This document is a Solicitation, Offer, and Award (SF 1442) for a Department of Veterans Affairs (VA) construction contract for the Electronic Health Record Modernization (EHRM) Installation at the John D. Dingell VA Medical Center in Detroit, Michigan. The solicitation is a 100% set-aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSB) under NAICS code 238210, with a small business size standard of $19 Million. The project involves installing 24 normal power outlets and 85 data drops to support Electronic Health Record (EHR) equipment deployment, with work to be completed after hours and on weekends. The contract magnitude is between $100,000 and $250,000, with a performance period of 10 calendar days for commencement and 75 calendar days for completion after receiving notice to proceed.

The solicitation includes detailed requirements for data drop installations, including using Category 6A cabling compliant with healthcare facility telecommunications infrastructure standards, specific installation and testing protocols, and comprehensive documentation requirements. Contractors must submit various documents with their proposal, including annual representations and certifications, a VA Notice of Limitations on Subcontracting certification, and comply with specific training, security, and privacy regulations. Proposals must be emailed to the Contract Specialist Christina Shockey by the specified due date, and the contract will be awarded to a certified SDVOSB listed in the SBA certification database.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C25025R0088 – EHRM Installation of DDPo2 553-25-706 – Detroit VAMC, MI

1. SOLICITATION NUMBER 2. TYPE OF SOLICITATION 3. DATE ISSUED PAGE OF PAGES

4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER

7. ISSUED BY CODE 8. ADDRESS OFFER TO

a. NAME b. EMAIL ADDRESS:

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014) STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

EMAIL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within ____________ calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES NO

a. Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b. An offer guarantee is, is not required.

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

1 69

36C25025R0088

X

06/04/2025

553-25-3-3508-0054

553-25-706

36C250

Department of Veterans Affairs Network Contracting Office (NCO) 10 24 Frank Lloyd Wright Dr.

Lobby M2200 Ann Arbor MI 48105

Christina Shockey Christina.Shockey@va.gov

Shockey, Christina Christina.Shockey@va.gov

Project entitled EHRM Installation of DDPo2, project number 553-25-706 which requires the contractor to furnish all labor, materials, supervision, equipment, and all other necessary resources to fully complete the work identified in the contract specifications and drawings.

This acquisition is a 100% set-aside for Service-Disabled Veteran Owned Small Businesses with the ability to accomplish the work via North American Industry Classification System (NAICS) code 238210, $19 Million Small Business Size Standard

Place of Performance is at the John D. Dingell VA Medical Center, Detroit, Michigan 48201.

Magnitude of Construction is Between $100,000.00 and $250,000.00.

EMAIL PROPOSALS TO CONTRACT SPECIALIST CHRISTINA SHOCKEY AT CHRISTINA.SHOCKEY@VA.GOV

10 75

X 52.211-10

EDT

mailto:Christina.Shockey@va.gov

14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO 10 U.S.C. 2304(c)( ) 41 U.S.C. 3304(a) ( )

26. ADMINISTERED BY 27. PAYMENT WILL BE MADE BY

PHONE: FAX:

28. NEGOTIATED AGREEMENT 29. AWARD Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code)

(Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

(Type or print)

(4 copies unless otherwise specified)

(Type or print) (Type or print)

(Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror)

(To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

OFFER AMOUNT ENTIRE PROJECT: $

Offeror Email Address:

Offeror Federal Tax ID:

Offeror Unique Entity ID:

36C250

Department of Veterans Affairs Network Contracting Office 10 6150 Oak Tree Blvd.

Suite 300 Ann Arbor OH 44131

Department of Veterans Affairs Financial Management System PO Box 149971 Austin TX 78714-9971 877-353-9791 512-460-5540

KYLE LIPPER

Table of Contents

PART I - THE SCHEDULE

SECTION A - SOLICITATION/CONTRACT FORM

A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)

A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION,

ALTERATION, OR REPAIR)– BACK

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

2.1 52.201-1 ACQUISITION 360: VOLUNTARY SURVEY (SEP 2023)

2.2 52.216-1 TYPE OF CONTRACT (APR 1984)

2.3 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE

OF THE WORK (MAY 2014)

2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION

MATERIALS (MAY 2014)

2.5 52.228-1 BID GUARANTEE (SEP 1996)

2.6 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE)

(FEB 2021)

2.7 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB

1998)

2.8 VAAR 852.239-75 INFORMATION AND COMMUNICATION TECHNOLOGY

ACCESSIBILITY NOTICE (FEB 2023)

REPRESENTATIONS AND CERTIFICATIONS

3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2025)

(DEVIATION FEB 2025)

3.2 52.204-29 FEDERAL ACQUISITION SUPPLY CHAIN SECURITY ACT ORDERS—

REPRESENTATION AND DISCLOSURES (DEC 2023)

GENERAL CONDITIONS

4.1 52.204-30 FEDERAL ACQUISITION SUPPLY CHAIN SECURITY ACT ORDERS—

PROHIBITION (DEC 2023)

4.2 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK

(APR 1984) ALTERNATE I (APR 1984)

4.3 52.219-28 POSTAWARD SMALL BUSINESS PROGRAM REREPRESENTATION

(JAN 2025)

4.4 52.223-21 FOAMS (MAY 2024)

4.5 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022)

4.6 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

4.7 SUPPLEMENTAL INSURANCE REQUIREMENTS

4.8 VAAR 852.201-70 CONTRACTING OFFICER'S REPRESENTATIVE (DEC 2022)

4.9 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)

4.10 VAAR 852.204-70 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR

PERSONNEL (MAY 2020)

4.11 VAAR 852.211-72 TECHNICAL INDUSTRY STANDARDS (NOV 2018)

4.12 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED

SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (JAN 2023)

(DEVIATION)

4.13 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—

CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (JAN 2023)

(DEVIATION)

4.14 VAAR 852.232-71 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION

CONTRACTS (INCLUDING NAS– CPM) (NOV 2018)

4.15 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV

2018)

4.16 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION

(APR 2019)

4.17 VAAR 852.236-72 PERFORMANCE OF WORK BY THE CONTRACTOR (APR

2019)

4.18 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)

4.19 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)

4.20 VAAR 852.239-76 INFORMATION AND COMMUNICATION TECHNOLOGY

ACCESSIBILITY (FEB 2023)

4.21 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020) ..56

4.22 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT

(SEP 2019)

4.23 VAAR 852.246-75 WARRANTY OF CONSTRUCTION—GUARANTEE PERIOD

SERVICES (OCT 2018)

4.24 IT CONTRACT SECURITY

IMPORTANT OFFEROR INFORMATION

OFFEROR SUBMISSION: The following documents shall be included with the proposal:

(1) An original, completed, signed and dated SF 1442 Offer page (‘wet ink signature’).

(a) The lump sum proposal amount for the entire project is entered in block 17 of the SF1442 Offer page.

Failure to provide a properly completed and signed original offer could result in the proposal being determined non-responsive and rejected. EMAIL IS REQUIRED.

(2) Acknowledgment of all amendments that are issued by one of the following methods:

a)Completing block 19 of the SF1442 by entering and acknowledging all issued amendments or;

b)Completing blocks 15a, b, and c of each issued amendment and including with the proposal submission.

Failure to acknowledge an Amendment or Amendments could (case dependent) result in the offer being determined non-responsive and rejected.

(3) Completed Annual Representations and Certifications (FAR 52.204-8) (JAN 2025)(DEVIATION).

It is highly recommended that offerors complete their Representations and Certifications online at

WWW.SAM.GOV.

(4) Completed VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—

CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (JAN 2023)

(DEVIATION). (see solicitation attachments for certification document to complete and return with offer)

Failure to provide a correctly completed certification cited in paragraph (4) above shall result in the proposal/offer being determined non-responsive and shall be rejected.

(5) Any and all other documentation required by the solicitation.

Offerors are wholly responsible for insuring and verifying their offer and all required proposal documents are received at the office designated in block 8 of the SF 1442 by the date and time specified in block 13a.

of the SF 1442 (subject to amendment).

http://www.sam.gov/

ADDITIONAL SOLICITATION INFORMATION

PROJECT No. 553-25-706

EHRM INSTALLATION OF DDPO2-DETROIT, MI

SCOPE OF WORK STATEMENT:

1. GENERAL INTENT:

The Contractor shall furnish all labor, materials and equipment to prepare the site identified at the Detroit VA Medical Center for the installation of additional data drops, power outlets and equipment bracing for equipment deployment of the Electronic Health Record (EHR).

2. STATEMENT OF WORK:

The selected contractor shall provide and install 24 normal power outlets, 85 data drops to support EHR equipment deployment at the Detroit VA Medical Center as shown and described in the project drawings and specifications. Work shall be completed after hours and on weekends.

2.1 Data Drops

2.1.1 Install Cat 6A cabling and data drops in accordance with attachments, location drawings, and specifications.

2.1.2 Horizontal cabling shall be Category 6A (Cat6A) (ANSI/TIA-1179 Healthcare Facility

Telecommunications Infrastructure).

2.1.3 Installation shall be compliant with the BICSI standards (ANSI/NECA/BICSI 568, Standard for Installing Commercial Building Telecommunications Cabling and ANSI/TIA-1179-A Healthcare Facility Telecommunications Infrastructure for new installations).

2.1.3.1 New cable installations additionally shall be compliant with TIA 568.2-D, TIA

TSB-184-A, and NFPA-70 Section 725.144 to prevent PoE heat accumulation. Provide certification reports to the COR.

2.1.3.2 Alternatively, new UTP cabling shall carry a UL listed "LP" (Limited Power) rating.

2.1.3.3 Cat6A cable shall be terminated to identified RJ-45 patch panel in IT closet and

CAT6A RJ-45 jack at wall plate and labeled at both ends.

2.1.3.4 Use a cable analyzer to determine cable length (max cable length

90M/295 linear feet) and certify that cable meets or exceeds TIA-EIA-568-C.2.

2.1.3.5 Cables shall be installed in continuous lengths from origin to destination, no splices with a 1’ service loop.

2.1.5 Cable management shall be implemented for all patch cables in accordance with Infrastructure Standard for Telecommunications Spaces (latest version on the TIL), ensuring proper bend radius, bundling, airflow, support and labeling.

2.1.6 Copper structured cabling shall be certified as meeting or exceeding TIA-EIA-568.1-D

(max fixed cable length 90M/295 linear feet) independent of media type.

2.1.7 Use existing raceways as much as possible. Cable shall be installed in accordance with manufacturer’s recommendations and best industry practices. Existing raceways shall not be filled greater than the NEC maximum fill for the raceway type.

2.1.8 Install and label outlets, faceplates and patch panels in accordance with specifications and VAMC standard. Patch panel labels shall include room number, outlet number, and jack number. The Contractor shall submit a labeling plan for outlets, faceplates and patch panels to the COR for approval prior to initiating installation. All label printing shall be machine generated.

2.1.9 Confirm locations, including installation height, with COR.

2.1.10 Patch and finish disturbed surfaces to match existing.

2.1.11 All new cable installation shall be tested and certified. Provide the certification report to

COR.

2.2 Power Outlets

2.2.1 Install conduit and conductors in accordance with attachments, location drawings, and specifications.

2.2.2 Use existing raceways as much as possible. Conductors shall be installed in accordance with manufacturer’s recommendations and best industry practices. Existing raceways shall not be filled greater than the NEC maximum fill for the raceway type.

2.1.8 Install and label outlets, faceplates and power panels in accordance with specifications and VAMC standard. The Contractor shall submit a labeling plan for outlets, faceplates and power panels to the COR for approval prior to initiating installation. All label printing shall be machine generated.

2.2.3 Confirm locations, including installation height, with COR.

2.2.4 Patch and finish disturbed surfaces to match existing.

2.3 Equipment and Mounting Hardware

2.3.1 List of equipment and mounting hardware requiring installation is Government-

Furnished. Locations shall be verified with COR prior to installation.

2.3.2 Install units in accordance with manufacturer’s installation instructions.

https://www.cfm.va.gov/til/dguide/OIT-InfrastrucStdTelecomSpaces-v4-0.pdf

2.3.3 Patch and finish disturbed surfaces to match existing.

3. PERIOD OF PERFORMANCE:

3.1 Work timelines and completion progress shall be communicated to the COR for tracking purposes.

3.2 Work described in Section 2 shall be completed within 120 days following Notice to Proceed.

4. SPECIFICATIONS:

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 01 32 16.15 Project Schedule 01 33 23 Shop Drawings, Product Data, and Samples 01 35 26 Safety Requirements 01 74 19 Construction Waste Management

DIVISION 02 – EXISTING CONDITIONS

02 41 00 Demolition

DIVISION 07 – THERMAL AND MOISTURE PROTECTION

07 84 00 Firestopping

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 26 05 19 Low-Voltage Electrical Power Conductors and Cables 26 05 26 Grounding and Bonding for Electrical Systems 26 05 33 Raceway and Boxes for Electrical Systems 26 27 26 Wiring Devices

DIVISION 27 – COMMUNICATIONS

27 05 11 Requirements for Communications Installations 27 05 33 Raceways and Boxes for Communications Systems 27 15 00 Communications Structured Cabling

5. SUBMITTALS:

5.1 In addition to submittals required by specifications, the contractor shall submit the following submittals for review:

5.1.1 Product data and sample of cable.

5.1.2 As-built drawings for all data locations and labels. The Contractor shall provide the central drawing set to the Owner at the end of the project. The marked-up drawing set will accurately depict the as-built status of the system including termination locations, cable routing, and all administration labeling for the cabling system. In addition, a narrative will be provided that describes any areas of difficulty encountered during the installation that could potentially cause problems to the telecommunications system.

5.1.3 As-built drawings for new power locations. Include one line diagram depicting which circuits feed new outlets and panel schedules for panels feeding new outlet locations.

5.1.4 Certification report. All testing documents shall reflect the appropriate labeling scheme.

5.1.5 Warranties of installation and cabling system. The Contractor shall provide a system warranty covering the installed cabling system against defects in workmanship, components, and performance, and covering follow-on support after project completion.

The above paragraphs constitute a basic outline of the work to be accomplished and in no way comprises all the details for this project. Contractor shall refer to drawings and specifications for comprehensive construction requirements.

End of SOW

WAGE DETERMINATION: Department of Labor General Decision Number MI2050100 dated 06/13/2025 is included as an attachment to solicitation and is applicable to any resultant contract. If necessary, subsequent revisions will be posted to the solicitation via amendment prior to DUE DATE.

Revision may also be applicable prior to any contract award. Wage decisions are available at Wage Determinations Online (WDOL) at https://sam.gov/content/wage-determinations .

REQUESTS FOR INFORMATION (RFI): To obtain clarifications and/or additional information concerning the solicitation requirements, specifications and/or drawings, or any other issue pertaining to the Request For Proposal (RFP), submit a written RFI utilizing the RFI Form attached to this solicitation and send via email to the attention of Contract Specialist Christina.Shockey@va.gov. The subject line of the email must read ‘RFI # – 36C25025R0088 Project 553-25-706 EHRM Installation of DDPO2. RFIs related to the project technical documents must be specific identifying section, paragraph and page no. of the specifications or cite the drawing number and must be in question format. RFIs related to the solicitation or other related documents shall refer to the specific provision, clause, etc. All RFIs submitted shall include the solicitation number and title, contractor name, city, state, telephone, email address, date submitted, and the RFI question(s). RFI responses will be posted to the original solicitation located at in amendment format. Deadline for submission of RFIs for this solicitation is July 8, 2025. No questions will be answered after this date unless determined to be in the best interest of the Government as deemed by the Contracting Officer. Telephone requests for information will not be accepted nor returned.

TYPE OF SET-ASIDE

THIS SOLICITATION IS A TOTAL SET-ASIDE FOR

SERVICE-DISABLED VETERAN OWNED SMALL BUSINESSES (SDVOSB)

SEE VAAR CLAUSE 852.219-73 FOR ELIGIBILITY REQUIREMENTS.

DATABASE REGISTRATION INFORMATION

SYSTEM FOR AWARD MANAGEMENT (SAM) REGISTRATION: The System for Award Management (SAM) website located at https://sam.gov is the Official U.S. Government system that https://sam.gov/content/wage-determinations mailto:Christina.Shockey@va.gov https://sam.gov/ consolidated the capabilities of the Central Contractor Registration (CCR including FedReg), Online Representations and Certifications Application (ORCA), and the Excluded Parties List System (EPLS).

Federal Acquisition Regulations require that federal contractors wishing to do business with the Government and bid on work shall have an active registration in SAM. The offeror shall have an active registration in SAM at the time of offer submission otherwise the Contracting Officer shall deem the offeror’s proposal non-responsive to the solicitation requirements (see FAR 52.204-7 for complete SAM registration requirements).

THE EXCLUDED PARTIES LIST SYSTEM (EPLS): To ensure that the individuals or businesses providing services under the contract have not engaged in fraud or abuse regarding Sections 1128 and 1128A of the Social Security Act regarding federal health care programs, the contractor is required to check the Excluded Parties List System (EPLS) located at https://sam.gov for each person or business providing services under this contract. During the performance of this contract the Contractor is prohibited from using any individual or business listed on the List of Excluded Individuals/Entities.

VETS-4212 REPORTING REQUIREMENT: Contractors are required to submit a required annual Form VETS-4212, Federal Contractor Veterans' Employment Report in all cases where the contractor or subcontractor has received an award of $150,000 or more in any fiscal year. Contracting Officers are prohibited from awarding a contract to a contractor that has not submitted a required VETS-4212 Report with respect to the preceding fiscal year if the contractor was subject to the reporting requirement of 38 U.S.C. 4212(d). Submit this report as soon as possible, if not already submitted, to avoid delays in the contract award process. For more information on this requirement and/or for completing the web-based reporting form, visit the following website https://www.dol.gov/agencies/vets/programs/vets4212. See FAR provision 52.222-38, Compliance with Veterans' Employment Reporting Requirements (FEB 2016) under the Representations, Certifications and Other Statements of Offerors, and FAR clause 52.222-37, Employment Reports on Veterans (JUN 2020) found in the General Conditions section of the solicitation.

BONDING INFORMATION

PERFORMANCE AND PAYMENT BONDS: In accordance with Contract Clause 52.228-15, and FAR 28.102, Contractors are reminded that any amount awarded over $35,000.00 shall require a Payment Bond (SF 25A), and awards exceeding $150,000.00 shall require both Payment and Performance Bonds (SF 25). Payment and Performance bonds are due no later than 10 days after notification of award.

Bonds must be provided with original ‘wet ink’ signatures - no white-outs or other corrections are allowable. Copies and facsimiles of bonds are not acceptable.

SECURITY

BACKGROUND INVESTIGATIONS: All contractor employees are subject to the same level of investigation as VA employees who have access to VA Sensitive Information. The level of background investigation is commensurate with the level of access needed to perform the statement of work. This requirement is also applicable to all subcontractor personnel requiring the same level of access.

Levels and associated types of Background Investigations:

https://sam.gov/ https://www.dol.gov/agencies/vets/programs/vets4212

• If the project requires that workers have only limited physical access to the VA facility for a period of one year or less, a local flash badge with fingerprint check is issued.

• If the project requires that workers require un-supervised, logical and/or physical access for 180 consecutive or aggregate days in a 365-day period, over a 3 year period, a background investigation may be required (Special Agency Check (SAC)) which must be completed prior to being allowed access.

• If the project requires that workers have access to a VA Network (such as the Building Management System) or un-supervised, full-time, logical, and/or restricted physical access for more than 6 months or more than 180 aggregate days in a one-year period, a background investigation is required (Special Agency Check and National Agency Check with Written Inquiries (NACI)) and access is not allowed until a favorable SAC completion.

All costs for SAC and NACI checks are borne by the contractor. The VA may at its discretion make deductions against the contract in order to recoup the investigation costs. At present, the VA is not charging contractors for background investigations, but this is subject to change.

MEDICAL CENTER ACCESS: Anyone participating in the site visit, or for any other reason that involves visiting the medical center related to this solicitation, must have a valid ID on their person and their vehicle must be properly registered and insured. Company owned vehicles must be clearly marked.

Visitors are prohibited from possessing weapons while on a federal installation (See 18 USC 930 – Possession of Firearms and Dangerous Weapons in Federal Facilities). Handheld cellphone usage or texting while driving is also prohibited. All VA Medical Centers and associated properties are Federal Property. Smoking and vaping is prohibited on medical center grounds including in vehicles or contractor owned/leased office or storage trailers.

PRIVACY TRAINING: All workers regardless of project length must take VA Privacy Training which will be coordinated after project award with the Contracting Officer’s Representative.

E-VERIFY SYSTEM (e-verify.gov): Companies awarded a contract in excess of $150,000 (except for those with performance periods of 120 calendar days or less) with the federal government shall enroll in E-Verify within 30 days of the contract award date. They shall also begin using the E-Verify system to confirm that all of their new hires and their employees directly working on federal contracts are authorized to legally work in the United States. E-Verify is an Internet-based system that allows an employer, using information reported on an employee's Form I-9, to determine the eligibility of that employee to work in the United States. There is no charge to employers to use E-Verify. (See FAR Clause 52.222-54).

OTHER IMPORTANT OFFEROR INFORMATION

This requirement is applicable to all subcontracting tiers, and prospective prime contractors are responsible for determining the responsibility of their prospective subcontractors.

CONFORMANCE WITH ENVIRONMENTAL MANAGEMENT SYSTEMS: The Contractor shall perform work under this contract consistent with the relevant policy and objectives identified in the agency, organizational, or facility Green Environmental Management System (GEMS) applicable for the contract. The Contractor shall perform work in a manner that conforms to all appropriate Environmental Management Programs and Operational Controls identified by the agency, organizational, or facility GEMS, and provide monitoring and measurement information as necessary for the organization to address environmental performance relative to the environmental, energy, and transportation management goals. In the event an environmental nonconformance or noncompliance associated with the contracted services is identified, the contractor shall take corrective and/or preventative actions. In the case of a noncompliance, the Contractor shall respond and take corrective action immediately. In the case of a nonconformance, the Contractor shall respond and take corrective action based on the time schedule established by the facility GEMS Coordinator. In addition, the Contractor shall ensure that their employees are aware of the roles and responsibilities identified by the environmental management system and how these requirements affect their work performed under this contract.

All on-site contractor personnel shall complete yearly EPA sponsored environmental training specified for the type of work conducted on-site. Upon inclusion in the contract, the Contracting Officer's Representative will verify that all contractor personnel have acquired EMS Awareness Training at their appropriate site or location.

REFERENCES TO VA ENGINEER, RESIDENT ENGINEER, SENIOR RESIDENT ENGINEER,

OR PROJECT MANAGER: Any reference contained within contract specifications and/or drawings to the “VA Engineer”, “Resident Engineer”, “Senior Resident Engineer”, “Project Manager”, or their abbreviations are to be read as meaning the “Contracting Officer’s Representative (COR)”.

PAYMENT FOR MATERIALS STORED OFF-SITE: Payment in advance of installation for materials stored off-site is at the discretion of the Contracting Officer after receipt of a request by the contractor. Extraordinary measures are required regarding the security, insurance, labeling, storage, etc. if payment is authorized for materials stored off-site. Payment for materials stored off-site is generally not authorized.

SCHEDULE OF MATERIAL SUBMITTALS: The submittals contemplated by FAR 52.236-5, Material and Workmanship are listed on the Schedule of Material Submittals in the Specifications, if provided. The schedule is for reference only – the selected contractor is responsible to provide all submittals required by the contract.

REVIEW REQUIRED REGISTRATION WITH CONTRACTOR PERFORMANCE

ASSESSMENT SYSTEM (CPARS)

(a) As prescribed in Federal Acquisition Regulation (FAR) Part 42.15, the Department of Veterans Affairs (VA) evaluates contractor past performance on all contracts that exceed $750,000 and shares those evaluations with other Federal Government contract specialists and procurement officials. The FAR requires that the contractor be provided an opportunity to comment on past performance evaluations prior to each report closing. To fulfill this requirement VA uses an online database, CPARS.

(b) Each contractor whose contract award is estimated to exceed $750,000 is required to register with CPARS database at the following web address: www.cpars.gov. Help in registering can be obtained by contacting Customer Support Desk at 207-438-1690. Registration should occur no later than thirty days after contract award and must be kept current should there be any change to the contractor's registered representative.

(c) For contracts with a period of one year or less, the contracting officer will perform a single evaluation when the contract is complete. For contracts exceeding one year, either by virtue of the original performance period or as modified, the contracting officer will evaluate the contractor's performance annually. Interim reports will be filed each year until the last year of the contract, when the final report will be completed. The report shall be assigned in CPARS to the contractor's designated representative for comment. The contractor representative will have thirty days to submit any comments and return.

(d) Failure to have a current registration in the CPARS database, or to re-assign the report to the VA contracting officer within those thirty days, will result in the Government's evaluation being placed on file in the database with a statement that the “contractor failed to respond.”

NATIONAL ARCHIVES AND RECORDS ADMINISTRATION RECORDS POLICIES

1. Contractor shall comply with all applicable records management laws and regulations, as well as National Archives and Records Administration (NARA) records policies, including but not limited to the Federal Records Act (44 U.S.C. chs. 21, 29, 31, 33), NARA regulations at 36 CFR Chapter XII Subchapter B, and those policies associated with the safeguarding of records covered by the Privacy Act of 1974 (5 U.S.C. 552a). These policies include the preservation of all records, regardless of form or characteristics, mode of transmission, or state of completion.

2. In accordance with 36 CFR 1222.32, all data created for Government use and delivered to, or falling under the legal control of, the Government are Federal records subject to the provisions of 44 U.S.C.

chapters 21, 29, 31, and 33, the Freedom of Information Act (FOIA) (5 U.S.C. 552), as amended, and the Privacy Act of 1974 (5 U.S.C. 552a), as amended and must be managed and scheduled for disposition only as permitted by statute or regulation.

3. In accordance with 36 CFR 1222.32, Contractor shall maintain all records created for Government use or created in the course of performing the contract and/or delivered to, or under the legal control of the Government and must be managed in accordance with Federal law. Electronic records and associated metadata must be accompanied by enough technical documentation to permit understanding and use of the records and data.

4. The Government and its contractors are responsible for preventing the alienation or unauthorized destruction of records, including all forms of mutilation. Records may not be removed from the legal custody of the Government or destroyed except for in accordance with the provisions of the agency records schedules and with the written concurrence of the Head of the Contracting Activity (HCA).

Willful and unlawful destruction, damage or alienation of Federal records is subject to the fines and penalties imposed by 18 U.S.C. 2701. In the event of any unlawful or accidental removal, defacing, alteration, or destruction of records, the contractor must report it to Government Contracting Officer. The agency must report promptly to NARA in accordance with 36 CFR 1230.

5. The Contractor shall immediately notify the appropriate Government Contracting Officer upon discovery of any inadvertent or unauthorized disclosures of information, data, documentary materials, records or equipment. Disclosure of non-public information is limited to authorized personnel with a need-to-know as described in the [contract vehicle]. The Contractor shall ensure that the appropriate personnel, administrative, technical, and physical safeguards are established to ensure the security and confidentiality of this information, data, documentary material, records and/or equipment is properly protected. The Contractor shall not remove material from Government facilities or systems, or facilities or systems operated or maintained on the Government’s behalf, without the express written permission of the Head of the Contracting Activity. When information, data, documentary material, records and/or equipment is no longer required, it shall be returned to the Government’s control or the Contractor must hold it until otherwise directed. Items returned to the Government shall be hand carried, mailed, emailed, or securely electronically transmitted to the Contracting Officer who awarded the contract. Destruction of records is EXPRESSLY PROHIBITED unless in accordance with Paragraph (4).

6. The Contractor is required to obtain the Contracting Officer's approval prior to engaging in any contractual relationship (sub-contractor) in support of this contract requiring the disclosure of information, documentary material and/or records generated under, or relating to, contracts. The Contractor (and any sub-contractor) is required to abide by all Government guidance for protecting sensitive, proprietary information, classified, and controlled unclassified information.

7. The Contractor shall only use Government IT equipment for purposes specifically tied to or authorized by the contract and in accordance with the project location VA Medical Center’s written policy.

8. The Contractor shall not create or maintain any records containing any non-public Government information that are not specifically tied to or authorized by the contract.

9. The Contractor shall not retain, use, sell, or disseminate copies of any deliverable that contains information covered by the Privacy Act of 1974 or that which is generally protected from public disclosure by an exemption to the Freedom of Information Act.

10. The Government owns the rights to all data and records produced as part of this contract. All deliverables under the contract are the property of the U.S. Government and shall have unlimited rights to use, dispose of, or disclose such data contained therein as it determines to be in the public interest. Any Contractor rights in the data or deliverables must be identified as required by FAR 52.227-11 through

FAR 52.227-20.

11. Training. All Contractor employees assigned to this contract who create, work with, or otherwise handle records are required to take VHA-provided records management training, Talent Management System (TMS) Item #3873736, Records Management for Records Officers and Liaisons. The Contractor is responsible for confirming training has been completed according to agency policies, including initial training and any annual or refresher training. All training shall be coordinate with the Contracting Officer’s Representative assigned to the contract.

OTHER IMPORTANT NOTICES

1. Contractor employees shall not be considered government employees for any purpose under this contract.

2. Contractor employees may be required to undergo Tuberculosis, Influenza, COVID, or other contagious disease screening prior to being authorized to work on-site. Screening is per individual VA Medical Center policy and shall be reviewed and discussed at the pre-construction conference.

3. Special Notes regarding FAR 52.229-3: Federal, State and Local Taxes:

Offerors are hereby notified that under Michigan Compiled Laws, Chapter 205 Taxation, Sections 205.54w & 205.54s, Michigan exempts from sales and use taxes personal property purchased by construction contractors that will be affixed to and made a structural part of a non-profit hospital. A “non-profit hospital” is defined as that portion of a building owned or operated by a governmental unit in which medical attention is provided, as well as that portion of real property necessary and related to a such a building. Therefore, VA has determined that the contractor’s purchase of such building and construction materials that will be affixed to or made a structural part of this particular

VA construction project is exempt from Michigan Sales or Use Tax. To take advantage of the tax exemption the successful offeror under this solicitation must complete a Michigan Sales and Use Tax Certificate of Exemption and keep on file as required by the Michigan Tax Code.

Notwithstanding FAR 52.229-3, all proposals received in response to this solicitation are presumed to reflect any tax benefit that may be realized upon the execution of the exemption certificate.

Link to the Michigan Sales and Use Tax Certificate of Exemption Form: 3372, Michigan Sales and Use Tax Certificate of Exemption

The VA will not field nor respond to any questions regarding the Michigan Sales and Use Tax Certification of Exemption nor any questions regarding Michigan Tax Code.

FAR DEVIATION FEB 2025 Instructions:

“System updates may lag policy updates. The System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in agency solicitations. Examples include 52.222-25, Affirmative Action Compliance, and paragraph (d) of 52.212-3, Offeror Representations and Certifications—Commercial Products and Commercial Services. Contracting officers will not consider these representations when making award decisions or enforce requirements. Entities are not required to, nor are they able to, update their entity registration to remove these representations in SAM.”

END OF IMPORTANT OFFEROR INFORMATION SECTION

https://www.michigan.gov/taxes/-/media/Project/Websites/taxes/Forms/2007/2007_3372.pdf?rev=f31828b81c1a4d1fb3144ca3f47ca7db&hash=79508DBC3FD550D40428001EA6E19C69 https://www.michigan.gov/taxes/-/media/Project/Websites/taxes/Forms/2007/2007_3372.pdf?rev=f31828b81c1a4d1fb3144ca3f47ca7db&hash=79508DBC3FD550D40428001EA6E19C69

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO

BIDDERS/OFFERORS

2.1 52.201-1 ACQUISITION 360: VOLUNTARY SURVEY (SEP 2023)

(a) All actual and potential offerors are encouraged to provide feedback on the preaward and debriefing processes, as applicable. Feedback may be provided to agencies up to 45 days after award. The feedback is anonymous, unless the participant self-identifies in the survey. Actual and potential offerors can participate in the survey by selecting the following link: https:// www.acquisition.gov/360.

(b) The Contracting Officer will not review the information provided until after contract award and will not consider it in the award decision. The survey is voluntary and does not convey any protections, rights, or grounds for protest. It creates a way for actual and potential offerors to provide the Government constructive feedback about the preaward and debriefing processes, as applicable, used for a specific acquisition.

(End of Clause)

2.2 52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.

(End of Provision)

2.3 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—

SECONDARY SITE OF THE WORK (MAY 2014)

(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of Provision)

2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—

CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

2.5 52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—

(1) To unsuccessful bidders as soon as practicable after the opening of bids; and

(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be percent of the bid price or , whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

(End of Provision)

2.6 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID

GUARANTEE) (FEB 2021)

(a) Offerors shall obtain from each person acting as an individual surety on a bid guarantee—

(1) A pledge of assets that meets the eligibility, valuation, and security requirements described in the Federal Acquisition Regulation (FAR) 28.203–1; and

(2) Standard Form 28, Affidavit of Individual Surety.

(b) The Offeror shall include with its offer the information required at paragraph (a) of this provision within the timeframe specified in the provision at FAR 52.228–1, Bid Guarantee, or as otherwise established by the Contracting Officer.

(c) The Contracting Officer may release the security interest on the individual surety’s assets in support of a bid guarantee based upon evidence that the offer supported by the individual surety will not result in contract award.

2.7 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY

REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

https://www.acquisition.gov/browse/index/far https://www.va.gov/oal/library/vaar/

FAR

Number

Title Date

52.204-7 SYSTEM FOR AWARD MANAGEMENT NOV 2024

52.204-16 COMMERCIAL AND GOVERNMENT ENTITY CODE

REPORTING

AUG 2020

52.204-22 ALTERNATIVE LINE ITEM PROPOSAL JAN 2017

52.215-1 INSTRUCTIONS TO OFFERORS—COMPETITIVE

ACQUISITION

NOV 2021

52.215-16 FACILITIES CAPITAL COST OF MONEY JUN 2003

52.236-28 PREPARATION OF PROPOSALS—CONSTRUCTION OCT 1997

2.8 VAAR 852.239-75 INFORMATION AND COMMUNICATION

TECHNOLOGY ACCESSIBILITY NOTICE (FEB 2023)

(a) Any offeror responding to this solicitation must comply with established VA Information and Communication Technology (ICT) (formerly Electronic and Information (EIT)) accessibility standards. Information about Section 508 is available at http://www.section508.va.gov/.

(b) The Section 508 accessibility standards applicable to this solicitation are stated in the clause at 852.239–75, Information and Communication Technology Accessibility. In order to facilitate the Government’s determination whether proposed ICT supplies meet applicable Section 508 accessibility standards, offerors must submit appropriate VA Section 508 Checklists, in accordance with the checklist completion instructions. The purpose of the checklists is to assist VA acquisition and program officials in determining whether proposed ICT supplies, or information, documentation and services conform to applicable Section 508 accessibility standards. The checklists allow offerors or developers to self-evaluate their supplies and document—in detail—whether they conform to a specific Section 508 accessibility standard, and any underway remediation efforts addressing conformance issues.

(c) Respondents to this solicitation must identify any exception to Section 508 requirements. If an offeror claims its supplies or services meet applicable Section 508 accessibility standards, http://www.section508.va.gov/ and it is later determined by the Government, i.e., after award of a contract or order, that supplies or services delivered do not conform to the described accessibility standards, remediation of the supplies or services to the level of conformance specified in the contract will be the responsibility of the Contractor at its expense.

REPRESENTATIONS AND CERTIFICATIONS

3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN

2025) (DEVIATION FEB 2025)

(a)(1) The North American Industry Classification…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .