This document is an amendment to a federal solicitation for an EHRM installation of data drops and power outlets project at the Tomah VA Medical Center. The key details include:

  • The bid opening date was extended from May 25th to June 1st at 12:30 PM CST due to the COVID-19 pandemic. Masks are required.

  • Revised drawings and a list of end user devices to be installed were provided as attachments, along with a wage determination.

  • The contractor is responsible for moving equipment and using J-hooks to properly support cabling. MC cable is not allowed.

  • Standard work hours are detailed in the statement of work. Coordination is required for access to clinical areas on the 2nd-4th floors and buildings 411-412, which are also clinical areas.

  • Testing is required before entering clinical spaces. A utility outage request form must be submitted two weeks in advance for power panel access.

  • The solicitation number is 36C25222B0027 and is issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 12 for the Tomah VA Medical Center.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 676-22-2-6985-0027 676-21-702 36C252 Department of Veterans Affairs Great Lakes Acquisition Center (GLAC) 115 S 84th Street, Suite 101 Milwaukee

WI

53214-1476 36C252 Department of Veterans Affairs Great Lakes Acquisition Center (GLAC) 115 S 84th Street, Suite 101 Milwaukee

WI

53214-1476 To all Offerors/Bidders

36C25222B0027 05-23-2022

X X X

June 1, 2022 @ 12:30 PM X Project# 676-21-702 EHRM Installation of Data Drops and Power Outlets (DDPO)

A. BID Opening Date Change/Information B. Questions and Answers C. Attachments D. Forthcoming

See Continuation Page(s)

Contracting Officer

SOLICITATION: 36C25222B0027

AMENDMENT: 0001

May 23, 2022

Project: EHRM Installation of Data Drops and Power Outlets (DDPO) Project Number: 676-21-702 Location: Tomah VA Medical Center, Tomah, WI

Amendment 0001 hereby incorporates the following clarifications/change(s) into the solicitation package.

A: BID opening Date Change:

Date has been extended from Wednesday, May 25, 2022, to Wednesday, June 1, 2022.

*Wednesday June 1, 2022, at 12:30 PM (CST) Due to national COVID-19 pandemic masks are required.

B. Questions and Answers Received from Contractor on 5/6/2022

1. There are no electrical rooms shown on published drawings to show where to get power. Can you provide the locations from which we will get power for the outlet installation? We suggest that we use the panels located near each area of work; please confirm

VA REPLY: See revised drawings provided in this amendment.

2. On the site visit it was mentioned that there would be specific ICRA requirements in the CLC areas, but we do not see these areas clearly identified on the drawings. Can you confirm which locations have specific dust/containment requirements and what these requirements are?

VA REPLY: The Tomah VAMC operates all areas with the same listed ICRA level; no exemptions are made on campus. We are requesting that contractors be COVID tested every 72 hours while working in CLC spaces on campus. This testing is provided by the Tomah VA once registration is completed with employee health. The process usually takes less than 20 minutes to register.

3. What is the required shut-down process for installing power in panels and who must this be coordinated with?

VA REPLY: A utility outage sheet must be filled out and provided to the VA with coordination between engineering and Facility services. This request needs to be submitted two weeks prior to requested shutdown.

4. Who is responsible for moving equipment that is located in areas where new devices are to be installed?

VA REPLY: This is the contractor’s responsibility.

5. Will free air cabling be allowed? The ceilings appear to be very congested and conduit installation will be very difficult.

VA REPLY: J hooks for Category 6A needs to be used for cables to properly support cabling.

6. Will MC type cable be allowed?

VA REPLY: MC cable is NOT allowed.

7. Are there alternate drawings for Bldgs. 411 and 412 - the device locations on these drawings appear to be off - (ex., one of them shows data and power in a restroom) –

VA REPLY: See revised drawings provided in this amendment.

8. On the site visit it was noted that there are some ongoing construction/remodeling projects (blood lab and urgent care areas). Will the SOW incorporate the new data and power needs for these areas or is it excluded from this SOW?

VA REPLY: At this time, they will still be included due to timelines of spaces being worked on.

9. Please confirm the available working hours, any restricted areas, any areas needing advanced notice and coordination process for any limited access areas.

VA REPLY: Standard work hours are detailed in the SOW, area with restricted access are CLC spaces on campus which are focused in 2nd and 3rd floors in 400 buildings except 407 and 408. 411 and 412 are also CLC spaces. Most work can be completed during the day with coordination with nurse managers on floors. For CLC spaces ensure testing is completed before entering spaces.

10. Is there a published Wage Determination document associated with this solicitation?

VA REPLY: Davis-Bacon Act WD # WI20220011. See Amendment 0001 attachment.

11. Page 1 of SOW document refers to Attachment 1 and Attachment 2, but I do not find documents with this naming. Please advise, where can I locate a copy of Attachment 1 - List of Devices and Attachment 2 - locations (I presume that the drawing package may serve as Attachment 2) – Attachment 1 - has been added to the solicitation, and you are correct on attachment 2.

C. Attachments:

Att 1 - Wage Determination Att 2 - Updated Drawings Att 3 - List of End User Devices

D. Forthcoming

Site Visit – Sign in sheet

(End of Document)

See attached document: S06 - Att 1 - 676-21-702 - List of End User Devices for Installation.

See attached document: S06 - Att 2 - 676-21-702 5.23.22 - Updated Project Drawings.

See attached document: S06 - Att 3 - 676-21-702 - Wage Determination WI20220011 04.29.2022.