About this file

This is a Lockout-Tagout (LOTO) Procedure document for Elevator P1 (equipment reference 538 EE4594) located in Building 1, Attic area, developed by the U.S. Department of Veterans Affairs. The procedure was created on August 7, 2024, and complies with 29 CFR 1910.147 OSHA regulations.

The document identifies three isolation points requiring lockout and tagout: G-1 (gravity isolation on the unit itself), E-1 (208V electrical breaker in the elevator equipment room), and E-2 (120V electrical breaker in the elevator equipment room). For the gravity isolation point, the unit must be lowered to the bottom level and visually verified. For both electrical isolation points, the breaker switches must be turned off and locked out, with voltage confirmed at zero using a meter. The procedure emphasizes that a machine stop must always be performed before locking out disconnects and that an open guard is not equivalent to a lockout. The document includes detailed shutdown and lockout sequences with seven steps, followed by five restoration steps to return equipment to normal operation. Critical enforcement notes warn that failure to properly follow lockout-tagout procedures may result in disciplinary action, and any machine modifications must be documented and approved by the safety department.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Developed by Reviewed by Revised by

DW

Equipment Name:

Area: Attic Revn: 0 Date: 8-7-2024

ID Device

G-1 None

E-1 Breaker device

E-2 Breaker device

LOCKOUT-TAGOUT

PROCEDURE

Elevator P1 (942058) Equip. Ref.: 538 EE4594

Building: 1

Isolation Points to be

Locked and Tagged

CAUTION

Origin Date: 8-7-2024

ALWAYS PERFORM A MACHINE STOP BEFORE LOCKING OUT DISCONNECTS

Source Location Method Check

Gravity Isolation point located on unit. Lower unit to bottom level.

Visually verify unit is at bottom level.

Electrical

208V

Isolation point located in elevator equipment room.

Switch breaker switch to off. Lock out.

Confirm 0 voltage with meter. Attempt restart at CP-1.

Electrical

120V

Isolation point located in elevator equipment room.

Switch breaker switch to off. Lock out.

Confirm 0 voltage with meter. Verify cab electronics are off.

AN OPEN GUARD IS NOT THE SAME AS A LOCKOUT

Any machine modifications must be shown in procedure. Contact safety department to update procedure.

Safety Depends on You!

! Note:

G-1

CP-1

E-1

E-2

Equipment Specific Lockout/Tagout Procedure

29 CFR 1910.147

Shutdown and Lockout Sequence