S05 - Pre-Bid RFIs 695-23-103 final.xlsx

XLSX spreadsheet 18 KB Posted

Attached to
Z1DA--Replace Bldg. 5 Roof 695-23-103 Federal contract opportunity
Solicitation number
36C25224B0008
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 12

About this file

This document contains a set of pre-bid Request for Information (RFIs) related to Solicitation #36C252-23-B-0031 for Project #695-23-103 to Replace Building 5 Roof at the Clement J. Zablocki VA Medical Center in Milwaukee, Wisconsin. The project aims to correct deficiencies in the existing roof, including missing shingles, deteriorated roof decking, improper flashing, and damaged membrane. The contractor will be required to remove and replace the roofing materials and the second-floor decking of the south porch. The project duration is anticipated to be 255 calendar days, with a pre-construction period of up to 90 days and a construction period of 120 days. The RFIs cover various aspects of the project, such as the availability of core samples and photos, the use of alternative bonding adhesives, access and staging constraints, the extent of deteriorated decking, hazardous materials, and tax exemptions. Responses to the RFIs are provided by the Architect/Engineer and the Facilities Manager.

View the file

Other files for this federal contract opportunity

Other files attached to Z1DA--Replace Bldg. 5 Roof 695-23-103, newest first.
File Type Posted
Amendement 2- RFI-6 695-23-103 VA Milwaukee B5 Roof - BID - Vol5 Appendices.pdf PDF
Amedment 2-RFI-1 695-23-103 Replace B5 Roof - RFI 01 response.pdf PDF
Amendment 2- RFI 6- Hazardous Material report.pdf PDF
36C25224B0008 0002.docx DOCX document
Site Visit 061224.pdf PDF
36C25224B0008 0001.docx DOCX document
S02 - 6b- 695-23-103 Drawings 1.pdf PDF
S02 - Wage Determination 3.14.24.pdf PDF
36C25224B0008.docx DOCX document
S02 - 6c- 695-23-103 Drawings 2.pdf PDF
S02 - 6a- 695-23-103 Specifications.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

695-23-103

Project # 695-23-103 Replace Building 5 Roof Solicitation # 36C252-23-B-0031
Pre-Bid RFIs
RFI #RFI FromDateQuestion/CommentResponse (AE Initial Response)Response Posted in Amendment #RESPONSIBILITYACTION ITEMS
1ONeill Contractors Inc.1/25/24Will photos and core samples be provided of the upper roof due to being unable to access the roof top during the preconstruction meeting?The core sample is not available. Photos are available and attached to this amendment.AE
2Systec LTD of Wisconsin Inc.1/31/21The specification calls for water based bonding adhesives to be used to bond the membrane, in areas of high humidity / near water the water based bonding adhesives take longer times to properly set up. This would be problematic when installing vertical flashings. Would either solvent based or lvoc bonding adhesives be acceptable at the vertical flashings?A substituion request will have to be made with the product that's intended to be used during the submittal process. If approved it will be allowed as long as the adhesive is comparable to the water based and all necessary precautions are used on installation.AE
3Van Ert Electric Company Inc.2/22/24There is ongoing construction on an adjacent building that impacts access around building #5 – will they have fencing / ground equipment still restricting access around the building when building #5 construction begins?It is estimated there will be fencing installed around that job site. It could change depending on the amount of progress made from now until construction begins. Coordination will occur between both contractors if work is taking place at the same time to ensure both project proceed without delays.FM
4Van Ert Electric Company Inc.2/22/24Will we need to maintain access to the road between the staging point and building #5 or will we be able to close off this street between buildings 3&4 if we were to maintain pedestrian access to the adjacent buildings?The road will need to remain open. It could be temporairly closed for a short duration of time, with proper authorization, for deliveries etc .FM
5Van Ert Electric Company Inc.2/22/24Is there a SF of the deck that is deteriorated and must be replaced?See Drawing Number A101, General Note 13, " THE EXTENT OF THE DAMAGE TO WOOD T&G ROOF DECKING IS NOT FULLY KNOWN, CONTRACTOR TO INCLUDE THE FOLLOWING QTY OF ITEMS FOR DEMO AND INSTALLATION: EIGHT HUNDRED (800) SQUARE FEET OF T&G ROOF DECKING REPLACEMENT (ABOVE AND BEYOND THAT SPECIFICALLY SHOWN/NOTED ON DRAWINGS)."AE
6Progressive Construction Services LLC2/16/24Is there a hazardous material survey available?Yes, Hazard Survey Results are available. It's in the Volume 5 Appendices, Appendix F and are attached as part of this amendment.AE
7Progressive Construction Services LLC2/19/24In our experience, some VA projects have tax exemptions for buying materials while others do not. Will you guys be providing the winning contractor a Wisconsin Sales Tax Exemption Certificate?The state of Wisconsin doesn’t allow for this exemption. While the federal government is under no obligation to abide by Wisconsin’s tax guidance, at this time it still does. If this project were in IL, we would provide the tax exemption form.GLAC
8Progressive Construction Services LLC2/19/24The quantity of deteriorated wood/decking won.t be completely understood until the deck and structural are completely exposed, should the contractors provide unit cost per board foot or square foot when submitting the bids?There is an 800 SF rotted deck allowance (RFI 5). This should permit us to determine a unit cost in the event that more than this SF quantity is required. VA contracting will determine if unit pricing is allowed to be sought.AE
9Armstrong elevator Company2/16/24Regarding the masonry section of the specification, was it included in this project manual due to the wood work and windows on this project? If so, should the contractor include a per linear ft. cost for brick replacement and tuck pointing?Masonry section is included for brick removal poecketing/patching for beams as detailed structurally. Tuckpointing is not in the scope of this project.AE
10Progressive Construction Services LLC2/15/24A101 Note 7 directs installation of New adhered TPO roof system over mechanically fastened ½” coverboard and 1” rigid insulation.
3.1 TPO roofing is not recommended by the manufacturer for this application. We recommend using a self-adhered SBS product that will closely match or compliment the shingles. (Or use shingles, the pitch is low but manufacturer will still warranty). Would self-adhered SBS or shingles be acceptable in-lieu of TPO roofing?Several products were considered during design. The choice, as ulitimatly determined by the VA, is a gray TPO membrane. The manufacture's rep we worked with helped guide the installation and detailing needed to achieve warrenty. For perspective, we are not only providing a weathertight roof but also replicating historical aspects of the building in a manner acceptable to SHPO. We aren't going back to shingles--bids should be based on drawings and specs.AE
11Progressive Construction Services LLC2/15/24What is the purpose for the 1” insulation and 1/2" coverboard? See A500 Detail 3. Can this be omitted?The cover board and insulation serve to provide an even base layer, substrate, and protection for the membrane roofing system. No, it cannot be omitted at this time.AE
12Progressive Construction Services LLC2/15/24Is Autodesk Construction Cloud an acceptable submittal management system if it meets all requirements in spec 01 33 23?VA will use OpCenter and will provide access to the awarded contactor. No other submital management system will be used.FM
13Progressive Construction Services LLC2/15/24
14Progressive Construction Services LLC2/15/24
15Progressive Construction Services LLC2/1/24
16Progressive Construction Services LLC2/15/24
17Progressive Construction Services LLC2/15/24
18Progressive Construction Services LLC2/15/24
19Progressive Construction Services LLC2/15/24
20Progressive Construction Services LLC2/15/24
21Progressive Construction Services LLC2/15/24
22Progressive Construction Services LLC2/15/24
23Progressive Construction Services LLC2/15/24
24Progressive Construction Services LLC2/15/24
25Progressive Construction Services LLC2/15/24
26Progressive Construction Services LLC2/15/24
27Progressive Construction Services LLC2/15/24
28Progressive Construction Services LLC2/15/24
29Progressive Construction Services LLC2/15/24
30Progressive Construction Services LLC2/15/24
31Progressive Construction Services LLC2/15/24
32Progressive Construction Services LLC2/15/24
33Progressive Construction Services LLC2/15/24
34Progressive Construction Services LLC15-Feb
35Progressive Construction Services LLC2/15/24
36Progressive Construction Services LLC2/15/24
37Progressive Construction Services LLC2/15/24
38Progressive Construction Services LLC2/15/24
39Progressive Construction Services LLC2/15/24
40Progressive Construction Services LLC2/15/24
41Progressive Construction Services LLC2/15/24
42Progressive Construction Services LLC2/15/24
43Progressive Construction Services LLC2/15/24
44Progressive Construction Services LLC2/15/24
45Progressive Construction Services LLC15-Feb
46Progressive Construction Services LLC2/15/24
47Progressive Construction Services LLC2/15/24
48Progressive Construction Services LLC2/15/24
49Progressive Construction Services LLC2/15/24
50Progressive Construction Services LLC2/15/24
51Progressive Construction Services LLC2/15/24
52Elevated Technologies Inc.2/15/24
53Elevated Technologies Inc.2/15/24
54Elevated Technologies Inc.2/15/24
55Elevated Technologies Inc.2/15/24
56Elevated Technologies Inc.2/15/24
57Elevated Technologies Inc.2/15/24
58Elevated Technologies Inc.2/15/24
59Elevated Technologies Inc.2/15/24
60Elevated Technologies Inc.2/15/24
61Elevated Technologies Inc.2/15/24
62Elevated Technologies Inc.2/15/24
63Elevated Technologies Inc.2/15/24
64Elevated Technologies Inc.2/15/24
65Elevated Technologies Inc.2/15/24
66Elevated Technologies Inc.2/15/24
67Elevated Technologies Inc.2/15/24
68Elevated Technologies Inc.2/15/24
69Elevated Technologies Inc.2/15/24
70Elevated Technologies Inc.2/15/24
71Elevated Technologies Inc.2/15/24
72Elevated Technologies Inc.2/15/24
73Elevated Technologies Inc.2/15/24
74Elevated Technologies Inc.2/15/24
75Elevated Technologies Inc.2/15/24
76Elevated Technologies Inc.2/15/24
77ONeill Contractors Inc.2/21/24
78ONeill Contractors Inc.2/21/24
79ONeill Contractors Inc.2/21/24
80ONeill Contractors Inc.2/21/24
81ONeill Contractors Inc.2/21/24
82ONeill Contractors Inc.2/21/24
83ONeill Contractors Inc.2/21/24
84ONeill Contractors Inc.2/21/24
85ONeill Contractors Inc.2/21/24
86ONeill Contractors Inc.2/21/24
87Progressive Construction Services LLC2/29/24
88Progressive Construction Services LLC2/29/24
89Progressive Construction Services LLC2/29/24
90Progressive Construction Services LLC2/29/24

&A &Z&F &D

File details come from the government source that posted it. Updated .