36C25525Q0499 0001.docx

DOCX document 121 KB Posted

Attached to
R410--Lockout/Tagout | Kansas City VAMC
Solicitation number
36C25525Q0499_1
Issued by

About this file

This document is an Amendment (Addenda #1) to Request for Quote (RFQ) 36C25525Q0499 for Lockout/Tagout (LOTO) Services for the Kansas City VA Medical Center (VAMC). The solicitation covers developing energy control procedures for 399 pieces of equipment across two campus locations: the main VAMC and the Honor Annex in Kansas City, Missouri. The amendment addresses eight vendor questions regarding equipment procedures, location details, training requirements, and software specifications.

Key details include the requirement for durable energy source tags, LOTO software training split across employee shifts, and five training sessions focused on LOTO software. The solicitation requires developing procedures for multiple building locations, with the VA providing current confined space area information. The response deadline has been extended to August 26, 2025, at 16:30 CDT, and the contract is being administered by the Department of Veterans Affairs Network Contracting Office in Leavenworth, Kansas. Optional contract line items (CLINs) will only require software licensing continuation in subsequent years, with no additional services required.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

08-21-2025

None 36C255 Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street Trafficway

Leavenworth KS 66048

36C255 Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street Trafficway

Leavenworth KS 66048 To all Offerors/Bidders

36C25525Q0499

X

** HOUR & DATE for Receipt of Offers is EXTENDED to: 08-26-2025 16:30 CDT

ONE (1)

This amendment is to answer questions from vendors.

All other terms and conditions remain the same.

Laura Ferguson

ADDENDA #1 August 21, 2025

RFQ 36C25525Q0499

LockOut/TagOut Services for the Kansas City VAMC

QUESTIONS AND ANSWERS

1. Question #1: Does any of the 399 pieces of equipment require more than 1 energy control procedure (ECP)?

a. If so, can you please specify how many additional ECP's you expect may be needed based on multiple energy sources?"

Answer #1:No the 399 will be the only equipment requiring procedures

2. Question #2: The SOW, page 8, states that “Services shall be executed throughout all KCVAMC buildings at two campus locations (divisions):”, however only one address is listed. Can the government confirm the number of locations that this requirement pertains to?

Answer #2: The other location is the Honor Annex 4251 Northern Ave, Kansas City, MO 64133

3. Question #3: Relating to the question above, can the government confirm that the 399 count of procedures is a either a not to exceed amount for the SOW, or just a rough estimate of procedures that may be exceeded based on site conditions?

Answer #3:This will not exceed the SOW, both the Maintenance and Operation supervisor and compliance office counted the devices.

4. Question #4: Regarding the energy source tags to be installed on the equipment, does the government require a specific type of material (brass, plastic, etc.) to be utilized for the energy source tags and mounting hardware?

Answer #4: Material should be durable

5. Question #5: In the SOW it mentions linking Confined Space Permit documents to respective LOTO procedures. Will the government supply the current confined space permits, or is the contractor required to also develop confined space entry procedures as a part of this effort?

Answer #5:KCVA will provide the current confined space areas but will not need specific procedures for devices.

6. Question #6: Regarding the five training sessions to be performed, does the government require training solely on the LOTO software, or does the training also need to cover LOTO regulatory requirements? As a follow up question, are all training sessions required to be performed within the same time period (i.e. consecutive days), or do they need to be split up over multiple weeks?

Answer #6: This training is for LOTO software, and the training will need to be split to accommodate employee shifts.

7. Question #7: Regarding the optional CLINs, does the government solely require the licensing be continued for each year, or are any other LOTO services required during the option years? For example, audit existing procedures, additional training, etc. If other services are required, could you list the deliverable requirements?

Answer #7: No further services will be required

8. Question #8: Regarding the software to be utilized, Section D(12) of the SOW mentions “eLOTO training and software”. Specifically, eLOTO is software sold by the Master Lock company. Does the government require that the specific MasterLock eLOTO software be used, or may other programs be used, provided they meet the SOW requirements?

Answer #8:We don’t require it to be a specific MasterLock eLOTO program