About this file

36C25218B1082 Specifications 695-18-109.pdf

View the file

Other files

File Type Posted
36C25219C0006-000.docx DOCX document
36C25218B1082-0003000.docx DOCX document
36C25218B1082-0003002.pdf PDF
36C25218B1082-0003001.pdf PDF
36C25218B1082-0003003.docx DOCX document
36C25218B1082-0002000.docx DOCX document
36C25218B1082-0001000.docx DOCX document
36C25218B1082-0001001.pdf PDF
36C25218B1082-003.pdf PDF
36C25218B1082-006.docx DOCX document
36C25218B1082-004.pdf PDF
36C25218B1082-005.pdf PDF
36C25218B1082-001.docx DOCX document
36C25218B1082-007.pdf PDF
36C25218B1082-000.docx DOCX document
Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Clement J. Zablocki VA Medical Center

Replace AHU Building 123 Kitchen

Project 695-18-109

Construction Documents

June 8, 2018

US Department of Veterans Affairs

Clement J. Zablocki VA Medical Center

5000 W. National Ave.

Milwaukee, WI 53295-0001

PROJECT MANUAL

SPECIFICATIONS

Prepared by:

Facility Management Division

Milwaukee VAMC Nov-2017

695-18-109 Replace AHU Building 123 Kitchen Construction Documents

Milwaukee, WI 53295 6/8/2018

00 01 10-1

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

DIVISION 00 - SPECIAL SECTIONS DATE

00 01 10 Table of Contents 11-17

00 01 15 List of Drawing Sheets 07-15

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 10-17

01 01 10 SN Special Notes 07-17

01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build) 04-13

01 33 23 Shop Drawings, Product Data, and Samples 05-17

01 35 26 Safety Requirements 02-17

01 57 19 Temporary Environmental Controls 08-17

01 74 19 Construction Waste Management 09-13

01 81 13 Sustainable Construction Requirements 10-17

01 91 00 General Commissioning Requirements 10-15

DIVISION 02 – EXISTING CONDITIONS

02 41 00 Demolition 08-17

02 42 00 Cutting, Removal, Demolition, Restoration and Patching 11-17

02 82 13.13 Glovebag Asbestos Abatement 09-15

DIVISION 05 – METALS

05 50 00 Metal Fabrications 07-14

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 08 00 Facility Exterior Closure Commissioning 11-16

07 21 13 Thermal Insulation 10-17

07 22 00 Roof and Deck Insulation 02-16

07 60 00 Flashing and Sheet Metal 07-14

07 84 00 Firestopping 02-16

07 92 00 Joint Sealants 10-17

DIVISION 09 – FINISHES

09 91 00 Painting 01-16

DIVISION 22 – PLUMBING

22 05 11 Common Work Results for Plumbing 07-16

22 05 33 Heat Tracing for Plumbing Piping 09-15

22 07 11 Plumbing Insulation 09-15

Milwaukee VAMC Nov-2017

00 01 10-2

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC 08-17

23 05 93 Testing, Adjusting, and Balancing for HVAC 02-15

23 07 11 HVAC and Boiler Plant Insulation 02-15

23 08 00 Commissioning of HVAC Systems 11-16

23 09 23 Direct-Digital Control System for HVAC 09-11

23 21 13 Hydronic Piping 08-17

23 31 00 HVAC Ducts and Casings 03-13

23 34 00 HVAC Fans 02-15

23 40 00 HVAC Air Cleaning Devices 02-12

23 74 13 Packaged, Outdoor, Central-Station Air-Handling Units 04-11

23 81 00 Decentralized Unitary HVAC Equipment 02-11

23 82 16 Air Coils 04-11

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 01-16

26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17

26 05 26 Grounding and Bonding for Electrical Systems 01-17

26 05 33 Raceway and Boxes for Electrical Systems 05-14

26 08 00 Commissioning of Electrical Systems 11-16

26 27 26 Wiring Devices 01-16

Milwaukee VAMC Jul-2015

Milwaukee, WI 53295 6/8/2018

00 01 15 - 1

SECTION 00 01 15

LIST OF DRAWINGS

The drawings listed below accompanying this specification form a part of the contract.

Drawing No. Title

GENERAL

G001 Cover Sheet

G002 General Notes

G003 Building 123 Statement of Conditions

G101 Phasing: Phases A and B

G102 Phasing: Phase C

MECHANICAL

M001 Mechanical Symbols & Abbreviations

MH101 Mechanical HVAC Demo

MH102 Mechanical HVAC Existing

MH103 Mechanical HVAC New Work

MP101 Mechanical Piping Demo

MP102 Mechanical Piping New Work

MI101 Mechanical Controls

M501 Mechanical Schedules

M601 Mechanical Details

ELECTRICAL

E001 Electrical Symbols & Abbreviations

EP101 Electrical Demo And New Work

E500 Electrical Panel Schedules

- - - E N D - - -

Milwaukee VAMC OCT 2017

01 00 00 -1

SECTION 01 00 00

GENERAL REQUIREMENTS

1.1 SAFETY REQUIREMENTS

A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.

1.2 GENERAL INTENTION

A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work as required by drawings and specifications.

B. Visits to the site by Bidders may be made only as described in the solicitation in accordance with FAR 52.236-27 Site Visit.

C. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

D. Routine inspections and maintenance during construction

a. Provide routine inspections and maintenance services as prescribed in Operations & Maintenance manuals required under this contract.

b. Provide services during construction and until items below are completed:

i. VA Inspection complete.

ii. Successful commissioning

iii. Training of VA Maintenance staff

iv. Acceptance by VA of each system described in other specifications related to this contract.

v. O&M Manual submittals received, reviewed, and approved by VA.

c. Systems included in this contract are:

iv. HVAC

v. Steam

vi. Electrical

E. Submit with O&M manuals: one spreadsheet based comprehensive summary schedule of routine inspection and maintenance for systems. List:

specification section, article, and paragraph; description of systems/subsystems; O&M Manual reference; frequency.

1.3 STATEMENT OF BID ITEM(S)- NOT USED

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. All drawings and specifications (contract documents) may be obtained from the FedBizOps website where the solicitation is posted. Hard copies will be the responsibility and expense of the contractor(s).

1.5 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

01 00 00 -2

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.

2. A Special Agreement SAC form is required for every contract employee. See the SPECIAL NOTES section specification for an example of this SAC form. This needs to be supplied to the COR for every contract employee on the job site. Even if the contractor has an active badge, a SAC form is needed for the COR’s records.

3. Refer to specification section 01 01 10 SN Special Notes for fingerprint, badging, construction door access and parking requirements. Permits shall be issued for General Contractor and its employees for parking in designated areas only.

4. No photography of VA premises is allowed without written permission of the Contracting Officer.

5. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.

C. Document Control:

1. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.

2. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting

Officer.

3. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.

4. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.

D. Motor Vehicle Restrictions

1. Refer to section 01 01 10 SN.

1.6 OPERATIONS AND STORAGE AREAS

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the

Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the

01 00 00 -3

Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the

Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting

Officer, the buildings and utilities may be abandoned and need not be removed.

C. The Contractor shall, under regulations prescribed by the Contracting

Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting

Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The

Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

(FAR 52.236-10)

D. Working space and space available for storing materials shall be as determined by the COR.

F. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by the COR where required by limited working space.

1. Do not store materials and equipment in other than assigned areas.

2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of

Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.

3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.

G. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR. All such actions shall be coordinated with the COR or Utility Company involved:

1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.

H. Phasing:

01 00 00 -4

The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur.

It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:

To insure such executions, Contractor shall furnish the COR with a schedule of approximate dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR three weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such dates to insure accomplishment of this work in successive phases mutually agreeable to

COR and Contractor, as follows:

Phase A: Staging and access

Phase B: Demolition of existing unit

Phase C: Replacement with new unit

I. Building No. 123 will be occupied during performance of work but immediate areas of alterations will be vacated for scheduled off-hours work.

1. Certain areas of Building No. 123 will be occupied by Medical Center personnel for various periods as listed below:

AREA PERIOD

(a)123 Kitchen 6:00am – 7:30pm (7 days a week)

(b)E Wing (non-kitchen) 24 hours, 7 days a week

Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of

Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc to facilitate patient and staff access.

Coordinate alteration work in areas occupied by Department of

Veterans Affairs so that Medical Center operations will continue during the construction period.

J. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:

1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.

01 00 00 -5

2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from

Contractor's employee or watchman.

K. Utilities Services: Maintain existing utility services for Medical

Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.

Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.

1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.

When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS for additional requirements.

2. Contractor shall submit a request to interrupt any such services to

COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.

3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.

4. Major interruptions of any system must be requested, in writing, at least 121 calendar days prior to the desired time and shall be performed as directed by the COR.

5. In case of a contract construction emergency, service will be interrupted on approval of the COR. Such approval will be confirmed in writing as soon as practical.

6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.

L. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.

01 00 00 -6

M. To minimize interference of construction activities with flow of

Medical Center traffic, comply with the following:

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.

2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.

N. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.

1.7 ALTERATIONS

A. Survey: Before any work is started, the Contractor shall make a thorough photographic survey with the COR, of work sites.

B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government.

Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR

52.243-4 and VAAR 852.236-88).

C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved.

1. Re-survey report shall list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of

Contractor to restore damage caused by Contractor's workmen in executing work of this contract.

D. Protection: Provide the following protective measures:

1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.

2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.

3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.

1.8 DISPOSAL AND RETENTION

A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

01 00 00 -7

1. Reserved items which are to remain property of the Government are noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by the COR.

2. Items not reserved shall become property of the Contractor and be removed by Contractor from the Medical Center.

3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.

1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND

IMPROVEMENTS

A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.

B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the

Contractor fails or refuses to repair the damage promptly, the

Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

(FAR 52.236-9)

C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and

"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.

1.10 RESTORATION

A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the

COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall

01 00 00 -8 conform in type and quality to that of original existing construction, except as otherwise shown or specified.

B. Upon completion of contract, deliver work complete and undamaged.

Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.

D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"

(FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR

52.236-2).

1.11 PHYSICAL DATA [NOT USED]

1.12 PROFESSIONAL SURVEYING SERVICES [NOT USED]

1.13 LAYOUT OF WORK [NOT USED]

1.14 AS-BUILT DRAWINGS

A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.

B. All variations shall be shown in the same general detail as used in the contract drawings. To insure compliance, as-built drawings shall be made available for the COR’s review as often as requested.

C. Contractor shall submit a completed set of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.

D. Paragraphs A, B, & C shall also apply to all shop drawings.

E. Contractors shall update (as work is completed) the VA electrical, medical gas, domestic plumbing and mechanical piping master schematic books. These books are located in the FM office.

1.15 USE OF ROADWAYS

A. For hauling, use only established public roads and roads on Medical

Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.

01 00 00 -9

1.16 RESIDENT ENGINEER'S FIELD OFFICE [NOT USED]

1.17 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT

A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:

1. Permission to use each unit or system must be given by the COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the

COR will withdraw permission for use of the equipment.

2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted.

Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National Electrical Code, (2014

Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.

3. Units shall be properly lubricated, balanced, and aligned.

Vibrations must be eliminated.

4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.

5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.

6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the Government.

B. Prior to final inspection, the new equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the Government.

C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.

D. Any damage to the equipment or excessive wear due to prolonged use will be repaired replaced by the contractor at the contractor’s expense.

01 00 00 -10

1.18 TEMPORARY USE OF EXISTING ELEVATORS [NOT USED]

1.19 TEMPORARY USE OF NEW ELEVATORS [NOT USED]

1.20 TEMPORARY TOILETS [NOT USED]

1.21 AVAILABILITY AND USE OF UTILITY SERVICES

A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to the Government. The Contractor shall carefully conserve any utilities furnished without charge.

B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia and repair restore the infrastructure as required.

C. Contractor shall install meters at Contractor's expense and furnish the

Medical Center a monthly record of the Contractor's usage of electricity as hereinafter specified.

D. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted.

E. Electricity (for Construction and Testing): Furnish all temporary electric services.

1. Obtain electricity by connecting to the Medical Center electrical distribution system. The Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat. Electricity for all other uses is available at no cost to the Contractor.

F. Water (for Construction and Testing): Furnish temporary water service.

1. Obtain water by connecting to the Medical Center water distribution system. Provide reduced pressure backflow preventer at each connection as per code. Water is available at no cost to the

Contractor.

2. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes will be cause for revocation (at COR’s discretion) of use of water from Medical Center's system.

G. Fuel: Natural and LP gas and burner fuel oil required for boiler cleaning, normal initial boiler-burner setup and adjusting, and for performing the specified boiler tests will be furnished by the

Government. Fuel required for prolonged boiler-burner setup, adjustments, or modifications due to improper design or operation of

01 00 00 -11 boiler, burner, or control devices shall be furnished and paid by the

Contractor at Contractor's expense.

1.22 NEW TELEPHONE EQUIPMENT [NOT USED]

1.23 TESTS

A. As per specification section 23 05 93 the contractor shall provide a written testing and commissioning plan complete with component level, equipment level, sub-system level and system level breakdowns. The plan will provide a schedule and a written sequence of what will be tested, how and what the expected outcome will be. This document will be submitted for approval prior to commencing work. The contractor shall document the results of the approved plan and submit for approval with the as built documentation.

B. Pre-test mechanical and electrical equipment and systems and make corrections required for proper operation of such systems before requesting final tests. Final test will not be conducted unless pre-tested.

C. Conduct final tests required in various sections of specifications in presence of an authorized representative of the Contracting Officer.

Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.

D. Mechanical and electrical systems shall be balanced, controlled and coordinated. A system is defined as the entire system which must be coordinated to work together during normal operation to produce results for which the system is designed. For example, air conditioning supply air is only one part of entire system which provides comfort conditions for a building. Other related components are return air, exhaust air, steam, chilled water, refrigerant, hot water, controls and electricity, etc.

E. All related components as defined above shall be functioning when any system component is tested. Tests shall be completed within a reasonably period of time during which operating and environmental conditions remain reasonably constant and are typical of the design conditions.

F. Individual test result of any component, where required, will only be accepted when submitted with the test results of related components and of the entire system.

1.24 INSTRUCTIONS

A. Contractor shall furnish Maintenance and Operating manuals (hard copies and electronic) and verbal instructions when required by the various sections of the specifications and as hereinafter specified.

B. Manuals: Maintenance and operating manuals and one compact disc (four hard copies and one electronic copy each) for each separate piece of equipment shall be delivered to the COR coincidental with the delivery of the equipment to the job site. Manuals shall be complete, detailed guides for the maintenance and operation of equipment. They shall include complete information necessary for starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub-assembly components. Manuals shall include an index covering all component parts clearly cross-referenced to diagrams and illustrations. Illustrations

01 00 00 -12 shall include "exploded" views showing and identifying each separate item. Emphasis shall be placed on the use of special tools and instruments. The function of each piece of equipment, component, accessory and control shall be clearly and thoroughly explained. All necessary precautions for the operation of the equipment and the reason for each precaution shall be clearly set forth. Manuals must reference the exact model, style and size of the piece of equipment and system being furnished. Manuals referencing equipment similar to but of a different model, style, and size than that furnished will not be accepted.

C. Instructions: Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed training to assigned

Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site. These requirements are more specifically detailed in the various technical sections. Instructions for different items of equipment that are component parts of a complete system, shall be given in an integrated, progressive manner. All instructors for every piece of component equipment in a system shall be available until instructions for all items included in the system have been completed.

This is to assure proper instruction in the operation of inter-related systems. All instruction periods shall be at such times as scheduled by the COR and shall be considered concluded only when the COR is satisfied in regard to complete and thorough coverage. The contractor shall submit a course outline with associated material to the COR for review and approval prior to scheduling training to ensure the subject matter covers the expectations of the VA and the contractual requirements. The Department of Veterans Affairs reserves the right to request the removal of, and substitution for, any instructor who, in the opinion of the COR, does not demonstrate sufficient qualifications in accordance with requirements for instructors above.

1.25 GOVERNMENT-FURNISHED PROPERTY [NOT USED]

1.26 RELOCATED EQUIPMENT [NOT USED]

1.27 STORAGE SPACE FOR DEPARTMENT OF VETERANS AFFAIRS EQUIPMENT [NOT USED]

1.28 CONSTRUCTION SIGN [NOT USED]

1.29 SAFETY SIGN

A. When work blocks doors or exits, or changes egress paths, the general contractor is to provide all temporary signage to re-route personnel and block the doors or exits. Locations to be determined based on the

ILSM.

1.30 PHOTOGRAPHIC DOCUMENTATION

A. During the construction period through completion, provide photographic documentation of construction progress and at selected milestones including electronic indexing, navigation, storage and remote access to the documentation, as per these specifications.

B. Photographic documentation elements:

1. Each digital image shall be taken with a camera with minimum size of

6 megapixels (MP) capable of producing 200x250mm (8 x 10 inch)

01 00 00 -13 prints with a minimum of 2272 x 1704 pixels and 400x500mm (16 x 20 inch) prints with a minimum 2592 x 1944 pixels.

2. Indexing and navigation system shall utilize actual AUTOCAD construction drawings, making such drawings interactive on an on-line interface. For all documentation referenced herein, indexing and navigation must be organized by both time (date-stamped) and location throughout the project.

3. Documentation shall combine indexing and navigation system with inspection-grade digital photography designed to capture actual conditions throughout construction and at critical milestones.

Documentation shall be accessible on-line through use of an internet connection. Documentation shall allow for secure multiple-user access, simultaneously, on-line.

4. Before construction, existing equipment and work site shall be documented.

7. As-built conditions of mechanical, electrical, plumbing and all other systems shall be documented post-inspection and pre-insulation, sheet rock or dry wall installation. This process shall include all finished systems located in the walls and ceilings of all buildings at the Project. Overlapping photographic techniques shall be used to insure maximum coverage.

8. As-built conditions of exterior skin shall be documented with an increased concentration of digital photographs as directed by the

COR in order to capture pre-determined focal points, such as waterproofing, architectural or Exterior Insulation and Finish

Systems (EIFS) detailing. Overlapping photographic techniques shall be used to insure maximum coverage.

10. Miscellaneous events that occur during any Contractor site visit, or events captured by the Department of Veterans Affairs independently, shall be dated, labeled and stored in the same “place” as the formal scope.

11. Customizable project-specific digital photographic documentation of other details or milestones. Indexing and navigation accomplished through interactive architectural plans.

1.31 FINAL ELEVATION DIGITAL IMAGES [NOT USED]

1.32 HISTORIC PRESERVATION

A. Where the Contractor or any of the Contractor's employees, prior to, or during the construction work, are advised of or discover any possible archeological, historical and/or cultural resources, the Contractor shall immediately notify the COR verbally, and then with a written follow up.

1.33 CONSTRUCTION COORDINATION DRAWINGS

A. Prepare and provide coordination drawings showing the location of openings through slabs, the pipe sleeves and hanger inserts, as well as the location and elevation of utility lines, including, but not limited to, conveyor systems, pneumatic tubes, ducts, all existing utilities, and conduits and pipes 50 mm (2 inches) and larger in diameter.

B. Drawings required for all areas being remodeled or new and ancillary areas required by such utility runs. Ancillary area drawings to

01 00 00 -14 include equal space on each side of main runs from main source to final location. These drawings, including plans, elevations, and sections as appropriate shall clearly show the manner in which the utilities fit into the available space and how they relate to each other and to existing building elements and controls for maintenance operations.

C. Drawings shall be of appropriate scale to satisfy the previously stated purposes, but not smaller than 9 mm (3/8 inch) scale. Drawings must be composite (with distinctive colors for the various trades) including but not limited to HVAC equipment, HVAC ductwork, mechanical piping, plumbing, fire protection, electrical, medical gases, telecommunications, etc..

D. The submitted drawings for a given area of the project shall show the work of all trades which will be involved in that particular area. A complete composite drawing set or complete sets of separate reproducible drawings and AutoCAD files shall be received by the

Government not less than 20 days prior to the scheduled start of the work in the area illustrated by the drawings, for the purpose of showing the contractor's planned method of installation. The objectives of such drawings are to promote carefully planned work sequence and proper trade coordination, in order to assure the expeditious solutions of problems and the installation of lines and equipment as contemplated by the contract documents while avoiding or minimizing additional costs to the contractor and to the Government.

E. In the event the contractor, in coordinating the various installations and in planning the method of installation, finds a conflict in location or elevation of any of the utilities with themselves, with structural items or with other construction items, the contractor shall bring this conflict to the attention of the contracting officer immediately. In doing so, the contractor shall explain the proposed method of solving the problem or shall request instructions as to how to proceed if adjustments beyond those of usual trades coordination are necessary.

1. Contractor to include initial and two revisions as part of original contract.

2. Utilities installation work will not proceed in any area prior to the submission and completion of the Government review of the coordinated drawings for that area, nor in any area in which conflicts are disclosed by the coordination drawings until the conflicts have been corrected to the satisfaction of the contracting officer.

F. It is the responsibility of the contractor to submit the required drawings in a timely manner consistent with the requirements to complete the work covered by this contract within the prescribed contract time.

- - - E N D - - -

Milwaukee VAMC 3/14/2018

01 01 10SN - 1

SECTION 01 01 10 (SN)

SPECIAL NOTES

PART 1 - GENERAL

1.1 DESCRIPTION

This section specifies special requirements, processes, procedures, protocols, practices, prohibitions, protections, personnel matters, provisions for unique characteristics of the Milwaukee VAMC, and practical matters pertinent to construction.

1.2 RELATED WORK

A. Section 01 35 26 SAFETY REQUIREMENTS.

B. Section 01 00 00 GENERAL REQUIREMENTS.

C. Section 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS.

D. Section 01 74 19 CONSTRUCTION WASTE MANAGEMENT.

PART 2 - PRODUCTS (NOT USED)

PART 3 – EXECUTION

3.1 ANTE-ROOM CONSTRUCTION PRACTICES

A. Coordinate construction of the ante-room with NFPA 241 and the

Specification Section 01 35 26 SAFETY REQUIREMENTS.

B. Type “A” and “B” activities are those in which the fire/smoke hazard risks are MINIMAL. Type “C” and “D” activities are those in which the fire/smoke hazard risks are HIGH. The General

Contractor is obligated to consider the specified containment measures with the costs included within the various contract items of work. Refer to the Appendix for the Construction

Barrier and Fire Risk Assessment Matrix of Precautions for more information.

C. Type A (Minimal Fire Risk Activity/Construction): Provide authority to proceed with work in area, includes a ceiling permit as required, when working above ceilings.

D. Type B (Limited Fire Risk Activity/Construction):

1. Coordinate temporary construction partition installation with Specification Section 01 35 26 SAFETY REQUIREMENTS.

2. Provide plastic from floor to ceiling above and seal joints and penetrations. All plastic will be labeled with the VA

ILSM TEMPORARY BARRIER orange tag once installed indicating the start of the three days. At openings, install z-wall overlapping plastic flap barriers or equivalent.

E. Type C (Moderate Fire Risk Activity/Construction): Coordinate temporary construction partition installation with Specification

Section 01 35 26 SAFETY REQUIREMENTS.

01 01 10SN - 2

1. Ante-room construction (as part of 1-hour construction barrier):

a. Ante-room shall be a 1-hour fire-rated smoke-tight temporary construction partition and shall be full height, extending through suspended ceilings to the floor slab or roof deck above.

b. Ante-room shall be constructed from one-hour fire-rated

5/8-in type “X” gypsum board both sides of metal stud wall, mudded and taped in accordance with ASTM C840. “Double” gypsum board installation on one side (exterior) of the ante-room is authorized to achieve the 1-hour fire-rated smoke-tight temporary construction partition requirement with prior COR approval.

c. In this case, the ante-room 1-hour fire-rated smoke-tight temporary construction partition walls will also function as an infection control barrier. Contractor shall add appropriate infection control measures. Refer to 01 35 26

SAFETY REQUIREMENTS for more information.

d. Ante-room gypsum board walls shall be taped to the existing floors utilizing 2-in wide glass foil tape: 7.3 mil aluminum foil laminated glass cloth silver tape with silicone adhesive backing. Where the ante-room walls meet the existing deck or a 1-hour rated existing wall, the seams shall be firecaulked.

e. The ante-room must also have a dedicated heat detector installed. See paragraph below for heat detector requirements.

f. Ante-room outer construction door opening requires a Class

C, 45-minute fire rated door with self-closing and self-latching devices.

g. Ante-room inner door must at least be plastic Z-Type door.

2. Ante-room construction (for infection control purposes only):

a. Ante-room need not be a 1-hour fire-rated smoke-tight temporary construction partition. Its walls do not need to go to the concrete deck above, nor is a hard ceiling required. At a minimum, the contractor must tape the top of the ante-room walls to the underside of the existing acoustical tile ceiling to achieve the smoke tight and infection control requirements.

b. Ante-room shall be constructed from one-hour fire-rated

5/8-in type “X” gypsum board one side of metal stud wall, mudded and taped in accordance with ASTM C840.

01 01 10SN - 3

c. Contractor shall add appropriate infection control measures. Refer to 01 35 26 SAFETY REQUIREMENTS for more information.

d. Ante-room gypsum board walls shall be taped to the existing floors, walls or ceilings utilizing 2-in wide glass foil tape: 7.3 mil aluminum foil laminated glass cloth silver tape with silicone adhesive backing. Where the ante-room walls meet the existing deck or a 1-hour rated existing wall, the seams shall be firecaulked.

e. The ante-room does not require a dedicated heat detector.

f. Ante-room outer construction door opening requires a Class

C, 45-minute fire rated door with self-closing and self-latching devices.

g. Ante-room inner construction door opening requires a Class

C, 45-minute fire rated door with self-closing and self-latching devices.

3. Provide heat detectors and notification devices (i.e., audio-visual devices) tied into the Building Siemens Pyrotronics

System at the rate of one (1) detector per 1000 square foot of clear construction area. Heat detectors to be FTP-11

Addressable, Tri-Color LED, 135°F, Combination Fixed or Rate of Rise. The Contractor shall provide certification documentation once the heat detectors and notification devices

(i.e., audio-visual devices) are installed and/or moved and tested prior to any construction work taking place in the space. Inside the construction space, existing units can be used if they are moved to the floor deck above.

4. Other than ante-room, all other temporary construction partitions shall be full height, extending through suspended ceilings to the floor slab or roof deck above and shall be one-hour fire rated 5/8-in type “X” gypsum board both sides of metal stud wall, mudded and taped in accordance with ASTM

C840. If sprinklers are installed per a hydraulically calculated stamped and certified system and sprinklers are operational on both sides of the temporary partition and ceilings are fully intact and complete, then the partition indicated above may be permitted to terminate at the ceiling in accordance with NFPA 241.

5. Coordinate with Section 01 01 10-SN Section 3.35 for Card

Reader and Physical Access Control System (PACS) requirements at ante-room outer construction door.

D. Type D (Significant Fire Risk Activity/Construction):

1. All requirements for Type C construction activities above are required for Type D construction activities.

01 01 10SN - 4

2. When required by the project, install one-hour fire-rated temporary construction partitions to maintain integrity of existing exit stair enclosures, exit passageways, fire-rated enclosures of hazardous areas, horizontal exits, smoke barriers, vertical shafts and openings and other enclosures as required by the current Life Safety Code NFPA

101. This may include new horizontal egress tunnels, exit stairs, etc. Coordinate these activities with the COR.

3.2 ASBESTOS-CONTAINING MATERIALS (ACM)

A. There are both friable and non-friable asbestos-containing materials (ACM) located within hospital complex. Inspection reports are available from Facilities Management.

B. ACM might be unforeseen and potentially discovered during work.

Do not disturb ACM. Refer to Specifications Section 01 00 00 for procedures addressing discovery of ACM.

C. See Specification Sections 02 82 11 or 02 82 13 (series) for

Traditional or Glovebag Asbestos Abatement details.

D. New work: no ACM allowed in new products.

E. Contractor to provide asbestos costs separately in invoices.

3.3 BADGES

A. All contractors working at Milwaukee VAMC shall be fingerprinted…