36C25026Q1040_1.docx

DOCX document 17 KB Posted

Attached to
4420--SPS Steam Water Heater (Equipment) - VAMC Chillicothe
Solicitation number
36C25026Q1040
Issued by

About this file

This is an Amendment to a Previous Combined Solicitation posting questions received from potential vendors and the Government's responses regarding a steam water heater procurement. The solicitation number is 36C25026Q1040, issued by the Department of Veterans Affairs Network Contracting Office in Cleveland, Ohio, for delivery to the Chillicothe VAMC in Chillicothe, Ohio. The requirement is for two packaged steam water heaters with all wetted parts manufactured from 316 or 316L stainless steel on ASME-stamped units. The response deadline is September 23, 2026, at 3:00 PM Eastern Time. The Product Service Code is 4420 (Pumps and Compressors), and the NAICS Code is 333415 (Air Conditioning and Warm Air Heating Equipment Manufacturing).

Key clarifications provided by the Government address critical specification and technical questions. The tube bundle must be stainless steel, not copper, due to low conductivity water compatibility requirements. The Government will accept delivery schedules exceeding the standard 90-day performance period if the vendor identifies the lead time in its quotation. Control valves must be electronic with BAS interface functionality preferred but not required. Installation, rigging, setup, and commissioning labor are explicitly excluded from scope; the vendor's responsibility ends at delivery to Building 23 Warehouse with cut sheets and operation and maintenance manuals. The Government does not require a specific number of past performance references and will accept commercial references via CPARS. The existing equipment is an electric tank-based water heater being replaced, with physical constraints limited to passage through standard 84-inch double doors.

View the file

Other files

File Type Posted
OPPORTUNITIES-DESCRIPTION 02.docx DOCX document
36C25026Q1040.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Amendment to a Previous Combined Solicitation

Amendment to a Previous Combined Solicitation

SUBJECT*
SPS Steam Water Heater (Equipment) - VAMC Chillicothe

GENERAL INFORMATION

CONTRACTING OFFICE’S ZIP CODE*
44131-6969
SOLICITATION NUMBER*
36C25026Q1040
RESPONSE DATE/TIME/ZONE
09-23-2026 15:00 EASTERN TIME, NEW YORK, USA
ARCHIVE
30 DAYS AFTER THE RESPONSE DATE
RECOVERY ACT FUNDS
N
SET-ASIDE
SBA
PRODUCT SERVICE CODE*
4420
NAICS CODE*
333415
CONTRACTING OFFICE ADDRESS
Department of Veterans Affairs

Network Contracting Office 10 6100 Oak Tree Boulevard Suite 490 Cleveland OH 44131-6969

POINT OF CONTACT*

Contracting Officer Christopher A. Callihan christopher.callihan@va.gov 216-707-7736 N/A N/A

PLACE OF PERFORMANCE

ADDRESS
Department of Veterans Affairs

Chillicothe VAMC

17273 State Route 104

Chillicothe OH

POSTAL CODE
45601
COUNTRY
USA

ADDITIONAL INFORMATION

AGENCY’S URL

URL DESCRIPTION

AGENCY CONTACT’S EMAIL ADDRESS

EMAIL DESCRIPTION

DESCRIPTION

The purpose of this amendment is to post questions received and provide the facilities responses. The response date and time remain unchanged.

1. DELIVERY / LEAD TIME

SOW paragraph 4 requires all wetted parts to be 316 or 316L stainless steel on an ASME-stamped packaged unit. Manufacturers we have approached indicate this is a made-to-order build rather than a catalog item, with fabrication lead times that may exceed the 90-day period of performance stated in paragraph 11. Will the Government accept a quoted delivery beyond 90 days after receipt of order where the vendor identifies the lead time in its quotation, or should quoters plan to invoke the 14-day notification provision in paragraph 11 after award?

The facility has indicated either is sufficient. Please submit the most accurate delivery schedule possible with your quote.

2. SCOPE OF "ALL WETTED PARTS"

Please confirm whether the 316/316L stainless requirement extends to the heat exchanger tube bundle and circulating pump, or whether it applies to the vessel, connections and wetted piping with a copper-alloy tube bundle remaining acceptable. Several standard packaged units meet every other requirement in paragraph 4 but use a copper U-bend coil or bronze circulator.

Tube-bundle must be stainless steel, as copper piping is not compatible with low conductivity water.

3. CONTROL VALVE CONFIGURATION

Paragraph 4 requires 1/3-2/3 control valves. Please confirm whether the control valves are to be pneumatic, electronic, or vendor's choice, and whether any BAS/BMS interface or signal type is required at the control panel.

Electronic controls. BAS interface functionality (integration is not within scope) would be preferable but not required.

4. SOLICITATION NUMBER IN THE DESCRIPTION

The first paragraph of the attached OPPORTUNITIES-DESCRIPTION 02 document references "solicitation number 36C25026Q1034" and also refers to providing "a Reverse Osmosis system." The CLIN schedule, Statement of Work, title and submission instructions all reference 36C25026Q1040 and two packaged steam water heaters. Please confirm that 36C25026Q1040 is the correct solicitation number and that the Reverse Osmosis reference is not part of this requirement.

Reverse Osmosis system is a different requirement and not associated with 36C25026Q1040, which is limited to the two packaged steam water heaters.

Paragraph is hereby corrected to:

“The contractor shall include all labor, materials, equipment, and shipping to comply with all applicable federal, state, local laws and regulations, and VA regulations as required to provide two packaged steam water heaters as outline in the SOW/SCHEDULE.:

5. INSTALLATION

SOW paragraph 3 states that equipment install and testing are not within the scope of this contract. Please confirm that the vendor's responsibility ends at delivery to the Building 23 Warehouse with cut sheets and O&M manuals furnished, and that no rigging, setting, startup or commissioning labor is to be priced.

Correct, install and setup is not required.

6. PAST PERFORMANCE

Please confirm the number of past performance references desired, the relevancy period, and whether commercial references are acceptable alongside federal references.

Past performance can be reviewed via CPARS. There is no specific number of references required.

7. EXISTING EQUIPMENT

If available, please provide the make and model of the existing end-of-life units being replaced, and any connection sizes or physical envelope constraints in the Sterile Processing mechanical space, so that quoted units can be confirmed as a fit.

Current system is an electric tank-based water heater at end of life. New water heater is being installed parallel to existing prior to cut over. Physical constraints limited to passage through standard height (84 inch) double door.

*= Required Field
Amendment to a Previous Combined Solicitation

Page 1 of

Amendment to a Previous Combined Solicitation

File details come from the government source that posted it. Updated .