impact on the facility.

c. In most instances, the VA Master Construction Specifications will be edited and incorporated in the project specifications. However, in those instances where corresponding VA Master Construction Specifications are not available, the A/E shall develop the specification for incorporation into the project specifications. It is required that the A/E design in accordance to VA guidelines as these guidelines supersede any other industry guidelines. It is important to note that all specification sections are to be thoroughly edited to maintain uniformity of formatting and structure. All spec writer notes must be removed.

d. Working drawings and specifications shall provide for construction within the National Fire Protection Association Code, VA Standards, and other applicable national codes.

e. The A/E firm shall provide a clause in the specifications indicating method by which a contractor will provide information to the firm to allow the firm to provide as-built drawings upon completion of construction.

5. As-Built Drawings:

a. The A/E firm shall submit one (1) complete set of drawings provided on disc using AutoCAD Release 2017 or later version and also .pdf format. Models should be provided in Revit 2016 or later. The A/E shall follow the VA Standard CAD format for layering in accordance with the “B3 DESIGN CRITERIA” section of this Supplement B.

b. The A/E firm shall submit said As-Built drawings within 30 days of project completion.

6. Reproduction of Drawings and Specifications:

a. Shall be prepared in MS Word and drawings shall be prepared in MS Word and drawings shall be prepared in AutoCad 2015 (or newer) and Revit and submitted to the VA in Revit formatted files in accordance with the “B4 DESIGN DELIVERABLES” section of this Supplement B.

b. The A/E is required to prepare architectural drawings in Revit. One DVD/CD-ROM computer disk containing all reports, specifications, documents and drawings will be required for each milestone submission. The final Construction Document submission shall include copies of the original digital files (in *.dwg and *.rvt) in addition to the .pdf format files. All necessary reports, cost estimates and other documents shall be prepared in accordance with all applicable portions of the A/E Submission Instructions, Program Guide PG-08-15, and Volume C. The VA reserves the right to require immediate delivery of the A/E’s digital files to the VA at any time.

c. Specifications should be provided in both hardcopy and electronic form.

d. One half size set of drawings and one set of specs shall be sent to the Contracting Officer Representative at the 95% and 100% construction document review periods.

e. At the 95% and 100% construction document review periods, the specifications should have all revisions incorporated providing a “clean” set of specifications for review and approval.

VI. PROMOTION OF FULL AND OPEN COMPETITION:

1. A/E agrees to prepare specifications that are not competitively restrictive or proprietary. Specifications will be based on performance criteria when possible and will not use a product by a specific manufacturer, except as a basis of design.

2. If an occasion arises that use of a product by a specific manufacturer is necessary, the A/E will provide a justification including:

a. Why the particular manufacturer/product must be used or why a performance specification cannot be written (proprietary design, etc.).

b. The evaluation criteria of alternate manufacturer’s product that must be met to be considered equal. These evaluation criteria will be used to accept the alternate manufacturer’s product as equal to the specified product. These evaluation criteria shall be comprehensive to ensure an equal product is supplied meeting contract requirements.

c. In the event it is necessary to pre-qualify major components, the A/E will advise the Contracting Officer of such, so that the necessary action can be taken to establish a Qualified Products List.

d. In addition to requirements of these special provisions, a certification will be provided stating the specification solicitation is not restrictive; it has been written to provide full and open competition; and will list at least three manufacturers who can supply the specified major components or systems of the project.

VII. MISCELLANEOUS:

1. The existing drawings of the Electrical Feeder System and transformers included within the limits of this project will be provided to the A/E consultant For Reference Only. As-Built and Record Drawings have been found to not show the actual location, quantity, etc., of all building features and should only be used as a general guide. The A/E shall verify the existing drawings to the extent necessary for completion of construction. Files in *.dwg or*.rvt format will be provided to the A/E if those files are available for distribution.

2. The VA COR will assist the A/E when site inspection procedures impact the functioning of any of the building utility systems, services or health care operations. Spaces with controlled access will require a member of the VA staff to continuously escort the A/E Consultant whilst accessing the space. As a result, the A/E must coordinate with VA Engineering to identify where the A/E is intending to perform site visit surveys at least fourteen (14) days in advance of any site visit.

3. Some utility systems, services or health care operations are critical, and if a disruption is required, it must be executed outside of normal working hours. Normal working hours are Monday through Friday, 7:00 a.m. to 4:00 p.m. This schedule must be coordinated with the VA COR fourteen (14) days in advance.

4. The A/E is responsible for recording the minutes of all meetings with the VA. The format of the meeting minutes shall be subject to prior approval from the VA COR. The draft meeting minutes shall be distributed for review and comment within one working day following the meeting to the COR, who will in turn distribute the same to each invited VA-attendee as required. Meeting minutes are loaded to Submittal Exchange or equal web system. The VA shall have two working days upon receipt of the meeting draft documents to make any additional comments or corrections. The final meeting minutes shall be issued within three working days after the meeting to the VA CO and the COR.

5. Coordination of each submittal will be fully documented by the A/E. Using industry standard methods, the A/E will collect, document and resolve all comments and consolidate them into a usable format. The resolution of each comment requires the COR and commenter’s concurrence. For each design submittal, the A/E will conduct a comment review meeting where each comment received will be either:

a. Concurred as Written

b. Non-Concurred; Request Discussion

c. Requires Clarification

6. At the conclusion of the comment review meeting, the A/E will provide meeting minutes showing the status of each comment made. The resolution will be incorporated into the project documents (drawings, specifications, etc.) prior to the next submittal. Any comment resolutions not included in the project documents will be provided to the CO and COR with explanation as to why each was not included.

VIII. DESIGN FUNDING LIMITATION:

1. In accordance with FAR 52.236-22, Design within Funding Limitation (APR 1984), the estimated Total Construction Contract Price for this Project proceeding into CDs is not to exceed Construction budget listed above not including any Project Contingencies, VA Furnished/ Installed Medical Equipment, VA Furnished/Installed FFE or Professional Service Fees. The A/E is responsible for designing the Project within the estimated total Construction Contract Price for the Design Development and Construction Document phases of this Project. If, at any time, the A/E determines that the design’s construction cost (excluding contingencies) will exceed the Total Construction Contract Price (TCCP), the A/E shall immediately inform the Contracting Officer in writing. Such written notification shall include the reasons why the A/E believes the TCCP will probably be exceeded and shall offer proposed solutions to reduce the project cost to be within the TCCP.

2. Deductive alternates (acceptable to the VA) of 20% of the Total Construction Contract Price will be included in the Contract Documents. These Deductive alternatives shall not be utilized to lower the estimated Total Construction Contract Price.

IX. PROBABLE CONSTRUCTION COST ESTIMATE:

1. The estimates shall be prepared using NCO15 Form 10-6298 AE Fee Proposal Submission Form and provide sufficient detail to identify the cost of project systems and components as appropriate for the stage of development of the design in the SD, DD and CD Phases. Update construction cost data with each submittal review milestone. The presented costs shall be broken down sufficiently to allow for direct comparison cost with the contractor’s proposed cost.

2. NCO15 Form 10-6298 AE Fee Proposal Submission Form: This form serves two purposes:

a. To show the division of cost between labor and material for each cost item; and

b. To extend the level of detail of an estimate beyond square foot cost summaries.

The estimated costs shall include all labor, materials, mobilization, overhead, insurance, and applicable contractor markup. A/E may utilize their estimate worksheets if approved in advance by the VA.

3. Electronic copy of estimate shall be provided with each submittal. Estimate details shall include a breakdown by Project specification division number for labor and material broken out by quantity and unit cost for each type of material or equipment, including equipment rentals. General Division shall include costs associated with project duration. Include Summary of estimate by Division Number with each submittal.

4. Providing the estimates as "lump sum" or "allowance" figures in the Construction Documents will not be acceptable. For the Schematic estimate, a 15% total contingency allowance is allowable. For the Design Development estimate, a 10% total contingency allowance is allowable. Contingency allowances are not permitted in the final Construction Documents Estimate. Construction cost estimating shall correspond with the work shown in the drawings and be commensurate with the degree of detail shown in the drawings. Construction cost estimating shall also include all elements within the contractor’s bid; such as reasonable overhead and profit and fees across all tiers, insurance, taxes, bonds, hazardous abatement and any other such items. Costs will include itemization of the following:

a. Number of labor hours by trade (or crew1)

b. Labor dollars by trade (or crew1)

c. Material quantity

d. Material dollars

e. Equipment Rental and associated cost

f. Any other Direct cost not associated with work to be performed by a specific trade

1 When using a crew, instead of a trade, then use a crew code and include a schedule, or legend, of only the crew codes applied, showing each type of trade, each hourly rate, and each trade person quantity.

5. Some costs for General Conditions or General Requirements may also be required in the project estimate whenever these costs can be shown to be direct costs as opposed to indirect (overhead) costs. For example, if it is common practice for the Contractor to use a rented negative air HEPA machine and consumable plastic sheeting to comply with the Infection Control Risk Assessment (ICRA) requirements, then the associated costs would be direct material and labor costs. In addition, if the Construction Documents require the Contractor to perform full-time on-site superintendence solely dedicated to the construction project, then these would be direct labor costs. Furthermore, whenever the Contractor is to provide on-site factory-authorized training to the VA staff, then the travel, lodging, meals and incidental costs would be direct costs. If the Construction Documents require the Contractor to perform housekeeping services, then the associated costs would be direct costs. If the Construction Documents call the Contractor to execute specific safety and OSHA activities, then the costs associated with these activities would be direct labor and material costs; however, OSHA activities performed by the Contractor by its staff at its home office and not specified in the Construction Documents, then such associated costs would be indirect costs and would not be included with the project estimate.

B2 INDUSTRIAL HYGIENE SERVICES:

I. INDUSTRIAL HYGIENIST TASKS:

For the work scope described in B1 SCHEDULE OF SERVICES above Hazardous materials (Asbestos, Lead, Mold, heavy metal and etc…) ARE included in this task order amendment. Lead and Asbestos Hazardous Material Inventories within the project limits may be available from the VA for consultant’s reference. Hazardous Materials site visits are to have conferences and inspections as needed.

1. Architect/Engineer Responsibilities:

a. Determine if asbestos, lead or mold is present. If found, design a method for abating/remediating all asbestos containing materials, lead containing materials and mold contaminated items impacting this project.

b. Determine location of asbestos, lead and/or mold contamination, and any water and moisture damage. Work with the I.H. to uncover and assess hidden areas.

c. For mold contamination, determine entry point of water infiltration

d. For asbestos and lead contamination, determine the extent of abatement required to eliminate all impacts to this project.

e. Review the I.H. Report.

f. Produce a written report compiling all necessary information.

II. VA PROFESSIONAL INDUSTRIAL HYGIENIST (VPIH):

The A/E will retain a specialist in VPIH services to provide sufficient oversight of the abatement process. The following VPIH services will comply with federal, state and local laws and regulations:

1. Review of Contractor Provided Asbestos Abatement Plan: The VPIH is responsible for reviewing and approving the Contractor's Professional Industrial Hygienist (CPIH) work plans. Provide comments and recommendations to ensure VA personnel and/or patients are not exposed to asbestos fibers.

2. Provide Air Sampling: Provide air sampling of the construction site to verify that no asbestos fibers were released during the asbestos abatement activities. Field work and sampling activities shall be performed by trained personnel under the direction of a licensed Industrial Hygienist or Board Certified Microbial Consultant.

3. Provide Abatement Oversight: Provide oversight of the abatement contractor to ensure compliance with abatement laws and regulations.

4. Provide Final Clearance: Ensure the contractor has completed the abatement work required and provide final clearance that the abatement work is complete and there are no impacts to the Medical Center.

5. Provide Final Report: Provide a final report showing daily logs, sampling results and collected documents.

III. All work shall be in compliance with applicable laws, regulations and procedures published or issued by federal, state and local regulatory agencies for the abatement and control of hazardous materials.

B3 GOVERNMENT FURNISHED DESIGN CRITERIA (COR to verify current list against TIL):

I. The A/E shall design in accordance with the requirements of the following VA publications, which can be found in the VA Tech Info Library (TIL) at http://www.cfm.va.gov/TIL/ :

-VA Master Construction Specifications, Program Guide, PG-18-1; http://www.cfm.va.gov/TIL/spec.asp -VA Design and Construction Procedures, PG-18-3; http://www.cfm.va.gov/TIL/cPro.asp -VA Standard Details, PG-18-4, Volumes 1, 3, 4, 5, 6 & 7; http://www.cfm.va.gov/TIL/sDetail.asp -VA Equipment Guide List, PG-18-5; http://www.cfm.va.gov/TIL/equip.asp -VA Design Manuals for the applicable disciplines, PG-18-10; http://www.cfm.va.gov/til/dManual.asp -VA Design Guides for graphics, PG-18-12; http://www.cfm.va.gov/til/dGuide.asp -VA Barrier Free Design Guide, PG-18-13; http://www.cfm.va.gov/TIL/accessibility.asp -VA Environmental Compliance Manual, PG-18-17; http://www.cfm.va.gov/til/spclRqmts.asp#EC

-VA Design Alerts and Quality Alerts; http://www.cfm.va.gov/til/alert.asp -VA CAD Standards; http://www.cfm.va.gov/til/projReq.asp#cad -VA Design Review Checklists; http://www.cfm.va.gov/til/projReq.asp#reviewCheck -VA AE Design Submission Requirements; http://www.cfm.va.gov/til/aeDesSubReq.asp -Office of Construction & Facilities Management Design Manual, Architectural Design Manual, http://www.cfm.va.gov/til/dManual/dmARhosp.pdf -VA Medical Center Memorandums (“MCM”) (Request From COR)

II. Other design criteria may be required to meet specific requirements of the design work scope that are not listed above, or are not available on the VA Office of Facilities web site. The A/E is responsible for obtaining and complying with all such criteria.

B4 DESIGN DELIVERABLES:

I. DISTRIBUTION OF A/E MATERIALS TO THE VA:

The A/E shall provide the means necessary to submit large electronic files to VA recipients. Files over 10 MB may not be transmitted through the VA email system. File transfer protocol websites (FTP) are prohibited for use by VA employees. Provide Submittal Exchange or equal web system. Service should be provided through construction period services and allow use by construction contractor.

1. Reproduction and delivery costs of Design Review Material in accordance with the “Milestone Submittal Requirements” are included in the costs for each design phase and are not reimbursable.

2. Bidding and Construction Material reproduction and delivery costs in accordance with the “Milestone Submittal Requirements” are included in the CD Phase and are not reimbursable.

3. The A/E shall provide a “Stand Alone Certification Memo” to the VA with the 65% Contract Documents for Bidding. (see attached format).

4. Record Documents (“As-Built”) shall be submitted to the VA immediately prior to final acceptance of the project by the VA. Record Documents shall conform to the VA standard requirements including originals and record specifications incorporating all of the actual finished conditions, project revisions/amendments and products. Record Document Material reproduction and delivery costs in accordance with the “Milestone Submittal Requirements” are included in the CPS Phase and are not reimbursable.

II. MILESTONE SUBMITTAL REQUIREMENTS (Refer to following page):

MILESTONE SUBMITTAL REQUIREMENTS

Number of Required Submittal Documents

Submittal Description
Digital File
Letter
Drawings
.orig
.pdf
Half Size
Full Size
Mylar

Design Narrative Submittal:

Condition Assessment

Cost Estimate
1
1

35% Schematic Design Submittal:

Cost Estimate
2
2

Reports & Calculations

Outline Specifications
2
2
Drawings
2
2
1
1
Existing Condition Record Drawings
2
2

65% Design Development Submittal

Cost Estimate
2
2
Reports
2
2
Draft Specifications
2
2
Drawings
2
2
1
1
Stand Alone Certification Memo
1
1

95% Contract Document Submittal

Cost Estimate
2
2
Reports
2
2
Specifications
2
2
Drawings
3
2
2
1

100% Contract Documents for Bidding

Fiinal Cost Estimate
2
2
Reports & Calculations
2
2
Specifications
2
2
Drawings
3
2
2
1

Release for Construction Set (Incorporate all Solicitation Amendments):

Final Cost Estimate
2
2
Reports & Calculations
2
2
Specifications
2
2
Drawings
2
2
1
1
Existing Condition Record Drawings
2
2
1
1

Record Document Submittal:

Final Project Construction Cost
2
3
Operation & Maintenance Manuals
2
3
Record Specifications
2
3
Record Drawings
2
3

Note 1: “.orig” indicates digital file in the document’s original file format i.e. “.doc”, “.rvt”, “.dwg”, “xls”, etc. Note 2: Letter size reports may contain 11” x 17” drawing or exhibit pages tri-folded to letter size as required.

Note 3: Letter size (8.5” x 11”) submittal documents less than or equal to 25 pages may be stapled, all other letter size documents shall be bound with a Cover Sheet containing the Project information, date and Table of Contents.

B5 DESIGN REVIEW AND COMPLETION SCHEDULE:

I. The A/E shall perform the work required by this contract within 180 calendar days reflective of schedule below. The A/E shall provide Professional Architects and Engineers as directed by the Contracting Officer who is familiar with the work to attend the…