36C25025R0068 0002.docx
DOCX document 24 KB Posted
- Solicitation number
- 36C25025R0068
About this file
This document is an Amendment to a Solicitation/Modification of Contract for a Job Order Contract (JOC) at the Cincinnati Veterans Affairs Medical Center (VAMC). The amendment, issued by the Department of Veterans Affairs Network Contracting Office, provides clarifications through a series of questions and answers related to the solicitation (36C25025R0068). Key clarifications include guidance on project management roles, with confirmation that the Project Manager may serve as Quality Control Manager and/or Safety Manager, but the Superintendent cannot simultaneously serve as Quality Control Manager or Safety Manager. The amendment also addresses tax exemption, noting that task orders for work at the Cincinnati VAMC location will be tax-exempt, while work at the Fort Thomas location may not be. The amendment does not change the proposal due date or time and serves primarily to provide additional context and answer contractor inquiries about the Job Order Contract's specific requirements and expectations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25025R0068 0001.docx | DOCX document | |
| Attachment II - Past Performance Questionnaire.pdf | ||
| Attachment I - DBA WD.pdf | ||
| Attachment IV - VAAR 852.219-75.pdf | ||
| Attachment III - JA RSMeans.pdf | ||
| 36C25025R0068_1.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7.
ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF
PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO:
Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED
STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF
CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF
SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 06-23 -2025 539-25-4-6074-0002 539-24-500 36C250 Department of Veterans Affairs Network Contracting Office (NCO) 10 260 E. University Avenue Cincinnati OH 45219 36C250 Department of Veterans Affairs Network Contracting Office (NCO) 10 260 E. University Avenue Cincinnati OH 45219 To all Offerors/Bidders
36C25025R0068 05-21-2025
X X X N/A
539-3650162-6074-854200-3223 23NRNR001
The purpose of this amendment is to provide answers for questions received. Those are located on page two. Not other items are affected by this amendment and the proposal due date/time has not changed.
Luke A. Turner Contracting Officer
VA-VHA-RPOC-2024-0076
Questions and Answers Question - Section F states in part: "Supervising construction projects similar to those required by this contract (i.e. more than 100 projects working simultaneously.") It is our understanding and practice that Superintendents are responsible for only one project at a time. We would have concerns with the Superintendent being responsible for more than one (1) project at a time, with the possible exceptions of certain specific situations, i.e. two smaller projects operating in nearby physical proximity. Is it the intent to have a Superintendent responsible for multiple projects at one time?
This section pertains to the Project Manager, not the Superintendent.
Question - Will this project be sales tax exempt?
Task Orders issued under the contract for work done at the Cincinnati VAMC location will be tax exempt. If orders are placed for work to be completed at the Fort Thomas location, those will not be exempt. These matters are dependent on state law(s). They cannot be guarantee under the contract throughout.
Question - Sections G & I reference dual roles which may be held by the Project Manager, allowing the Project Manager to hold multiple roles, either Project Manager and QCM roles or Project Manager and Safety Manager. It is our normal practice for the Project Manager also function as the QCM and the Superintendent to also function as the Safety Manager. Is this acceptable? If not, it would be necessary to account for an additional team member on each project which would increase the project costs.
The Project Manager may serve as the Quality Control Manager and/or the Safety Manager roles, although these indicate the individual must be present on project sites, if that is not possible, then yes, a separate individual should be staffed to cover these roles. The superintendent may not function as the QCM or Safety Manager as this has been an ineffective and detrimental practice.
***END OF Q&A/AMENDMENT***