36C25218B1082-0003000.docx
DOCX document 36 KB Posted
- Solicitation number
- 36C25218B1082
About this file
36C25218B1082 0003 36C25218B1082 0003.docx
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25219C0006-000.docx | DOCX document | |
| 36C25218B1082-0003002.pdf | ||
| 36C25218B1082-0003001.pdf | ||
| 36C25218B1082-0003003.docx | DOCX document | |
| 36C25218B1082-0002000.docx | DOCX document | |
| 36C25218B1082-0001000.docx | DOCX document | |
| 36C25218B1082-0001001.pdf | ||
| 36C25218B1082-002.pdf | ||
| 36C25218B1082-003.pdf | ||
| 36C25218B1082-006.docx | DOCX document | |
| 36C25218B1082-004.pdf | ||
| 36C25218B1082-005.pdf | ||
| 36C25218B1082-001.docx | DOCX document | |
| 36C25218B1082-007.pdf | ||
| 36C25218B1082-000.docx | DOCX document |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2.
AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE
OF PAGES
10A. MODIFICATION OF
CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV.
11/2016) is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITE M 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR
43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes r eference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
BY
Contractor
16C. DATE SIGNED
14.
DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME
AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS
OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 09-04-2018 695-18-4-6988-0008 695-18-109 36C252 Department of Veterans Affairs Great Lakes Acquisition Center (GLAC) 115 S 84th Street, Suite 101 Milwaukee WI 53214-1476 36C252 Department of Veterans Affairs Great Lakes Acquisition Center (GLAC) 115 S 84th Street, Suite Milwaukee WI 53214-1476 To all Offerors/Bidders
36C25218B1082 07-25-2018
X X X See continuation page for RFI responses and changes to specificaitons, drawings, and brand name or equal products.
Continue to monitor FBO.GOV for any and all changes to this solicitatio n.
Jerrod Schleis Contracting Officer Amendment of Solicitation Amendment 0003 Solicitation 36C252-18-B-1082 Replace AHU Building 123 Kitchen Project 695-18-109 Clement J. Zablocki VAMC, Milwaukee, WI
This Amendment consists of specification and drawing changes identified in the below narrative, responses to requests for information, and a revised brand name or equal products attachment.
The following changes are hereby provided by amendment:
SPECIFICATIONS:
1. Specification Section 00 01 10 Table of Contents
a. ADD Specification 26 41 00 Facility Lightning Protection
b. REMOVE Specification 22 05 33 Heat Tracing for Plumbing Piping
2. Specification 07 22 00 Roof Deck Insulation
a. REMOVE Section 2.5 Paragraph D.1
b. ADD “Glass-Mat, Water-Resistant Gypsum Roof Board: ASTM C1177/C1177M, Type X, 16 mm (5/8 inch) thick, factory primed.” as Section 2.5 Paragraph E.2
3. Specification 22 05 33 Heat Tracing for Plumbing Piping
a. REMOVE this Specification in its entirety
4. Specification 23 74 13 Packaged, Outdoor, Central-Station Air-Handling Units
a. REMOVE Section 1.4 Paragraph D
b. MODIFY Section 1.4 Paragraph F.3 to read “If shipping splits are provided, protect the unit and provide all necessary hardware (e.g. bolts, gaskets etc.) to assemble unit on site (see section 2.1. A4).
c. MODIFY Section 2.1 Paragraph A.3 to read “RTUs shall be fully assembled by the manufacturer in the factory in accordance with the arrangement shown on the drawings. The unit shall be assembled into the largest sections possible subject to shipping and rigging restrictions. The correct fit of all components and casing sections shall be verified in the factory for all units prior to shipment. All units shall be fully assembled and then split to accommodate shipment and job site rigging. On units not shipped fully assembled, the manufacturer shall tag each section and include air flow direction to facilitate assembly at the job site. Lifting lugs or shipping skids shall be provided for each section to allow for field rigging and final placement of unit.”
d. MODIFY Section 2.1 Paragraph A.4 to read “The RTU manufacturer shall provide the necessary gasketing, caulking, and all screws, nuts, and bolts required for assembly”
e. REMOVE Section 2.1 Paragraph A.7
f. MODIFY Section 2.1 Paragraph B title to read “Structural Steel Base Rail”
g. MODIFY Section 2.1 Paragraph C.5 to read “The thickness of insulation and mode of application shall be such that there is no visible condensation on the exterior panels of the AHU.”
h. MODIFY Section 2.1 Paragraph G.2 to read “Fan drive and belts shall be factory mounted with final alignment and belt adjustment to be made by the Contractor after installation. Drive and belts shall be as specified in Section 23 05 11, COMMON WORK RESULTS FOR HVAC AND STEAM GENERATION. Provide alternate sheaves or belts if required during balancing, to achieve desired airflow.”
i. MODIFY Section 2.1 Paragraph H.3 to read “The plenum fan shall be driven by a variable speed drive.”
j. REMOVE Section 2.1 Paragraph H.5.a
k. REMOVE Section 2.1 Paragraph I
l. REMOVE Section 2.1 Paragraph K
m. MODIFY Section 2.1 Paragraph L.2 to read “Integral Face and Bypass Coils: Provide integral vertical face and bypass dampers as required. Electric damper operators shall be furnished and mounted by the RTU manufacturer at the factory. Damper operators shall be of same manufacturer as controls furnished under Section 23 09 23, DIRECT-DIGITAL CONTROL SYSTEM FOR HVAC.”
n. REMOVE Section 2.1 Paragraph M
o. MODIFY Section 2.1 Paragraph N to read “Discharge Section: Provide aerodynamically designed framed discharge openings to minimize pressure loss.”
p. MODIFY Section 2.1 Paragraph O.1 to read “Vapor-proof marine lights using cast aluminum base style with glass globe and cast aluminum guard shall be installed in access sections for fan, mixing box, and any section over 300mm (12 inch) wide. A switch shall control the lights in each compartment with pilot light mounted outside the respective compartment access door. Wiring between switches and lights shall be factory installed.”
q. MODIFY Section 3.2 Paragraph C to read “An authorized factory representative should provide support for unit start up.”
5. Specification 23 82 16 Air Coils
a. REMOVE Section 2.1 Paragraph C
b. MODIFY Section 2.1 Paragraph E to read “Fins: 0.1397 mm (0.0055 inch) aluminum mechanically bonded or soldered or helically wound around tubing.”
c. MODIFY Section 2.1 Paragraph O to read “Dampers: Interlocking opposed blades to completely isolate coil from air flow when unit is in bypass position; 1.6 mm (l6 gage) steel, coated with factory applied corrosion resistant baked enamel finish. Provide damper linkage and electric operators.”
6. Specification 26 41 00 Facility Lightning Protection
a. ADD this specification section
DRAWINGS (attached):
1. Sheet MP-101: MODIFY Key Note 6 to read “BRANCH SHUTOFF VALVE LOCATIONS TO BE VERIFIED BY CONTRACTOR BEFORE START OF WORK.”
2. Sheet MP-102: MODIFY Key Note 1 to read “ROUTE NEW MECHANICAL PIPING FROM UNIT TO EXISTING PIPES ABOVE ROOF. VERIFY EXISTING PIPE TYPES AND LOCATIONS. REFER TO SPECIFICATION 09 91 00 FOR PIPE IDENTIFICATION STANDARDS.” ADD Key Note 5 to drawing. MODIFY Key Note 5 to read “PIPE CHASE TO BE ENCASED AT ROOF PENETRATION, SEE 12/M-601” and Key Note 6 to read “INTAKE HOOD WITH STAINLESS STEEL BIRD SCREEN TO OVERHANG PARAPET WALL. INTAKE HOOD TO BE FIELD FABRICATED BY CONTRACTOR”. REMOVE “CHR” and “CHS” labels on the DX piping.
3. Sheet MI-101: MODIFY Sequence Note J to read “J: SPACE TEMP CONTROL - UNIT TO MAINTAIN SPACE TEMPERATURE OF 68°F (ADJ) BASED ON ZONE TEMPERATURE SENSOR.”
4. Sheet M-501: REMOVE modulating valve on DX cooling coil and “CHR” and “CHS” labels. MODIFY outside air dampers to show parallel blade type instead of opposed blade type. REMOVE diffuser plate after supply fan. ADD Face and bypass dampers of parallel blade type before preheat coil. MODIFY existing modulating 3-way valves to new modulating 2-way valves on HWR and HWGR lines. MODIFY Note 3 to read “FURNISH UNIT WITH VARIABLE FREQUENCY DRIVE WITH FUSED DISCONNECT”. MODIFY pre-filter to be MERV 8 rating. MODIFY schedule remarks to read “Filters - MERV-8 and MERV-11 box filters
5. Sheet M-601: ADD Detail 13. MODIFY Detail 8 Note 5 to read “DUCT SUPPORTS TO BE ADDED TO INTAKE DUCT AT EVERY 8 FEET” MODIFY Detail 8 Note 6 to read “INTAKE HOOD WITH STAINLESS STEEL BIRD SCREEN TO BE FIELD FABRICATED BY CONTRACTOR”
BRAND NAME OR EQUAL PRODUCTS:
1. REMOVE Variable Frequency Drive from the Brand Name or Equal Products list.
REQUEST FOR INFORMATION RESPONSES
The following questions and answers provide clarification on the contract documents:
Q1. General Note 3 on Sheet MP-101 indicates asbestos testing will be performed by VA and removal will be done by contractor. How much pipe insulation abatement should be included in bid? Will abatement need to be done off-hours?
Response: Refer to Specification Section 02 82 13.13 part 1.1.2.B for ACM pipe insulation estimate of 40 linear feet of <2” diameter pipe. Replace insulation according to the specifications. Per Sheet MP-101 General Note 1, abatement must be done between 8:00pm and 4:00am if the location of work is in the vicinity of kitchen or linen equipment, supplies, or areas.
Q2. Key Note 5 on Sheet MP-102 indicates Pipe Chase to Be Encased. However, key note is not marked on the plan and the detail referenced on Sheet M-601 doesn’t show encased pipe chase. Does this key note apply?
Response: Pipe chase shall be encased at roof penetration. See Drawing Revisions Sheet MP-102 Key Note 5.
Q3. General Note 1 on Sheet MP101 indicates demo work in the vicinity of the kitchen needs to be done between 8:00PM & 4:00AM. Can all other work that doesn’t impact the kitchen be done during normal work hours?
Response: Sheet MP-101 General Note 1 also indicates that work in linen areas to take place between 8:00PM and 4:00AM. All other work that does not impact the kitchen or linen areas may be done during normal work hours. Utility outage times and coordination are to comply with the specifications.
Q4. Section 02 82 13.13 part 1.1.2 specifies asbestos abatement of 40 linear feet of pipe insulation and replacement of an unknown quantity of dielectric unions. What is the location of the abatement? How many unions need to be replaced?
Response: Insulation to be abated is above ceilings and on penetrations through the roof. Assume 15 unions for replacement. Replace dielectric unions with ball valves and insulation according to the specifications.
Q5. Is the commissioning agent and all associated costs being supplied by the VA?
Response: Contractor is responsible for startup, manufacturer commissioning and training as per the specifications. The VA may hire an external commissioning agent for 3rd party services.
Q6. Key note 6 on plan sheet MP-101 is vague. How is the contractor to know if the existing branch valves are functional?
Response: Branch valves are assumed to be functional, comment has been edited. See Drawing Revisions Sheet MP-101 Key Note 6.
Q7. Key note 1 on plan sheet MP-102 is vague. The contractor should not decide if heat tracing is required. Please clarify the scope of work and if heat tracing is required provide a material specification.
Response: Heat tracing reference removed from drawings, heat tracing is not required. See Drawing Revisions Sheet MP-102 Key Note 1.
Q8. Key note 6 on plan sheet MP-102. Please clarify material type for bird screen (stainless steel or galvanized).
Response: Bird screens to be stainless steel. See Drawing Revisions Sheet MP-102 Key Note 6 and Sheet M-601 Detail 8 Note 6.
Q9. Plan sheet M-601, detail 6 & 7, please confirm all the existing hand valves are being reused for the hot water and chilled water coils. Are the valves located below the roof level near the pipe penetration to the roof?
Response: Existing hand valves will be reused. See Sheet MP-101 for location of existing branch shutoff valves located below roof. See Sheet MP-101 Key Note 3 for details on chilled water piping.
Q10. Plan sheet M-604, detail 5. Are roof rails acceptable to use for the support of the refrigeration piping?
Response: Roof rails are not acceptable. Plan sheet M-604 does not exist. See M-601 detail 10 for supporting piping on roof.
Q11. Are roof supports as manufactured by PHP (see attached) acceptable for the roof ductwork?
Response: Ductwork support detail added to drawings. See Drawing Revisions Sheet M-601 Detail 13. Specific manufacturer products will not be reviewed for approval at this time.
Q12. Please clarify the scope of work associated with duct testing as there is minimal supply air ductwork. Please be specific what the VA needs tested.
Response: Refer to Specification Sections 23 31 00 HVAC Ducts and Casings, and Section 23 05 93 Testing, Adjusting, and Balancing for HVAC.
Q13. As York is listed as the brand name for the HVAC we assume if there are items in specification section 23 74 13, 23 81 00 and 23 82 16 that are non-standard with their manufacturing process for the HVAC equipment that the York will be waived of these requirements. Please advise.
Response: See Specification Revisions, removing inconsistencies between the specifications and the brand name or equal product identified. The AHU will not be waived of contract requirements outlined in the project Specifications.
Q14. Key Note 4 on Sheet MH-103 says, “Provide unit lightning protection to existing rooftop ground system”. What are the requirements of the unit lightning protection? The Facility Lightning Protection specification section is not included in the bid documents and the plans do not provide information on the existing rooftop ground system.
Response: See Specification Revisions, Specification Section 26 41 00 Facility Lightning Protection added to contract.
Q15. Section 23 05 11, Plan sheet M-601, detail 6 & 7. Is it acceptable to use pipe supports/equipment rails in lieu of pipe stands? Please advise.
Response: Equipment rails are not acceptable. See M-601 detail 10 for supporting piping on roof.
Q16. What are the working hours for the work inside the building and outside the building?
Response: Per Sheet MP-101 General Note 1, work must be done between 8:00pm and 4:00am if the location of work is in the vicinity of kitchen or linen equipment, supplies, or areas. Utility outage times and coordination are to comply with the specifications.
Q17. Specification section 02 82 13.13 subsection 1.1.2 B indicates “Removal, clean-up and disposal of ACM piping and fittings and asbestos contaminated elements in an appropriate regulated area in the following approximate quantities: 40 linear feet of <2" diameter pipe insulation” Are these pipes located in the ceiling inside the building? Drawings do not indicate such work. Please clarify.
Response: Insulation to be abated is above ceilings and on penetrations through the roof. Replace insulation according to the specifications.
Q18. Specification section 02 82 13.13 subsection 1.1.2 B indicates” Replace dielectric unions during abatement process. Allow for 15% of the dielectric unions to be replaced to be changed after demo and after full abatement of the area.” Please quantify the number of dielectric unions needed to be replaced.
Response: Assume 15 dielectric unions.
Q19. Project manual specification have included the specification section 09 91 00 and 22 05 33. We did not find any work concerning these specification section. Please clarify the scope of work concerning these specification sections.
Response: Specification 09 91 00 details pipe identification standards as noted on Sheet MP-102 Key Note 1. Specification 22 05 33 is not required, and reference to it has been removed, see Drawing Revisions Sheet MP-102 Key Note 1 and Specifications Revisions.
Q20. Specification Section 07 22 00-6 subsection 2.5 D & E, can ASTM C1177 be added to section E and could section D be cleared up by removing C1396 (drywall) board?
Response: The above changes are acceptable, see Specification Revisions for modifications to Specification Section 07 22 00 Paragraphs D and E.
See attached document: Amend 0003 Specifications.
See attached document: Amend 0003 Drawings.
See attached document: Amend 0003 Brand Name or Equal Products.
36C252-18-B-1082 Amendment 0003