36C25526R0081 0002.docx
DOCX document 20 KB Posted
- Solicitation number
- 36C25526R0081
About this file
This is Amendment A0002 to solicitation 36C25526R0081 for the Resurface Campus Roads project at the Department of Veterans Affairs Leavenworth facility. The amendment publishes eleven questions submitted by offerors during the site visit phase along with official responses from the Contracting Officer. Key clarifications include: the four required on-site key personnel (Safety Officer, Site Superintendent, Quality Control, and Project Manager) must be present during construction, with the Site Superintendent required on-site at all times when work is ongoing or a stop work order will be issued at contractor expense; no additional site visits will be scheduled beyond the initial pre-proposal conference; seal coat application requirements for asphalt have been deleted from the specifications; salt guard sealant is required on pavement only, not all curb and gutter; seeding is acceptable in lieu of sod for backfilled areas; and licensed surveyors are required only as specified in the contract documents.
The amendment establishes a new proposal due date of Tuesday, May 26, 2026, at 2:00 p.m. Central Time, with submissions required at the NCO-15 Contracting Office in Leavenworth, Kansas, addressed to Contracting Officer Tim Parison. The project involves resurfacing campus roads with a magnitude estimated between $1,000,000 and $2,000,000, a 180-day period of performance, and a 100 percent set-aside for Service-Disabled Veteran-Owned Small Businesses with a requirement that the prime contractor perform no less than 15 percent of construction labor. Award will be made using the Lowest Price Technically Acceptable source selection process, and offerors must provide detailed breakdowns of labor and material costs by division for each bid item or their proposals will be deemed technically unacceptable.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25526R0081 0004.docx | DOCX document | |
| S04 Pre-Proposal Conference Attendance List 05182026.pdf | ||
| 36C25526R0081 0003.docx | DOCX document | |
| 36C25526R0081 0001.docx | DOCX document | |
| Final Drawing.pdf | ||
| 36C25526R0081.docx | DOCX document | |
| FINAL SPECS PG 01-129 589A6-26-449.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment A0002 589A6-26-449 Resurface Campus Roads, Leavenworth Questions 01-11
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 05-13-2026 589A6-26-449 36C255 Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street Trafficway Leavenworth
KS
66048 36C255 Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street Trafficway Leavenworth
KS
66048 To all Offerors/Bidders
36C25526R0081
X X X This amendment is to promulgate the following changes:
1. Publish questions/RFI with responses, see attached.
Questions with responses 01-11 attached.
Proposals are due Tuesday 26 May 2026, by 2:00pm. Send all proposals to the NCO-15 Contracting Office 3450 South 4th St Levenworth Kansas. Attn: Tim Parison Contracting Officer.
All other terms and conditions remain the same.
1. What are the key personal requirements? Of the project manager, superintendent, safety, and quality control who can wear dual hats for each role. How many of the key personnel are required to be on-site during construction?
Response: See solicitation for roles, these roles will be strictly adhered to too and any changes will still require a confirmed qualification of that role.
Of the 4-key personnel listed the desire is to have the Safety Officer, Site Superintendent, Quality Control and Project Manager on site. However, if there is work going on the Site Superintendent must be on site at all time, if not the CO will issue a stop work at the expense of the contractor.
2. Can you provide the site visit sign in sheet?
Response: See amendment A0001 in SAMS for those who were in attendance.
3. Can you provide an additional site visit? If an organized site visit cannot be accommodated, are we able to view the site for field measurements?
Response: no, an additional site visit will not be scheduled. Normally that is not granted due to the time it takes to schedule the initial site visit. Recommend you use the specs and drawings as your measure of cost.
4. Can you provide quantities of 2” mill and overlay?
Response: Drawing sheet is stationed and notes limits of work. Also see SOW and specs.
5. Can you provide quantities of curb and gutter to be removed and replaced?
Response: Drawing sheet is stationed and notes limits of work. Also see SOW and specs.
6. Can you provide quantities of concrete paving to be removed and replaced?
Response: Drawing sheet is stationed and notes limits of work. Also see SOW and specs.
7. Can you provide a marked-up plan showing the scope of work? Drawing NO. 160-L7 has no annotations of the scope of work on the drawing.
Response: See SOW and specs for details. Also see notes on Drawing.
8. Specification section 32 12 16 Asphalt Paving Section 2.4 & 3.6 call for a seal coat to be applied to the asphalt. Where will this be required? If required on the new asphalt, will we be required to wait 1 year for application or will the section 3.6 D. (Seal coating asphalt less than a year) be preferred?
Response: Delete seal coat.
9. Specification section 32 05 23 Cement And Concrete For Exterior Improvements Section 3.19 Concrete Protective Coating calls for a salt guard sealant to be applied after the concrete has been cured and backfilled. Will this be required on all curb/gutter and paving?
Response: Pavement only.
10. Will sod or seeding be required in backfilled areas with grass? If so, are we required to use sod or seed?
Response: Seeding will be acceptable.
11. Will a licensed surveyor be required for this project? The scope of work covers remove and replace work; there should be no need for a surveyor on this project.
Response: Only as required per specifications.
Final END of Questions