This document is an Amendment to Solicitation for grease trap services issued by the Department of Veterans Affairs Great Lakes Acquisition Center. The amendment extends the response due date to November 27, 2026, at 10:00 AM CST and answers twenty vendor questions regarding solicitation requirements. The amendment also incorporates an updated Performance Work Statement (PWS) that adds the capacity specification of the lift station located in Building 410 (approximately 3,000 gallons). The solicitation is a total small business set-aside with SDVOSB/VOSB evaluation preferences applied; all offerors must complete and sign VAAR 852.219-75 (VA Notice of Limitations on Subcontracting) regardless of business size or status. Quotes should be submitted by email to Sonja Freeman (Sonja.freeman@va.gov) with no specified page limit or file format requirement.
The contract is a follow-on to Contract #36C252-22-P-0128 and covers grease trap and lift station services at the Tomah VA Medical Center in Tomah, Wisconsin. Services include six annual service inspections (December, February, April, June, August, October) to pump and clean six grease traps ranging from 17 to 2,000 gallons, plus up to three annual lift station pump service calls for the 3,000-gallon capacity unit in Building 410. The contractor must provide all labor, materials, equipment, and tools; comply with federal, state, and local safety regulations; and submit service reports documenting date of service, actions taken, parts replaced, labor hours, and equipment serviced. Work is performed Monday through Friday, 7:30 AM to 4:30 PM, excluding federal holidays, with coordination required through the Contracting Officer's Representative. Offerors should provide pricing per service call and total price for three service calls in the price schedule section.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25227Q0069 0001_2 SAM.gov.pdf | ||
| 36C25227Q0069 0001_1.docx | DOCX document | |
| 36C25227Q0069_1 SAM.gov.pdf | ||
| WG Determination NO. 2015-4929.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE 7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO. 1. CONTRACT ID CODE
FACILITY CODE CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30 PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243
(Type or print) (Type or print)
(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code)
(If other than Item 6)
(Specify type of modification and authority)
(such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
None
1 8 36C25227Q0069
0001 11-19-2026
676-27-1-559-0001
36C252
Department of Veterans Affairs 115 South 84th Street, Suite 101
Milwaukee WI 53214-1476
36C252
Department of Veterans Affairs Great Lakes Acquisition Center - HC 115 South 84th Street, Suite 101
Milwaukee WI 53214-1476
To all Offerors/Bidders
36C25227Q0069
X
X X
** HOUR & DATE for Receipt of Offers is EXTENDED to: 11-27-2026 10:00 CST
676-3670162-559-854100-2543 010055590 x 1
This amendment is issued to:
1. Answer questions submitted by interested offerors.
2. Extend the response due date to 11-27-2026 at 10:00 AM CST. (This change corrects the discrepancy between the due date displayed on page 1 of the SF1449 and the due date displayed on the SAM.gov notice).
3. Incorporate an updated Performance Work Statement (PWS). The PWS was revised to add the capacity of the lift station located in Bldg. 410.
All other terms and conditions of the solicitation remain unchanged.
Ashley Johnson Contracting Officer
Vendor Questions and Answers:
1. Is this requirement open to all small businesses, or limited to SDVOSB or VOSB firms only?
The requirement is solicited as a total small business set-aside. It is not restricted to SDVOSBs or VOSBs. To be eligible to compete for award, vendors much qualify as a small business under the applicable NAICS code assigned to this solicitation and have an active registration in SAM.gov reflecting that NAICS code.
2. Which limitation on subcontracting applies: FAR 52.219-14 (similarly situated small businesses) or VAAR 852.219-75? Clause 852.219-75, VA Notice of Limitations on Subcontracting, is included in Section C (pages 35–36) with the services box ticked, and its certificate is mandatory. This solicitation is a total small business set-aside rather than an SDVOSB or VOSB set-aside.
Does the 50 percent limitation apply to a small-business prime contractor, and must the subcontracted portion be performed by certified SDVOSB or VOSB firms?
VAAR 852.219-75 is included because SDVOSB/VOSB evaluation preferences will be applied to this requirement. If an SDVOSB or VOSB receives the award based on this preference, it must comply with the applicable Limitations on Subcontracting requirements. Please note that VAAR 852.219-75 must be completed and signed by all offerors, regardless of business size and status because it is a mandatory VA subcontracting compliance certification under VAAR Part 852.
Quotes will not be considered for award if VAAR 852.219-75 is not completed and signed. Because the anticipated value of this requirement is below the Simplified Acquisition Threshold, FAR 52.219-14 does not apply.
3. Item 5.C on page 3 refers to the 52.212-1 addendum for submission instructions, but the addendum (pages 39–41) does not give an email address, file format or page limit.
Please confirm how quotes should be submitted.
Quotes should be submitted by email to the primary point of contact listed on SAM.gov: Sonja Freeman, Sonja.freeman@va.gov. Addendum to FAR 52.212-1, Instructions to Offerors, specifies required administrative information. Offerors may provide information demonstrating technical capability, relevant experience, and Veterans Involvement (if applicable) in the format of their choosing. There is no page limit.
4. Block 8 of the SF1449 shows quotes due 20 November 2026 at 10:00 Central; the SAM.gov listing shows 23 November. Which date applies?
This amendment extends the response due date to Wednesday, November 25, 2026, at 10:00 AM CST. (This corrects the discrepancy between the due date on the SF1449 and the due date on the SAM.gov notice).
5. For line items x002, what is the capacity of the lift station in Building 410, and is the line paid per call-out actually ordered or as a fixed annual amount regardless of calls?
The lift station capacity in Building 410 is approximately 3,000 gallons. The line item will be paid per service call. Offerors should provide pricing per service call and the total price for three service calls in Section B.2 Price/Schedule.
6. Incumbent Contract: Is this requirement a follow-on to an existing contract? If so, could you confirm the incumbent contractor, previous contract number, and whether historical pricing information is publicly available?
This solicitation is issued to award a follow-on contract to Contract #36C252-22-P-0128. Award details, to include award amount, for Contract #36C252-22-P-0128 may be found on SAM.gov.
mailto:Sonja.freeman@va.gov
7. Is a pre-quotation site visit scheduled or available? If not, would the VA consider arranging a walkthrough for interested vendors before the quotation deadline?
A site visit is not scheduled for a specific date and time. The VA will coordinate site visits as requested by interested offerors. Please contact the Contracting Officer’s Representative, Zachary Hibma, at 608-372-3971 ext. 64360, to schedule a site visit.
8. Subcontracting: Gordon Group LLC anticipates partnering with a qualified specialty subcontractor.
Are there any solicitation-specific subcontractor qualifications or documents that must accompany our quotation?
The prime may rely on the proposed subcontractor’s technical capabilities and relevant experience, provided the quote identifies the subcontractor’s role. The prime must demonstrate in its quote an understanding of the requirement and their ability to manage and oversee contract performance.
The quote should demonstrate that the proposed subcontractor has relevant experience performing the required services.
9. PWS 1.C requires up to three (3) service calls per contract year to pump the lift station in Building 410, but the capacity is not stated. Can you confirm the lift station's wet-well capacity in gallons and the typical volume removed per service call?
Lift station capacity is approximately 3,000 gallons. Offerors should use a 3,000-gallon capacity as the basis for estimating the volume of material to be removed during each service visit and for developing their pricing. (The PWS has been revised to include the lift station capacity at Bldg.
410).
10. Is there a government-recommended or required disposal facility for the grease removed under PWS 1.B.1, or may the contractor use its own permitted disposal/receiving facility?
The Tomah VA does not provide an approved onsite disposal or receiving facility for grease-trap waste. The contractor is responsible for transporting the waste to an offsite location. Please refer to the Performance Work Statement (Section B.3) in the solicitation.
11. Are disposal manifests or receipts required with the Service Report?
Please refer to the #6 Contract Deliverables in the PWS for service report requirements.
12. Will the VA provide water (e.g., a hose connection) at the grease trap locations for cleaning, and are the 17- and 30-gallon traps (Buildings 409–412) indoor under-sink units that must be cleaned by hand?
A hose connection is available at grease trap locations for cleaning. There are no indoor under-sink units.
13. For CLIN x001 (6 JB per year), does each "job" (service inspection) include pumping and cleaning all six grease traps listed in PWS 1.A? Can you also share the approximate gallons of grease/waste removed per service under the prior contract?
Each job includes servicing all six grease traps in accordance with the PWS. Each of the six services will be serviced six times per year. Offerors should use the grease trap capacities identified in the PWS as the basis for estimating the volume of material to be removed during each service visit and for developing their pricing. (Refer to Question-Answer #17).
14, We are interested in bidding on this project as a subcontractor. Could you please provide a list of general contractors we can submit our bid to?
The VA does not maintain a list of general contractors seeking subcontractor support.
15. How many grease traps are there, and what size is each trap?
Please refer to Section B.3. Performance Work Statement for the number of grease traps and the size of each.
16. Where are the traps located, inside or outside the building?
The grease trap at Bldg. 424 is outside the building. All other grease traps for this requirement are inside.
17. Roughly how many gallons come out per service?
Offerors should use the grease trap capacities identified in the PWS as the basis for estimating the volume of material to be removed during each service visit and for developing their pricing. The actual volume of accumulated grease and waste removed may vary depending on usage and accumulation. However, the Government is not providing a separate estimated volume for each cleaning. Offerors should account for the identified trap capacities when estimating resources.
18. The lift station pumping is up to three calls a year. How many were actually used last year?
The service call requirement is not included in the current contract. This will be a new requirement.
19. The SAM.gov notice shows the set-aside as "None." The RFQ addendum states the procurement is 100% set aside for small businesses and includes FAR 52.219-6. The RFQ also includes VAAR 852.219- 75 with the services box checked, which limits payments to firms that are not certified SDVOSBs or VOSBs to 50%. Which applies to this RFQ? If 852.219-75 applies, please confirm that a small-business subcontractor that is not a certified SDVOSB or VOSB may perform up to 50% of the amount paid by the Government.
Please refer to Question-Answer #2.
20. The package includes an 852.219-75 certification page. If a subcontractor, is not SDVOSB/VOSB and represents about 87% of the price, on a 100% small-business set-aside, is that certification page required on this buy, and if so, how should it be completed — or should the page be removed?
Please refer to Question-Answer #2.
Section 9.h / VHA Directive 1192, requires the contractor to ensure implementation including providing face masks and influenza vaccines for all employees working at a VA facility. For the grease trap service technicians (non-clinical contractor personnel), does compliance require influenza vaccination specifically, or does wearing a face mask on site satisfy the directive?
The requiring activity is seeking additional clarification regarding the applicability of the VA influenza vaccination requirements to this contract. A response will be provided through a subsequent amendment.
GREASE TRAP SERVICES
PERFORMANCE WORK STATEMENT
Contractor shall provide all labor, materials, equipment, and tools necessary to clean grease traps and to dispose of grease. Grease traps are located at/in Building 424 (in-patient dining facility), 405, 409, 410, 411 and 412 at the Tomah VAMC, Tomah WI., according to this Performance Work Statement.
1. SCOPE
A. Equipment to be covered under this contract.
1) One (1) 2000 Gallon Grease Trap (Located in Building 424).
2) Two (2) 30 Gallon Grease Traps (Buildings 409 & 410).
3) Two (2) 17 Gallon Grease Traps (Buildings 411 & 412).
4) One (1) 240 Gallon Grease Trap (Building 405).
B. Provide six (6) service inspections per contract year, to occur in the months of December, February, April, June, August, and October. Each service inspection shall require contractor to:
1) Remove and dispose of grease per all Federal, State and Local regulations.
2) Clean grease traps after removal of grease is completed.
C. Provide up to three (3) service calls per contract year to pump lift station located in Building 410. Lift station capacity is approximately 3,000 gallons.
D. Any changes to this PWS shall be authorized and approved only through written modification of this contract from the CO (Contracting Officer) in coordination with the COR (Contracting Officers Representative). Costs incurred by the contractor through the actions of parties other than the Contracting Officer shall be borne by the contractor.
E. Notwithstanding, the Contractor shall perform no additional work without the prior written authorization of the Contracting Officer. Any additional work, which may be performed by the Contractor without this approval, will be performed by the Contractor at no additional cost to the Government.
Within fourteen (14) days of the award of this contract, the Contractor and the Government shall agree upon a date for work to take place.
2. SERVICE HOURS AND FEDERAL HOLIDAYS
A. Normal hours of coverage are Monday through Friday from 7:30 am to 4:30 pm, excluding holidays. All work shall be performed during normal hours of coverage unless otherwise requested or approved by the COR or their designee.
B. All contract work shall be on a date and time mutually agreed upon between the Contractor and the COR.
C. Federal Holidays observed by the VAMC are:
New Years’ Day Independence Day Christmas Day
Columbus Day Labor Day Martin Luther King Day
Memorial Day Presidents’ Day Veterans’ Day
Juneteenth Thanksgiving Day
3. GENERAL INFORMATION
A. The contractor shall comply with all applicable federal, state and local safety regulations.
B. The Contractor shall coordinate all dates for service and testing with contract COR.
C. The contractor’s FST (Field Service Technician) shall contact the COR/POC prior to performing service at this location and shall communicate to the COR of their presence on the Tomah VA Medical Center campus.
D. Contractor is responsible to replace any items damaged by the contractor, sub-contractor, their employees or equipment at no extra charge to the Government.
E. Contractor personnel must conduct their work in a manner that does not interfere with the normal functions of the facility and will stop work if asked by the CO/COR as required if interruptions do occur.
4. CONTRACTING OFFICER’S REPRESENTATIVE (COR)
A. Scheduling of work shall be arranged with at least one, or all the Point of Contacts in the following order; contract COR (Contracting Officers Representative) or contract ACOR (Alternate Contracting Officers Representative).
5. ORIENTATION FOR CONTRACTOR EMPLOYEES:
A. Contractor will attend an orientation meeting as arranged by the Contracting Officer's Representative (COR). The VA will schedule this meeting and it will include discussion of the following topics: (VA will provide information to the contractor regarding these topics and will document the meeting)
• Fire and Safety
• Infection control
• Disaster procedures - Other
B. The Contractor will be responsible to ensure that Contractor employees coming to the work site will receive the information required above.
6. CONTRACT DELIVERABLES
Contractor shall provide, to the COR after completion of work, at the minimum, the following deliverables:
A. Provide record of pump out to include the completed Service Report to Facilities Services Building 40, Room 108a with the following applicable items:
1) Date of service.
2) Action taken.
3) Parts replaced.
4) Labor hours.
5) Equipment serviced.
B. At start of each contract year, Contractor shall provide service schedule to COR for approval.
7. SECURITY REQUIREMENTS
A. All Contractor FST’s (Field Service Technician(s)) shall obtain contractor ID badges from the COR. Identification shall be worn visible always by the Contractor and all FST’s while on premises. Contractor shall coordinate with COR to acquire said identification badges.
B. During normal working hours of operation, Monday through Friday, the contractor shall check in with the COR/Tomah VAMC (Veterans Affairs Medical Center) Point of Contact (POC) when arriving to perform work and check out with the COR/Tomah VAMC POC when work/work day is complete.
C. During other than normal hours of operation, the contractor shall sign in and out with the Fire Department located on the east end of B36.
D. It is the responsibility of the Contractor to park in the appropriate designated parking areas. Information on parking is available from the VA Police Section. The VAMC will not invalidate or make reimbursement for parking violations of the Contractor under any conditions.
E. Effective October 1, 2019, smoking is prohibited both inside and outside (entire campus) at the VAMC.
F. Possession of weapons is prohibited. Enclosed containers, including tool kits, shall be subject to search. Violations of VA regulations may result in citation answerable in the United States (Federal) District Court, not a local district, state, or municipal court.
8. PLACE OF PERFORMANCE
Tomah VA Medical Center, 500 E. Veterans St., Tomah, WI. 54660
9. PERIOD OF PERFORMANCE
A. Support and service, as defined in this PWS, is to occur as scheduled and as required during the period of performance.
B. Work shall be completed in a timely manner and a performance schedule shall be coordinated with the Government upon contract award.
END
| 2. SERVICE HOURS AND FEDERAL HOLIDAYS |
| A. Normal hours of coverage are Monday through Friday from 7:30 am to 4:30 pm, excluding holidays. All work shall be performed during normal hours of coverage unless otherwise requested or approved by the COR or their designee. |
| B. All contract work shall be on a date and time mutually agreed upon between the Contractor and the COR. |
| C. Federal Holidays observed by the VAMC are: |
| 5. ORIENTATION FOR CONTRACTOR EMPLOYEES: |
| B. During normal working hours of operation, Monday through Friday, the contractor shall check in with the COR/Tomah VAMC (Veterans Affairs Medical Center) Point of Contact (POC) when arriving to perform work and check out with the COR/Tomah VAMC POC ... |
| C. During other than normal hours of operation, the contractor shall sign in and out with the Fire Department located on the east end of B36. |
| F. Possession of weapons is prohibited. Enclosed containers, including tool kits, shall be subject to search. Violations of VA regulations may result in citation answerable in the United States (Federal) District Court, not a local district, state, or... |
File details come from the government source that posted it. Updated .