This document contains pre-bid Request for Information (RFI) questions and responses related to Solicitation 36C25224B0015 for the demolition of nine buildings at the Danville VA Medical Center (VAMC) under Project 550-24-202.
The key details are:
- The project involves the demolition of Buildings 31, 32, 33, 34, 37, 38, 75, 81, and 83 at the Danville VAMC.
- The RFI responses provide clarification on items such as asbestos and lead paint testing/removal, utility demolition, landscaping, and project site access.
- The contractor will be responsible for disposing of any stored items within the buildings after the VA removes them prior to the Notice to Proceed.
- The VA will provide a sales tax exemption certificate to the awarded contractor.
- The contractor will need to coordinate with the utility companies for the removal of gas and electric meters.
- Utilities are to be removed to their origin/service main for each building.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pre-Bid RFIs Danville VAMC 550-24-202 Demolish Buildings 31, 32, 33, 34, 37, 38, 75, 81, and 83
| Pre-Bid RFIs | 36C25224B0015 | |||
| No. | Date Submitted | SUBJECT/COMMENT | Response | Included in Amendment # |
| 1 | 9/3/24 | Will the original asbestos testing results for the referenced project could be provided? These results will be required to send to the state before any abatement takes place and it will help more accurately account for materials to be abated. | Appendix #1 in specifications includes Scope of Asbestos/Hazmat removal. | :001 |
| 2 | 9/5/24 | What is the intention for Lead Paint? Are we removing all lead painted components or just loose and failing paint (concentrated lead waste)? | See response to question below regarding lead paint. | :001 |
| 3 | 9/12/24 | What is the intent to remove electric, communication and control lines inside the construction area? Is that just to remove the cable? Or do you want the conduit removed as well? Please confirm if work work is only inside the construction boundaries. | Indicated existing utilities inside the construction area as shown in the drawings are to be removed. Conduit is to be removed as well. Demolition is to occur within the boundaries shown in the drawings. For further clarification see specification section 02 41 00. The cable tv line needs to be re-routed to the Green Homes per drawing page GI003 Utility Note 14, with minimal outage of cable tv feed. | :001 |
| 4 | 9/9/24 | Page 6 of Attachment+4_550-24-202_BD+Drawings-rev-Part+2+of+6.pdf, under Seeding Maintenance, it states "Fertilization turf areas annually." Is the contractor expected to fertilize the grass annually? if so, how many years? | Any disturbed areas shall be backfilled with suitable soil, graded, and seeded with Turf Type Tall Fescue grass seed. The use of Fiberglass Seed Blankets is prohibited. The area shall be maintained until grass is successfully established. Annual fertilization is not required. | :001 |
| 5 | 9/9/24 | Or is the contactor expected to fertilize the grass until it is established? | See response above. | :001 |
| 6 | 9/6/24 | Can you please provide/post the sign in sheet from the Project's site visit. | This will be provided winthin the RIF responses. | :001 |
| 7 | 9/10/24 | Is landscaping in the scope of work? | See previous response regarding landscaping. | :001 |
| 8 | 9/10/24 | Are the buildings clear of items or is removal required? | Stored items will be removed by the VA ahead of NTP. After NTP, any items within the buildings are to be disposed of by the contractor. | :001 |
| 9 | 9/11/24 | Solicitation; Sales Tax: Will a sales tax exemption certificate be provided to the awarded contractor for this project? | Yes Tax exemption is provided with the awarding of the project. | :001 |
| 10 | 9/11/24 | Demo Gas and Electric Meters: Is the utility company responsible for the gas and electrical meters? If so, can the contact information for the gas and electrical utility companies be provided? | Contractor will need to coordinate with Ameren for removal of gas and electric meters at each building. | :001 |
| 11 | 9/12/24 | Utility Demolition Plans: The Utility Demolition Plans show a wavy line for utilities to be removed. Is the intent to excavate and remove the conduits or pipe to the extent of the wavy line or can the utility be inactivated at the building it was serving and considered abandoned in place? | Utilities are to be removed according to notes on plans or to their origin (take off) of their respective service main for each building. | :001 |
| 12 | Is there anyway you can get a clarification on something for me? It calls out all plaster and wood that is painted to be removed because of lead paint. That seems like extreme overkill to me, but they have it in the specs. Can you please find out if they are expecting all of that to be removed prior to demo? Thanks guys. | From the Illinois EPA Analysis and Disposal (illinois.gov) - If demolition/construction debris containing LBP still adhered to the substrate is generated from a non-residential structure, the waste may be handled as general refuse. However, if the LBP is removed from the original substrate to which it was adhered, then the waste is a special waste. | :001 |