Attachment A Updated Quality Assurance Surveillance Plan QASP.pdf
PDF 172 KB Posted
- Solicitation number
- 36C25526Q0028
About this file
This Quality Assurance Surveillance Plan (QASP) outlines the performance monitoring procedures for Pond Restoration and Stewardship at JC & JB VA Medical Centers. The document details a performance-based approach to contract management, focusing on measuring outcomes rather than compliance processes. Key performance requirements include invasive species removal, debris and trash removal, herbicide application, mulch maintenance, underdrain inspection, pruning, plant maintenance, and annual flower replacement, with strict acceptable quality levels (AQLs) ranging from 0-5% deviation.
The QASP establishes a comprehensive surveillance methodology involving monthly and quarterly inspections, customer feedback, document reviews, and site observations. The Contracting Officer's Representative (COR) will monitor performance using a standardized Quality Assurance Monitoring Form, with a structured corrective action process that includes issuing Contract Discrepancy Reports (CDRs) for performance shortfalls. Contractors are required to acknowledge issues, submit corrective action plans, and implement improvements at no additional cost, with potential consequences including removal from the site or contract reassessment if performance standards are not consistently met.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUALITY ASSURANCE SURVEILLANCE PLAN (QASP)
Pond Restoration and Stewardship For JC & JB VAMCs
Table of Contents
QUALITY ASSURANCE SURVEILLANCE PLAN (QASP)……………………………………………2
(a). INTRODUCTION……………………………………………………………………………………...2
(b). ROLES AND RESPONSIBILITIES………………………………………………………………….3
(c). IDENTIFICATION OF REQUIRED PERFORMANCE STANDARDS/QUALITY LEVELS……3
(d). METHODOLOGIES TO MONITOR PERFORMANCE……………………………………………3
(e). QUALITY ASSURANCE DOCUMENTATION……………………………………………………..4
(f). ANALYSIS OF QUALITY ASSURANCE ASSESSMENT …………………………………………5
ATTACHMENT 1: SAMPLE QUALITY ASSURANCE MONITORING FORM……………………..9
QUALITY ASSURANCE SURVEILLANCE PLAN (QASP)
(a). INTRODUCTION:
This quality assurance surveillance plan (QASP) is pursuant to the requirements listed in the Performance Work Statement (PWS). This plan sets forth the procedures and guidelines the Wichita VA Medical Center will use in ensuring the required performance standards or services levels are achieved by the contractor.
(1). Purpose
(A). The purpose of the QASP is to describe the systematic methods used to monitor performance and to identify the required documentation and the resources to be employed. The QASP provides a means for evaluating whether the contractor is meeting the performance standards/quality levels identified in the PWS and the contractor’s quality control plan (QCP), and to ensure that the government pays only for the level of services received.
(B). This QASP defines the roles and responsibilities of all members of the contracting team , identifies the performance objectives, defines the methodologies used to monitor and evaluate the contractor’s performance, describes quality assurance documentation requirements, and describes the analysis of quality assurance monitoring results.
(2). Performance Management Approach
(A). The PWS structures the acquisition around “what” service or quality level is required, as opposed to “how” the contractor should perform the work (i.e., results, not compliance). This QASP will define the performance management approach taken by the VA Medical Centers to monitor and manage the contractor’s performance to ensure the expected outcomes or performance objectives communicated in the PWS are achieved. Performance management rests on developing a capability to review and analyze information generated through performance assessment. The ability to make decisions based on the analysis of performance data is the cornerstone of performance management; this analysis yields information that indicates whether expected outcomes for the project are being achieved by the contractor.
(B). Performance management represents a significant shift from the more traditional quality assurance (QA) concepts in several ways. Performance management focuses on assessing whether outcomes are being achieved and to what extent. This approach migrates away from scrutiny of compliance with the processes and practices used to achieve the outcome. A performance-based approach enables the contractor to play a large role in how the work is performed, as long as the proposed processes are within the stated constraints. The only exceptions to process reviews are those required by law (federal, state, and local) and compelling business situations, such as safety and health. A “results” focus provides the contractor flexibility to continuously improve and innovate over the course of the contract as long as the critical outcomes expected are being achieved and/or the desired performance levels are being met.
(3). Performance Management Strategy
(A). The contractor is responsible for the quality of all work performed. The contractor measures that quality through the contractor’s own quality control (QC) program. QC is work output, not workers, and therefore includes all work performed under this contract regardless of whether the work is performed by contractor employees or by subcontractors. The contractor’s QCP will set forth the staffing and procedures for self-inspecting the quality, timeliness, responsiveness, customer satisfaction, and other performance requirements in the PWS. The contractor will develop and implement a performance management system with processes to assess and report its performance to the designated government representative. The contractor’s QCP will set forth the staffing and procedures for self-inspecting the quality, timeliness, responsiveness, customer satisfaction, and other performance requirements in the PWS. This QASP enables the government to take advantage of the contractor’s QC program.
(B). The government representative(s) will monitor performance and review performance reports furnished by the contractor to determine how the contractor is performing against communicated performance objectives. The government will make determination regarding incentives based on performance measurement metric data and notify the contractor of those decisions. The contractor will be responsible for making required changes in processes and practices to ensure performance is managed effectively.
(b). ROLES AND RESPONSIBILITIES:
(1). The Contracting Officer
The contracting officer (CO) is responsible for monitoring contract compliance, contract administration, and cost control and for resolving any differences between the observations documented by the contracting officer's representative (COR) and the contractor. The CO will designate one full-time COR as the government authority for performance management. The number of additional representatives serving as technical inspectors depends on the complexity of the services measured, as well as the contractor’s performance, and must be identified and designated by the Contractor.
(2). The Contracting Officer’s Representative
The contracting officer’s representative (COR) is designated in writing by the CO to act as his or her authorized representative to assist in administering a contract. COR limitations are contained in the written appointment letter. The COR is responsible for technical administration of the project and ensures proper government surveillance of the contractor’s performance. The COR is not empowered to make any contractual commitments or to authorize any contractual changes on the government’s behalf. Any changes that the contractor deems may affect contract price, terms, or conditions shall be referred to the CO for action. The COR will have the responsibility for completing QA monitoring forms used to document the inspection and evaluation of the contractor’s work performance. Government surveillance may occur under the inspection of services clause for any service relating to the contract.
(c). IDENTIFICATION OF REQUIRED PERFORMANCE STANDARDS/QUALITY LEVELS:
The required performance standards and/or quality levels are included in the PWS and in Attachment 1, “Performance Requirements Summary” to this document. If the contractor meets the required service or performance level, it will be paid the amount agreed on in the contract. Failure to meet the required service or performance levels may be documented in the contractor’s performance evaluation and will be used in considering a determination of suitability for future contract extensions of services.
(d). METHODOLOGIES TO MONITOR PERFORMANCE:
(1). Surveillance Techniques
In an effort to minimize the performance management burden, simplified surveillance methods shall be used by the government to evaluate contractor performance when appropriate. The primary methods of surveillance are:
(A). Random monitoring, which shall be performed by the COR or his designated inspector.
(B). Periodic Inspection – COR typically performs the periodic inspection on a monthly or quarterly basis.
(C). Feedback from facilities being served by the contract, satisfaction or complaints.
(D). Monthly review of invoices, reports, and documents.
(E). Contractor quality assurance reports.
(2). Customer Feedback .
(A). The contractor is expected to establish and maintain professional communication between its employees and customers. The primary objective of this communication is customer satisfaction.
Customer satisfaction is the most significant external indicator of the success and effectiveness of all services provided and can be measured through customer complaints.
(B). Performance management drives the contractor to be customer focused through initially and internally addressing customer complaints and investigating the issues and/or problems but the customer always has the option to communicate complaints to the COR, as opposed to the contractor.
(C). Customer complaints, to be considered valid, must set forth clearly and in writing the detailed nature of the complaint, must be signed, and must be forwarded to the COR. The COR will accept those customer complaints and investigate using the Quality Assurance Monitoring Form identified in Attachment 2.
(D). Customer feedback may also be obtained either from the results of formal customer satisfaction surveys or from random customer complaints.
(3). Acceptable Quality Levels
The acceptable quality levels (AQLs) included in Attachment 1, Performance Requirements Summary Table, for contractor performance are structured to allow the contractor to manage how the work is performed while providing negative incentives for performance shortfalls. For certain critical activities such as those involving delivery time frames and, the desired performance level is established at 100 percent.
Other levels of performance are keyed to the relative importance of the task to the overall mission performance at the VA Medical Centers.
(e). QUALITY ASSURANCE DOCUMENTATION:
(1). The Performance Management Feedback Loop
The performance management feedback loop begins with the communication of expected outcomes.
Performance standards are expressed in the PWS.
(2). Monitoring Forms
(A). The government’s QA surveillance, accomplished by the COR, will be reported using the monitoring form in Attachments 1. The form, when completed, will document the government’s assessment of the contractor’s performance under the contract to ensure that the required results are being achieved.
(B). The COR will retain a copy of all completed QA surveillance forms.
(f). ANALYSIS OF QUALITY ASSURANCE ASSESSMENT:
(1). Determining Performance
Government shall use the monitoring methods cited to determine whether the performance standards/service levels/AQLs have been met. If the contractor has not met the minimum requirements, it may be asked to develop a corrective action plan to show how and by what date it intends to bring performance up to the required levels.
(2). Reporting
(A). Semi-annually the COR will prepare a written report summarizing the overall results of the quality assurance surveillance of the contractor’s performance. This written report, which includes the monthly report and the completed quality assurance monitoring forms (Attachment 2), will become part of the QA documentation. It will enable the government to demonstrate whether the contractor is meeting the stated objectives and/or performance standards, including cost/technical/scheduling objectives.
(3). Reviews and Resolution
(A). The COR may require the contractor’s project manager, or a designated alternate, to meet with the CO, COR, and other government personnel as deemed necessary to discuss performance evaluation.
The COR will define a frequency of in-depth reviews with the contractor, including appropriate self-assessments by the contractor; however, if the need arises, the contractor will meet with the COR as often as required or per the contractor’s request. The agenda of the reviews may include:
(i). Monthly performance assessment data and trend analysis
(ii). Issues and concerns of both parties
(iii). Projected outlook for upcoming months and progress against expected trends, including a corrective action plan analysis
(iv). Recommendations for improved efficiency and/or effectiveness
(B).The COR must coordinate and communicate with the contractor to resolve issues and concerns regarding marginal or unacceptable performance.
(C). The COR and contractor should jointly formulate tactical and long-term courses of action. Decisions regarding changes to metrics, thresholds, or service levels should be clearly documented. Changes to service levels, procedures, and metrics will be incorporated as a contract modification at the convenience of the CO.
Performance Requirements Summary:
Acceptance Quality Level (AQL) Summary Table
Performance Requirement
Performance Standard
Surveillance Method
Frequency AQL Corrective Action Process
Removal of Invasive/Weedy Species
100% removal in designated areas per MSD specs
Site Inspection
/ COR
Observation
Monthly 0% CDR issued for any missed areas; CAP required within 5 business days
Debris, Trash, and Silt Removal
100% removal from all identified zones
Field Inspection / Photo Documentation
Monthly 0% Immediate rework required; CDR if recurring
Herbicide Application & Weed Control
100% compliance with label, SDS, and licensing
SDS Review / Applicator License Check / Site Inspection
Per Application
0% CDR for non-compliance;
suspension of chemical use until resolved
Mulch Maintenance
95% of designated areas properly mulched
Visual Inspection
Monthly 5% CDR if >5% of areas are bare; re-mulching required
Underdrain Inspection & Flushing
100% of cleanouts inspected and flushed as needed
COR
Inspection / Field Report Review
Quarterly 0% CDR for missed inspections or sediment buildup
Pruning & Plant Maintenance
100% compliance with horticultural standards
COR
Observation / Site Walkthrough
Monthly 0% CDR for improper pruning or plant damage
Annual Flower Replacement
100% of approved flowers
COR Approval / Site Inspection
Annually 0% CDR for unapproved or missing plantings
Performance Requirement
Performance Standard
Surveillance Method
Frequency AQL Corrective Action Process planted and maintained
Field Report Submission
100% of visits documented with signed reports
Document Review
Per Visit 0% CDR for missing/incomplete reports
Off-Hours Maintenance (Bldg. 55)
100% compliance with schedule
COR
Verification / Time Logs
Quarterly 0% CDR for any work during restricted hours
Quarterly COR Walkthroughs
100% contractor participation and correction of noted issues
COR
Inspection / Follow-up Review
Quarterly 0% CDR for missed walkthroughs or uncorrected issues
Personnel Identification &
PPE
100% of staff properly identified and equipped
Visual Inspection / VA Police Reports
Ongoing 0% CDR for violations;
removal from site if repeated
Contractor Qualifications
100% of staff meet BMP and stewardship experience requirements
Resume Review / License Verification
At Award & As Needed
0% CDR for unqualified personnel;
replacement required
Corrective Action Process Summary
• Unacceptable performance is identified through:
• Observation of actual performance
• Inspection of services
• Review of documentation and complaints
• COR Actions:
• Notify contractor (verbal or written)
• Document all communications
• Issue Contract Discrepancy Report (CDR) when formal action is needed
• Contractor Actions:
• Acknowledge CDR in writing
• Submit Corrective Action Plan (CAP) within specified timeframe
• Implement corrective measures at no additional cost to the Government
• Government Rights:
• Increase or decrease surveillance based on performance
ATTACHMENT 1: SAMPLE QUALITY ASSURANCE MONITORING FORM
Contract #:____________________________________
Contractor:____________________________________
SERVICE or STANDARD:
SURVEY PERIOD:
SURVEILLANCE METHOD (Check):
[__] Periodic Inspection [__] Customer Complaint [__] Review of documents
LEVEL OF SURVEILLANCE (Check):
[__] Monthly [__] Quarterly [ ] As needed
PERCENTAGE OF ITEMS SAMPLED DURING SURVEY PERIOD: ______ %
ANALYSIS OF RESULTS:
Observed Service Provider Performance Measurement Rate: ______%
Service Provider’s Performance (Check): [__] Meets Standards
[__] Does Not Meet Standards
Narrative of Performance During Survey Period:
PREPARED BY: ___________________________________ DATE: _________________